← Back to search

Huntstown, North Road, Finglas, Dublin 11

GRANT PERMISSION

Planning application FW18A/0159

Dublin - Fingal County Council

Proposed Development

Planning Permission is sought for an increase in the annual volume of

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Oct 2018

  2. Decision: GRANT PERMISSION

    13 Dec 2018

  3. Decision due

    20 Dec 2018

  4. Grant issued

    30 Jan 2019

Application Details

Location
Huntstown, North Road, Finglas, Dublin 11
Applicant
N/A
Application Type
Permission
Planning Authority
Fingal County Council
Site Area
1820 ha

Timeline

Registration Date
26 October 2018
Status
Decision made
Decision
GRANT PERMISSION
Decision Date
13 December 2018
Grant Date
30 January 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

30m
FW23A/0276GRANT PERMISSION14 Sept 2023

Planning Permission to erect 1,795 m2 or 371.68 Kwp of photovoltaic p

Huntstown Power Station, Johnstown, Dublin, D11N28R

51m
FW24A/0082GRANT PERMISSION1 Mar 2024

The development will consist of upgrade works abd alterations to an ex

Lands at Huntstown BioEnergy Plant, Huntstown, Dublin 11, D11 N28R

72m
FW22A/0258GRANT PERMISSION20 Feb 2023

The development comprises the construction and operation of 3 no weigh

Huntstown and Cappogue Townlands, North Road, Finglas, Dublin 11

115m
FW18A/0082GRANT PERMISSION12 Jun 2018

The development is a wastewater treatment plant comprising a 3m high b

Huntstown, North Road, Finglas, Dublin 11

116m
FW13A/0089GRANT PERMISSION15 Aug 2013

Permission for the construction of a Renewable Bio Energy Plant

Site within Roadstone Wood's Huntstown Quarry, Huntstown, North Rd, Fi

286m
FW19A/0015GRANT PERMISSION4 Feb 2019

The development will consist of a Battery Energy Storage System (BESS)

Huntstown Power Station, Huntstown Quarry, Finglas, Dublin, D11 N407

328m
FW21A/0151GRANT PERMISSION24 Feb 2022

Demolition of 2 no. existing residential dwellings and ancillary

Lands adjacent to Huntstown Power Station, North Road, Finglas, Dublin

334m
FW24A/0400EGRANT PERMISSION2 Oct 2024

1) A Battery Energy Storage System facility to include up to 85 no. co

Huntstown Power Station, In the townlands of Hunstown and Johnstown, C

339m
WEB2824/24APPLICATION DECLARED INVA23 Dec 2024

***OUTSIDE DCC JURISDICTION***The replacement of approx. 251 m of existing 2.4 m high chainlink perimeter fencing and associated access/emergency gates with new 2.4 m high security fencing, gates and all associated site works.

Huntstown Power Station, Huntstown, Co. Dublin

383m
FW21A/0144GRANT PERMISSION11 Aug 2021

The development will consist of the installation of electrical infrast

Townlands of Johnstown, Huntstown, Coldwinters & Balseskin, at Blancha

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?