Keppel Data Centre, 4 Ballycoolin Rd, Ballycoolin, Dublin 15, D15 AKK1
GRANT PERMISSIONPlanning application FW24A/0214E
Dublin - Fingal County Council
Proposed Development
We, Grid Beyond Limited, intend to apply for Permission for developmen
View the full application file on the council's planning portal →Application Timeline
Application received
17 May 2024
Decision: GRANT PERMISSION
2 Jul 2024
Decision due
11 Jul 2024
Grant issued
6 Aug 2024
Application Details
- Location
- Keppel Data Centre, 4 Ballycoolin Rd, Ballycoolin, Dublin 15, D15 AKK1
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Fingal County Council
- Site Area
- 160 ha
Timeline
- Registration Date
- 17 May 2024
- Status
- Final Grant
- Decision
- GRANT PERMISSION
- Decision Date
- 2 July 2024
- Grant Date
- 6 August 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development will consist of proposed alterations to the existing g
KDCR (Ireland) 2 Limited, Unit B10, IDA Business Park, Ballycoolin, Du
Permission for development to consist of the erection of a new ESB Sub
Keppel, Unit B10 IDA Business Park, Ballycoolin, Dublin 15, D15 YN9K
Provision of a generator and air handling unit compound including 4 no
Kepple, Unit B10 IDA Business Park, Ballycoolin, Dublin 15, D15 YN9K
For amendedments to previously approved Grant of Permission (Reg Ref F
Keppel, Unit B10 IDA Business Park, Ballycoolin, Dublin 15, D15 YN9K
Permission for amendments to previously approved Grant of Permission
Kepple, Unit B10, Ballycoolin Business Park, Ballycoolin, Dublin 15
Retention of a) 2 no. generator compounds, b) Boundary Fencing, c) rel
Unit B10, IDA Business Park, Ballycoolin, Dublin 15
Change of use from factory unit to electronic data storage centre, wit
Building B10, IDA Business Park, Ballycoolin Industrial Estate, Blanch
Permission for the separation of Building 1 and Building 2
Ballycoolin Business Park, Blanchardstown, Dublin 15
1. Retention of the existing Generator Building, fuel loading area an
IDA Blanchardstown Business & Technology Park, Snugborough Road, Dubli
Planning permission is sought for: - Removal of 22 parking spaces to a
On a site comprising an area of existing hard standing to the north of