Proposed Development

STRATEGIC INFRASTRUCTURE DEVELOPMENT (ABP Decision) 110kV onsite electrical substation with associated electrical plant, electrical equipment, welfare facilities and waste water holding tank and security fencing. 110kV overhead line grid connection cabling, upgrade of existing tracks and provision of new site access roads with all associated site development and ancillary works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 Dec 2018

  2. Decision: CONDITIONAL

    29 Jul 2020

  3. Grant issued

    29 Aug 2020

  4. Decision due

    14 Dec 2020

Application Details

Location
Timahoe East , Co. Kildare
Applicant
N/A
Application Type
N/A
Planning Authority
Kildare County Council

Timeline

Registration Date
14 December 2018Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
29 July 2020
Grant Date
29 August 2020
Permission Expires
28 August 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

698m
181514REFUSED14 Dec 2018

a ten year planning permission to develop a renewable energy development. The proposed renewable energy development will comprise of (a) the construction and operation of 2 areas of solar photovoltaic arrays mounted on metal frames over an area of approximately 200ha, and having a maximum overall height of 3 metres over ground level; (b) Internal solar farm underground cabling; (c) 2 no. temporary construction compounds; (d) recreation and amenity works, including looped walk (upgrade of existing tracks and provision of new tracks, car parking and vehicular access); (e) 1 no. Battery Storage compound; (f) upgrade of existing tracks and provision of new site access roads; (g) site drainage; (h) forestry felling and replanting; (i) permanent signage; and (j) all associated site development and ancillary works. The proposed renewable energy development will have an operational life of 35 years from the date of commissioning. The overall renewable energy project also includes the provision of a 110kV substation with associated electrical plant, welfare facilities, waste water holding tank, security fencing, upgrade of existing tracks and provision of new site access roads, 110kV overhead line grid connection cabling with associated angle lattice masts and supporting polesets and all ancillary works, which is subject to a separate planning application made directly to An Bord Pleanála in accordance with Section 182A of the Planning and Development Act 2000 (as amended). An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been prepared in relation to the project and accompanies this planning application. Revised by significant further information consisting of; Further Information Response Report; Updated Environmental Impact Assessment Report and Appendices; Updated Natura Impact Statement; Amended Planning Application Drawings, showing; amended access/amenity track (relocated to accommodate Marsh Fritillary habitat), updated amenity signage, clarification of road sectional drawings, additional substation cross section drawing. Updated photomontage booklet

Townlands of Drehid Mulgeeth , Ballynamullagh Mucklon Kilmurray (Carbury By) , Killyon and Timahoe East

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?