Proposed Development
A 10-year planning permission with a 30-year operational life for development on a site area of 3.23 hectares in the townland of Ticknevin, Carbury, Co. Kildare. The development will consist of up to 1 (one) wind turbine with a tip height of up to 187 metres, and all associated foundations and hardstanding areas, 20 metres of new wind farm road, and all associated underground electrical and communications cabling. This single turbine application forms part of a larger wind farm development located within County Offaly and Kildare with a separate planning application being submitted to Offaly County Council concurrently. The overall development will consist of up to 9 turbines (8 in Offaly and 1 in Kildare) with a tip height of up to 187 metres, and all associated foundations and hardstanding areas, approximately 4,750 metres of new internal access roads, associated drainage and turning areas; upgrade of approximately 3,500 metres of the existing L50062 public road including upgrade of the existing bridge; a new bridge crossing of the Figile River to provide access between Turbine 3 and Turbine 4; a 2,950-metre recreation trail and all associated development to include gravel pathways, a footbridge across the Figile River, a parking area, signage, information boards and outdoor fitness equipment; an off-site electrical substation and a battery energy storage facility; all associated underground electrical and communications cabling to connect the turbines to the substation including approximately 1,550 metres along the R401 Regional Road, a spoil storage area; a permanent meteorological mast up to 110.5 metres high; 2 No. temporary construction compounds; 2 No. temporary blade adapter set-down areas within the wind farm site and at the junction of the R402 and R401 at Rathmore, Edenderry, Co. Offaly; turbine delivery route works including widening of the junction of the R420 and R402 at Ballina, Geashill, Co. Offaly and all associated site development works. This application is accompanied by an Environmental Impact Assessment Report and a Natura Impact Statement
Application Timeline
Application received
28 Nov 2019
Decision due
31 Jan 2020
Decision: REFUSED
31 Jan 2020
Appeal submitted
27 Feb 2020
Grant issued
23 Sept 2020
Appeal decided: CONDITIONAL
23 Sept 2020
Application Details
- Location
- Ticknevin , Carbury , Co. Kildare.
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kildare County Council
- Site Area
- 3.23 ha
Timeline
- Registration Date
- 28 November 2019Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- REFUSED
- Decision Date
- 31 January 2020
- Grant Date
- 23 September 2020
- Permission Expires
- 22 September 2025
An Coimisiún Pleanála Appeal
- Appeal Reference
- 306748-20
- Decision
- CONDITIONAL
- Submitted
- 27 February 2020
- Decided
- 23 September 2020
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 10-year planning permission with a 30-year operational life for development on a total site area of approximately 63.9 hectares in the townlands of Ballykilleen, Shean, Kilcumber, Cloncant, Cushaling and Rathmore, Edenderry, Ballina, Geashill, Co. Offaly and Ticknevin, Carbury, Co. Kildare. The development will consist of up to 9 No. wind turbines (8 in Co. Offaly, 1 in Co. Kildare), with a tip height of up to 187 metres, and all associated foundations and hardstanding areas; approximately 4,750 metres of new internal access roads associated drainage and turning areas; upgrade of approximately 3,500 metres of the existing L50062 public road including upgrade of the existing bridge; a new bridge crossing of the Figile River to provide access between Turbine 3 and Turbine 4; a 2,950 metre recreation trail and all associated development to include gravel pathways, a footbridge across the Figile River, a parking area, signage, information boards and outdoor fitness equipment; and off-site electrical substation and a battery energy storage facility; all associated underground electrical and communications cabling to connect the turbines to the substation including approximately 1,550m along the R401 Regional Road; a spoil storage area; a permanent meteorological mast up to 110.5 metres high; 2 No. temporary construction compounds; 2 No. temporary blade adapter set-down areas, turbine delivery route works and all associated site development works. An Environmental Impact Assessment Report and a Natura Impact Statement has been prepared in respect of the application.
Ticknevin , Carbury , Co. Kildare.
(A) CONVERSION OF EXISTING ATTIC STORAGE SPACE TO HABITABLE ROOM, (B) INCREASED ROOF HEIGHT, (C) 30M2 OF GARDEN SHED AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
6 DERRIES EDENDERRY , CO. OFFALY , R45 R156
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?