Proposed Development
Extension of Duration of Planning Reg. Ref. 17/519 - Extension of Duration of Planning Reg. Ref. 12/251. The development consists of
- (A)erection of bungalow, garage for domestic use and the installation of Septech 2000 wastewater treatment system & percolation area
- (B)removal of existing septic tank and the installation of Septech 2000 wastewater treatment system & percolation area to serve the existing adjoining house.
- (C)alter the existing entrance to the adjoining house, to form a combined double recessed entrance to serve the existing and proposed houses.
- (D)permanently close up the existing field entrance and all associated site works
Application Details
- Location
- Taghadoe , Maynooth , Co. Kildare
- Applicant
- N/A
- Application Type
- EXTENSION OF DURATION
- Planning Authority
- Kildare County Council
Timeline
- Registration Date
- 25 November 2022
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Extension of Duration of Planning Ref. No. 12/251 - The development consists of: (A) Erection of bungalow, garage for domestic use and the installation of Septech 2000 wastewater treatment system & percolation area; (B) Removal of existing septic tank and the installation of Septech 2000 wastewater treatment system & percolation area to serve the existing adjoining house; (C) Alter the existing entrance to the adjoining house, to form a combined double recessed entrance to serve the existing and proposed houses; (D) Permanently close up the existing field entrance and all associated site works
Taghadoe , Maynooth , Co. Kildare.
for the development consisting of completion of single storey type house, garage for domestic use and proprietary wastewater treatment system presently under construction, all granted planning permission under file ref no. 12/251 & extension of duration granted under file ref no. 17/519.
Taghadoe , Maynooth , Co. Kildare.
Completion of single storey type house, garage for domestic use and proprietary wastewater treatment system presently under construction, all granted planning permission under file Ref. No. 12/251 and extension of duration granted under file Ref. No. 17/519
Taghadoe , Maynooth , Co. Kildare.
Extension of Duration of Planning Reg. Ref. 12/251. The development consists of (A) erection of bungalow, garage for domestic use and the installation of Septech 2000 wastewater treatment system & percolation area (B) removal of existing septic tank and the installation of Septech 2000 wastewater treatment system & percolation area to serve the existing adjoining house. (C) alter the existing entrance to the adjoining house , to form a combined double recessed entrance to serve the existing and proposed houses. (D) permanently close up the existing field entrance and all associated site works
Taghadoe , Maynooth , Co Kildare
for (A) increased in ridge height on house previously granted planning permission under file ref no.23/54, 17/519 & 12/251 and (B) Retention Permission for first floor accommodation for residential use with 4 no. roof lights to the rear (west) elevation and 1 no. roof light to front (east) elevation
Taghadoe , Maynooth , Co. Kildare
The application will consist of the closing up of existing shared entrance to farm and residence and relocation of same to the South, to allow for greater sight lines onto road R406. It will include the construction of 2mt high entrance piers, addition of new traditional style gates, removal of existing hedging, replanting of new hedging and all associated site works.
Toolstown , Maynooth , County Kildare
for the construction of infrastructure, and associated development, at the existing and planned expanded substation, comprising:- •construction of a new 220 kV Gas Insulated Switchgear (GIS) building (83.5m long x 18.5m wide (25.1m including staircases), 17m in height) (1,637 sqm); • construction of a new 110kV GIS building (68.8m x 15.4m, (22m including staircases) 15m in height) (1,138sqm); • both of the GIS Buildings will have 8 no. associated air rods on each of the roofs (3m in height); • construction of 4 no. 220/110kV power transformers to include connections to the new GIS buildings; • 2 no. 220kV and 1 no. 110kV line/cable interface towers and associated removal of 3 no. existing end masts; • 3 no. lightning masts (height 22m); • cable connections to the 220kV GIS building; • new 4.5m wide internal access road and 10 no. new permanent car parking spaces; • associated site excavation, infrastructural and site development works, and above and below ground boundary treatment and landscaping including palisade fencing (2.6m height), lighting and surface water drainage and foul water tank; • associated demolition of existing bungalow farmhouse and agricultural buildings (1,111.6m2 floorspace total) to facilitate the proposed development; and • all ancillary and associated temporary works to facilitate the development at the construction stage, including construction access track, temporary construction compound / site laydown areas and cable connection for the existing Derryiron-Maynooth 110kV overhead line. Planning permission is sought for a period of 10 years. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application.
Maynooth 220kV Substation , Taghadoe , Co. Kildare
for a new vehicular access driveway to serve the main farmhouse in lieu of the current shared residential and agricultural entrance driveway to include associated gates, pillars, wing walls and set down/hardstanding area between the carriageway and the gates.
Toolestown , Straffan Road , Maynooth
for construction of a new 220 kV Gas Insulated Switchgear (GIS) building (83.5m long x 18.5m wide (25.1m including staircases), 17m in height) (1,637 sqm); construction of a new 110kV GIS building (68.8m long x 15.4m wide (22m including staircases), 15m in height) (1,138 sqm); both of the GIS Buildings will have 8 no. associated lightning protection spikes / rods on each of the roofs (3m in height); construction of 4 no. 220/110kV power transformers to include connections to the new GIS buildings; 2 no. 220kV and 1 no. 110kV line/cable interface towers and associated removal of 3 no. existing end masts and overhead line and cable works; 3 no. lightning masts (height 22m); cable connections to the 220kV GIS and 110kV buildings; new 4.5m wide internal access road and 10 no. new permanent car parking spaces; associated site excavation, infrastructural and site development works, and above and below ground boundary treatment and landscaping including palisade fencing (2.6m height), lighting and surface water drainage and foul water tank; associated demolition of existing bungalow farmhouse and agricultural buildings (1,112sqm floorspace total) to facilitate the proposed development; and all ancillary and associated temporary works to facilitate the development at the construction stage, including construction access track, temporary construction compound / site laydown areas and cable connection for the existing Derryiron-Maynooth 110kV overhead line. Planning permission is sought for a period of 10 years. A Natura Impact Statement will be submitted to the Planning Authority with the application
Maynooth 220kV Substation , Taghadoe and Windgates , Co. Kildare
for the construction of a solar PV development and an ‘under the fence’ transformer compound on a ca. 180ha site consisting of: I. Solar PV panels laid out in arrays across the Site; II. 39 No. inverter units (ca. 2.9m (h) x ca. 6.1m (l) and 2.4(w)); III. 1 No. control room structure (5m (h) x 15.3m (l) and 3.7m (w)); IV. 1 No. transformer unit (ca. 6m x ca. 4m) and associated bund; V. Security fencing around the ‘under the fence’ transformer compound (2.65m high); VI. Electrical and communications cabling; VII. Pole-mounted security cameras; VIII. Perimeter security fencing (2m high) and security gates; IX. Upgrade of 3 No. existing Site entrances; X. Development of 2 No. new Site entrances; XI. 3 No. temporary construction compounds; XII. Internal access tracks; and, XIII All associated ancillary development, landscaping and reinstatement works
Cowanstown Kealstown Bryanstown Dowdstown , Donaghstown Posseckstown Taghadoe Toolestown , - Windgates Rowanstown and Roosk
The submission window has closed
Observations on this application closed on Saturday 7 January 2023, five weeks after it was received. The authority cannot accept a late submission.