Osprey Hotel & Spa , Devoy Quarter , Naas
CONDITIONALPlanning application 23870
Kildare - Kildare County Council
Proposed Development
the construction of a 3 storey extension to the hotel to provide 34 additional bedrooms. The ground floor level will be a screened surface car park providing 19 no. parking spaces, with stair and lift access for residents, to the upper floors. A further 7 no. parking spaces are to be provided adjacent to the chiller compound. The extension is to be constructed on the site of an existing car park which currently provides 32 spaces. The entrance to the reconfigured parking area is to be relocated to the east end of the proposed bedroom block. The existing single storey plant room for the hotel back up generator is to be demolished and the generator is to be relocated to the existing chiller compound which is below ground level. The existing hotel courtyard will be landscaped to create a wedding garden and the landscaped berm above the existing car park ramp is to be reprofiled to provide pedestrian access from the ground floor of the new extension to the hotel reception area
View the full application file on the council's planning portal →Application Timeline
Application received
28 Aug 2023
Decision: CONDITIONAL
17 Oct 2023
Decision due
22 Oct 2023
Grant issued
29 Nov 2023
Application Details
- Location
- Osprey Hotel & Spa , Devoy Quarter , Naas
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kildare County Council
- Site Area
- 0.1834 ha
Timeline
- Registration Date
- 28 August 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 17 October 2023
- Grant Date
- 29 November 2023
- Permission Expires
- 28 November 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of a 3 storey extension to the hotel to provide 34 additional bedrooms. The ground floor will be a screened surface car park providing 19 no. parking spaces, with stair and lift access for residents to the upper floors. A further 7 no. car parking spaces are to be provided adjacent to the chiller compound. The extension is to be constructed on the site of an existing car park which currently provides 32 spaces. The entrance to the reconfigured parking area is to be relocated to the east of the proposed bedroom block. The existing single storey plant room for the hotel back-up generator is to be demolished and the generator is to be relocated to the existing chiller compound which is below ground level. The existing hotel courtyard will be landscaped to create a wedding garden and the landscaped berm above the existing car park ramp is to be reprofiled to provide pedestrian access from the ground floor of the new extension to the hotel reception area.
Osprey Hotel , Devoy Quarter , Naas
(a) the construction of a detached new 24 bedroom block over three storeys to the side of the existing hotel. (b) the demolition of the existing single storey hotel backup generator outbuilding and adjacent associated landscaping and the relocation of the hotel backup generator to the existing basement shaft to the side of the proposed bedroom block. (c) the redistribution of the existing 32 car parking spaces by way of 8 spaces in front of the proposed bedroom block, 10 new spaces to the existing bus parking bays on the northern boundary of the site and by creating an entrance into the existing currently inaccessible ESB substation area and for the provision of 14 new spaces in this area including associated ancillary site works
The Osprey Hotel & Spa , Devoy Quarter , Naas
1.) Demolition of 2 No. existing external entrance canopy structures and associated alterations to the eastern and western facades of the Time Nightclub/Osprey Business & Conference Centre building; 2.) Demolitions and alterations to facade & construction of new double height glazed entrance structure/extensions at ground/first floor level to the western facade of the Time Venue Nightclub/Osprey Business & Conference Centre building; 3.) Construction of new glazing/window locations at ground floor level to the eastern facade of the Time Venue Nightclub/Osprey Business & Conference Centre building; 4.) Demolitions and alterations to facade and construction of new double height glazed entrance structure/extensions at ground/first floor level to the Osprey Hotel Spa facility at the eastern facade of the Osprey Hotel building; 5.) New external bicycle parking spaces and car parking space; & 6.) All necessary consequent internal and external alterations, site works and ancillary works
Time Venue/Premier Business Centre Building and Osprey Hotel , Osprey Campus , Devoy Quarter
1.) The Change of Use from Multi-Purpose Entertainment Venue to Office Use at Ground Floor Level, First Floor Level & Second Floor Level areas of the Time Venue Nightclub/Premier Business Centre building; 2.) Construction of New Roof Lights at Roof Level; 3.) New External Bicycle Parking Spaces; & 4.) All necessary consequent internal and external alterations and ancillary works. All
Time Venue/Premier Business Centre , Osprey Business Campus , Devoy Quarter
The change of use from part of multi-purpose entertainment venue to office use at first floor level at the north of the premier business centre/time venue building
Premier Business Centre/Time Venue Building , Osprey Business Campus , Devoy Quarter Naas
for modifications to a previously permitted Strategic Housing Development (permitted under ABP-307258-20 and altered under ABP-31161-21 & ABP311825-21) on lands at Devoy Quarter, Naas West, Co. Kildare (under construction 'Rathvoy Park'). This application for the proposed modifications to the consented scheme is a Large-Scale Residential Development (LRD) as defined under section 2 of the Planning & Development Act 2000, as amended. The development will consist of: 1) Proposed external and internal modifications to the southern portion of previously permitted Block 1, to provide for the change of use of the additional storage room to residential use to provide for 1 no. 2-bedroom apartment, including an external west facing private open space area, this would result in an overall increase from 171 units previously permitted to 172 no. units in total. 2) Proposed external and internal modifications to previously permitted apartment no 8. in Block 4, from a 1-bedroom apartment to a 2 bedroom apartment. 3) Proposed external and internal modifications and change of use to previously permitted Community Use Building to provide for an additional creche facility, including the provision of an external play area.4) The addition of 1no. car-parking space and 10 bike spaces from that previously permitted. The proposed development will include modifications to previously permitted hard and soft landscaping; car-parking layout, including the provision of an additional set-down area to facilitate the change of use of the community use building; modifications to the location of the bin and bike storage; and all associated ancillary site development works necessary to facilitate the development
Devoy Quarter , Naas West , Naas
test
test ,
STRATEGIC HOUSING DEVELOPMENT: Residential Development of 152 Apartments within 9 Blocks, Childcare Facility & Single Storey Community Use Building. ABP-307258-20 & ABP-311825-21
Devoy Quarter , Naas West , Naas
This is just a test record used for checking software development. Please do not delete it. Please disregard this file. There is no development but this description should be really long to test the layout of all the letters. This is just a test record used for checking software development. Please do not delete it. Please disregard this file. There is no development but this description should be really long to test the layout of all the letters. This is just a test record used for checking software development. Please do not delete it. Please disregard this file. There is no development but this description should be really long to test the layout of all the letters.
KILDARE COUNTY COUNCIL , Áras Chill Dara John Devoy Road Devoy Park , Naas
(i) Demolishing an existing 2 storey dwelling and stable block (ii) Constructing 10 no. two-storey dwellings consisting of 2 no semi detached units facing onto Rathasker Road, 1 no. terraced block containing three units and 1 no. terraced block containing five units (iii) Construction of a new wastewater pumping station with new rising main to service part of the site (iv) Revisions to the existing vehicular entrance and construction of new internal access road to service dwellings and all ancillary site works. Revised by Significant Further Information which consists of (a) a revised site layout relocating proposed dwellings to the south and construction of boundary wall to the north, (b) retention of Clough Farmhouse and single storey extension to rear of same, (c) proposed demolition of part of existing stable block and first floor extension to remaining section of same, (d) a revised foul sewer layout removing any requirement of a wastewater pumping station
Clough , Rathasker Road , Naas
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?