← Back to search

Aisling , 13 Whitethorn Grove , Kill

CONDITIONAL

Planning application 24366

Kildare - Kildare County Council

Proposed Development

For retention of habitable ground floor extension to the rear of the existing dwelling house . Retention of habitable ground floor extension to the front of the existing dwelling house. Retention of conversion of existing garage space to habitable space within the existing footprint of the existing dwelling house.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    22 Nov 2024

  2. Decision: CONDITIONAL

    22 Jan 2025

  3. Decision due

    25 Jan 2025

  4. Grant issued

    4 Mar 2025

Application Details

Location
Aisling , 13 Whitethorn Grove , Kill
Applicant
N/A
Application Type
RETENTION
Planning Authority
Kildare County Council
Site Area
0.0734 ha

Timeline

Registration Date
22 November 2024
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
22 January 2025
Grant Date
4 March 2025
Permission Expires
3 March 2030

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

41m
2560403CONDITIONAL16 Apr 2025

for a single storey front, side and rear extension, comprising of a bedroom, wet room, utility room and family room, with flat roof and all associated site works

1880 St. Bridgid’s Terrace , Kill , Co. Kildare

42m
23989CONDITIONAL14 Nov 2023

demolition of existing single storey garage and link to side and construction of new single storey extension to side and front

17 Whitethorn Grove , Kill , Co. Kildare

70m
20997N/A2 Sept 2020

retention of existing 1.8m fence at the front of the house and at the right side when facing the house,

9 Whitethorn Grove , Kill , Co. Kildare

106m
2461137REFUSED30 Oct 2024

for amendments to the previously permitted development (Kildare County Council Reg. Ref. 04/2631), at a site of approximately 0.43 hectares. The proposed development will consist of: the part-demolition of the single storey forecourt building (21 sq m) and the removal of external compounds, substation, car wash, storage shed, and totem signs; the construction of a 219 sq m extension to the forecourt building and revised facades resulting in a part-one/part-two storey building of 525 sq m to accommodate a retail unit (100 sq m net retail area, including a 9 sq m ancillary off licence), 3 No. restaurant/cafe areas (which will include the sale of hot and cold food for consumption on and off the premises) (1 No. to include a drive-thru facility), associated seating area, back of house areas, circulation spaces, and a substation/switch room (8 sq m); and the construction of an EV Charging Hub (consisting of 8 No. EV charging spaces, a canopy, ancillary plant, and substation). The development will also consist of revisions to the overall site layout resulting in: 23 No. car parking spaces (in addition to the EV Hub spaces); motorbike and bicycle parking spaces; revised vehicular circulation; relocated water and air services, offset fills and vents; external lighting; provision of an outdoor seating area; changes to levels, hard and soft landscaping, including revised boundary treatments; associated site servicing (water supply, foul and surface water drainage including surface water attenuation measures); all other associated site development works above and below ground. The development will also consist of 24 No. signs: 1 No. replacement 8.2 m high double-sided internally illuminated totem sign; 1 No. 4.8 m high double-sided internally illuminated freestanding sign; 8 No. charge point signs at the EV Hub; 9 No. signs fixed to the forecourt building (3 No. of which are illuminated); 2 No free-standing signs; 3 No. fixed signs. The proposed development also proposes to alter Condition No. 10 of KCC Reg. Ref. 04/2631, “The proposed café/ take – away hours of operation shall be 07.00 to 21.00. Reason: In the interests of the preservation of residential amenities and the proper planning and sustainable development of the area.”, to allow for the operation of the cafe/restaurants (including drive-thru) from 06.30-00.00 Monday to Thursday, and 24 hours Friday to Sunday. The development will also consist of a single storey temporary structure (72 sq m) to accommodat

Maxol Service Station N7 Naas Road , Kill , Co. Kildare

108m
20816N/A27 Jul 2020

to erect 279m² of photovoltaic panels on the roof of our existing building with all associated site works

Main Street , Kill , Co. Kildare.

111m
20851N/A4 Aug 2020

279sqm of photovoltaic panels on the roof of our existing building with all associated site works

Eurospar , Main Street , Kill

112m
2560228CONDITIONAL7 Mar 2025

for the alterations to the approved storm water network to serve the development approved under Kildare County Council Reference Number 23/986 including the construction of a new outfall discharge route to the adjoining Kill River and all associated site development works. Revised by Significant Further Information which consists of amendments to the storm water network design and inclusion of additional professional reports

Marsville House , Main St , Kill

116m
2660347CONDITIONAL1 Apr 2026

As constructed 2 storey side extension to existing 2 storey house and all associated site development works

2002 Saint Brigid's Terrace , Kill , Co. Kildare

124m
191392N/A16 Dec 2019

the demolition of existing single storey forecourt building accommodating a shop and café (246 sqm GFA), removal of external compounds, substation and car wash; and the provision of a temporary structure to accommodate the shop/office (72 sqm GFA) during the construction phase. The proposed development will also consist of the construction of: single storey forecourt building (531 sqm GFA) accommodating a shop (100 sqm net, including a 9.5 sqm ancillary off-licence), 3 No. restaurant/café areas (which will include for the sale of hot and cold food for consumption on and off the premises) (one of which will include a drive-thru facility), associated restaurant/café seating area, ancillary kitchens, staff and customer facilities, plant, storage, back of house and circulation spaces; and a new substation (23 sqm GFA). The proposed development will also consist of: new shopfront signage (some illuminated) (9 sqm), a replacement double sided illuminated totem (18 sqm each side); revisions to the site layout, including the provision of 37 No. car parking space and new waste compound, relocation of the air/water services; changes to levels; alterations to external lighting; hard and soft landscaping, including revised boundary treatments and an external public seating area; associated alterations to the permitted scheme’s services (mechanical and electrical, water supply, sewage disposal and surface water disposal); and all other associated site development works above and below ground. The proposed development will also consist of the retention of a solid fuel store (6.4 sqm GFA).

site of approximately 0.45 hectares at , Maxol N7 Naas Road , Kill Co. Kildare

125m
201058CONDITIONAL16 Sept 2020

to erect 279sqm of photovoltaic panels on the roof of our existing building with all associated site works

EUROSPAR , Main Street , Kill

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?