The site consists of up to approximately 15.05 kilometres (km) of 38 kilovolts (kV) underground cable (UGC) and all associated site and development works at various locations in County Kildare with a total site area of c. 16.13ha. , Cullaghreeva Conf
N/APlanning application 2660074
Kildare - Kildare County Council
Proposed Development
a 10-year approval for development at this site consisting of up to approximately 15.05 kilometres (km) of 38 kilovolts (kV) underground cable (UGC) and all associated site and development works at various locations in County Kildare with a total site area of c. 16.13ha. The proposed development crosses the townlands of Cullaghreeva, Confey, Newtown, Leixlip, Kellystown, Sion, Ravensdale, Blakestown, Collinstown, Greenfield, Dowdstown and Railpark. The proposed development consists of the following elements: Installation of 3no. new 38 kV underground cable routes, or cable route sections, and all associated site and development works within the administrative area of Kildare County Council (KCC) as outlined below and illustrated on the maps herein: The proposed Coolmine cable route section in KCC (shown in purple) is approximately 1 km in length crossing the townlands of Cullaghreeva and Confey from east to west. The proposed Leixlip cable route section in KCC (shown in blue) is approximately 11.51 km in length crossing the townlands of Newtown, Confey, Leixlip, Kellystown, Sion, Ravensdale, Blakestown and Collinstown from east to west. There are two Protected Structures located within the application area of the Leixlip cable route, Deey Bridge and Lock (RPS B06-14) and Sandford Bridge (RPS B06-16). The proposed Moneycooley cable route is wholly within KCC (shown in orange) and is approximately 2.54 km in length crossing the townlands of Greenfield, Dowdstown and Railpark from south to north. The primary purpose of the proposed underground cables is to provide electrical power to the Dart+ West Railway project as granted under the DART+ West Railway Order (ACP Ref. 314232). The proposed underground cable routes will incorporate the following elements: - Communication links and fibre optic cables between all substations in the same trench as the UGC; Joint bays and communication chambers along the UGC alignment; Temporary construction laydown and work areas with ancillary staff facilities and parking, temporary access tracks, passing bays and water and utility crossings; - All associated and ancillary above and below ground site development works, including works comprising or relating to permanent and temporary construction and roadworks and excavation (including HDD) and vegetation clearance. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application
Application Details
- Location
- The site consists of up to approximately 15.05 kilometres (km) of 38 kilovolts (kV) underground cable (UGC) and all associated site and development works at various locations in County Kildare with a total site area of c. 16.13ha. , Cullaghreeva Conf
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kildare County Council
- Site Area
- 16.13 ha
Timeline
- Registration Date
- 27 January 2026Other applications received that week
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Single storey detached bungalow, recessed entrance, secondary effluent treatment system and all associated site works
Kilmacredock , Maynooth , Co. Kildare
provision of a temporary contractor’s car park and contractor’s compound(s) for a period of 5 years, associated with the development of the proposed extended and revised manufacturing facility at Intel, granted under An Bord Pleanála ref: 304672. The development will include: 1. Modifications to existing site entrance and associated modifications to the existing adjacent footpath and cycle lane. 2. Surface car park to accommodate 300 cars, maximum. 3. Contractor compounds comprising approximately 14 no. compounds ranging in area from 1,500 sq.m to 10,500 sq.m. Each compound will accommodate work cabins of single (3.5m) or double (7.0m) height, and a maximum of approximately 6-8 cabins (8m x 3m each). 4. Site accommodation which will include single storey - Office canteen and welfare facilities, (c.42mx12m) – Entrance security cabin, (c.7m x 3m) – Compound security & welfare cabin (c.12m x 3m) – Toilet block (c.12m x 6m) – Bus Shelter (c.3m x 1.2m) – Maintenance shed (c.8m x 7m) – Electrical substation/switchroom (c.13m x 4.4m) 5. A c. 2,700sq.m temporary decrating building, measuring c. 40m x 69m, and 15m high, and associated c. 3,716sq.m nonpermeable maneuvering and operational space. 6. Logistics & maintenance yard. 7. Transport vehicle (truck) holding compound for approximately 30 units. 8. Internal road network, site lighting, landscaping, mobile cranes and associated site works, security fencing to site and compound boundaries. A Natura Impact Assessment (NIS) accompanies this application and will be available for inspection at the office of the Planning Authority. Development is at a site of c. 14.95 hectares, bounded by the R449 to the east and the Maynooth to Leixlip railway line/royal canal to the North
Collinstown , Leixlip , Co. Kildare.
modifications to existing Fab 10, 14 and 24 facilities and yards, comprising: - A 3 storey support building housing plant and equipment, sized 540 square meters and 18.5 meters high, located to the rear of Fab 10, and a sunken bund area with a roof canopy 6 meters high, housing plant and tanks in the yard area to the rear of Fab 10 sized 270 square meters and 7 meters deep and with a pipe bridge and with 2 gound level tanks. – An external equipment lift shaft sized 200 square meters and 18 meters high and a single storey chemical room extension for F10 sized 210 square meters and 9 meters high both located to the west of Fab 10. – A single storey gas cylinder storage extension sized 168 square meters and 5 meters high located to the west of Fab 10. – A single storey Water Treatment building extension with an internal mezzanine sized 300 square meters and 9 meters high located to the north of the Fab 10 Water Treatment building and a single storey energy centre extension sized 156 square meters and 9 meters high and a bunded tank enclosure located to the north of the Fab 10 energy centre. – Roof mounted equipment, a 4 meters high acoustic screen and a 4 meters high visual screen and 3 general exhaust stacks, 6.5 meters high above existing parapet located to the rear of the Fab 10 roof. – Building links located between Fab 10 and Fab 14, one elevated link sized 264 square meters, 9 meters high and 5 meters above ground; and the extension of an existing elevated pedestrian link sized 69 square meters, 9 meters high and 5 meters above ground level; and a ground level link sized 138 square meters, 9 meters high both including roof modiciations to existing single storey kitchen server; and an elevated link located between Fab 14 and Fab 24 sized 456 square meters, 9 meters high and 5 meters above ground, all housing plant and equipment. – 2 no. bunded solvent storage tanks and associated truck staging area located to the rear of Fab 14. This application consists of a variation to a previously permitted development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and full details of the proposed development and its anticipated environmental impacts will be notified to the Environmental Protection Agency. This is a site to which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies
Collinstown Leixlip Blakestown Kellystown , Collinstown Industrial Park , Leixlip
modifications to the existing entrance and the existing footpath and cycle lane to the western side of the R449 in order to provide a new left-in left-out vehicular access including pedestrian and cycle access from the R449 to an internal access road and junctions to facilitate the future development of "Collinstown Business Campus" together with public lighting, landscaping and associated services on its lands. Revised by significant further information consisting of: submission of revised indicative masterplan
Collinstown , Leixlip , Co. Kildare.
1) Installing a new all weather 'astro-turf' playing surface to existing grassed soccer pitch, 2) Installation of new floodlighting and floodlighting columns numbering six at 15m in height, 3) Erecting new 3m high perimeter fencing surrounding the new pitch and 6.3m high netting locally behind the goals at either end of new pitch , 4) and all associated site works
Leixlip United , Leixlip Amenities Centre , Collinstown
the replacement of 10 No. previously approved house type G (three bedroom, two storey houses) at 45-54 The Avenue, with 6 No. M1 type houses (three bedroom, two storey houses) and 4 No. D and D1 type houses (four bedroom, two storey houses). The houses being replaced were originally granted planning permission under PL 09.247909 (KCC Ref. 16/282) on this site
Westfield , Green Lane , Leixlip
amendments to the previously granted house types of G & G2 at houses 23-28 The Avenue, & 1-8 The Close consisting of amendments to the front elevation, ground floor plan, along with the provision of a canopy over the front entrance doors of those units. The houses the subject matter of this application were previously granted planning permission under reg. ref. 16/282 on the applicants lands
Westfield , Green Lane , Leixlip
the construction of an additional floor to the approved 3 storey apartment block - Block B, previously granted planning permission under reg. ref. 16/282, comprising of an additional 5 no. 2 bed apartments along with amendments to the site layout to provide for the required additional car parking spaces along with all other ancillary site development works
The Mews , Westfield , Green Lane Leixlip
the replacement of 2 No. previously approved house type C and F (three bedroom, two storey semi-detached houses) at 43 and 44 The Avenue, with 2 No C3 type houses (four bedroom, two storey detached houses). The houses being replaced were originally granted planning permission under PL 09.247909 (KCC Ref. 16/282) on this site
Westfield , Green Lane , Leixlip
(1) Modular Storage Unit. A Single storey storage unit, sized approximately 7 metres by 12 metres and 6 metre high, located in the Utilities Yard to the north of the existing Fab10 Support Building. (2) FAB10 Waste Tanks. The installation of 3no. new bunded waste storage tanks, 2no. sized approximately 2.5 metres in diameter and 16.5 metres high, located in the Utilities Yard to north of the existing Fab10 Support Building and 1no. sized approximately 3.7metres in diameter and 15 metres high located to the north of the Fab10 Utilities Yard. (3) Process Support Building Extension. The construction of a two-storey extension to the existing Process Support Building (PSB) sized approximately 20 metres by 11 metres and 14 metres high, located to the north east of the existing Fab 24 Process Support Building. (4) FAB24 and FAB14 Waste Tanks. The installation of 3no. additional waste tanks and associated access platforms and stairways, 1no. sized approximately 9 metres by 10 metres and 7 metres high, located in the Utilities Yard to the north of the existing FAB24 Manufacturing Building and 1no. sized approximately 3 metres high located to the south of existing FAB14 Process Building and 1 no. sized approximately 4.25 metres in diameter and 16 metres high, located to the south of existing FAB14 process Building.(5) Site Works. The proposed development includes linking pipe-bridges to the Fab10 and Fab14 support buildings, site development works, site utilities, site lighting, separation walls, road alterations, landscaping and all associated site works. This application consists of a variation to a previously permitted development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) is required. A Natura Impact Statement ("NIS") accompanies this application for inspection or purchase at the office of the Planning Authority. This is a site to which the Chemical Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 (S.I.209 of 2015) applies
Collinstown Leixlip , Blakestown Kellystown , Collinstown Industrial Park
The submission window has closed
Observations on this application closed on Monday 2 March 2026, five weeks after it was received. The authority cannot accept a late submission.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?