Manor Stone , Oldglass , Ballacolla
CONDITIONALPlanning application 22506
Laois - Laois County Council
Proposed Development
diversify the grant of retention and planning permission reference 21/668 on the farm shop to include an off licence in a portion of the farm shop, also planning permission for signage on the front façade and all associated works
View the full application file on the council's planning portal →Application Timeline
Application received
17 Aug 2022
Further information requested
5 Oct 2022
Further information received
15 Nov 2022
Decision: CONDITIONAL
7 Dec 2022
Decision due
12 Dec 2022
Grant issued
20 Jan 2023
Application Details
- Location
- Manor Stone , Oldglass , Ballacolla
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Laois County Council
- Site Area
- 0.04 ha
Timeline
- Registration Date
- 17 August 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 7 December 2022
- Grant Date
- 20 January 2023
- Permission Expires
- 4 July 2027
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Develop as follows: a) RETENTION PLANNING PERMISSION FOR SAW SHED 1, SAW SHED 2, WORKSHOP,ESB SUBSTATION STORAGE SHED AND A PORTACABIN CONTAINING CANTEEN AND TOILET b) RETENTION PLANNING PERMISSION FOR FARMSHOP AND FULL PLANNING PERMISSION FOR EXTENSION TO FARMSHOP, c) RETENTION PLANNING PERMISSION FOR BICYCLE HIRE SHOP AND STORE d) RETENTION PLANNING PERMISSION FOR CAR SALES & SERVICE UNIT CONSISTING OF WORKSHOP, VALETING UNIT, PORTACABIN OFFICE, DISPLAY YARD, ENTRANCE AND SIGNAGE e) RETENTION PLANNING PERMISSION FOR ENTRANCE A ACCESS TO MANOR STONE DISPLAY AREA AND SIGNAGE, f) PLANNING PERMISSION FOR 'TASTE OF LAOIS CENTRE' CONSISTING OF ARTISAN UNITS, LECTURE THEATRE, AUDIO-VISUAL ROOM, TOILET BLOCKS, STAFF TOILET AND OFFICE AND SIGNAGE g)PLANNING PERMISSION FOR NEW ENTRANCE B FROM THE R433 TO PARKING AREA IN MANOR STONE AND TASTE OF LAOIS CENTRE h) PLANNING PERMISSlON FOR A CYCLE ACCESS WITH SAFETY BARRIER INCLUDING ALL ASSOCIATED AND NECESSARY SITE WORKS ON A SERVICED SITE
Oldglass , Ballacolla , Co. Laois
retain garden centre as constructed and all associated and necessary site works on a serviced site
Manor Stone , Oldglass , Ballacolla
retain garden centre as constructed. Also retention permission for covered access, office building and lean to storage and all associated and necessary site works on a serviced site
Manor Stone , Oldglass , Ballacolla
(I) car wash, (ii) car wash plant room with water recycling system, (iii) all associated structures, drainage and site development works
Circle K , Manor Stone Service station , Tintore Ballacolla
construct (i) car wash, (ii)car wash plant room with water recycling system, (iii)all associated structures, drainage and site development works.
Circle K Manor Stone Service Station , Tintore , Ballacolla
retain a retail unit to provide an off-licence and ancillary and associated site works and planning permission for signage
Tintore , Ballacolla , Co. Laois
retain a retail unit to provide an off-licence and ancillary and associated site works and planning permission for signage
Tintore , Ballacolla , Co. Laois
change use from permitted retail use to retail use including the sale of alcohol for consumption off the premises (i.e. off-licence use) within the overall permitted retail unit, where floor area for the off-licence use is 16sqm and is ancillary to the primary retail use
M8 Motorway , Tintore , Ballacolla
for change of use from permitted retail use to retail use including the sale of alcohol for consumption off the premises (i.e. off licence use) within the overall permitted retail unit, where floor area for the off licence use is 16sqm. and is ancillary to the primary retail use
Circle K Manor Stone Service Station , Off Junction 3 on M8 Motorway , Tintore Ballacolla Co. Laois
construct a high-power electric vehicle charging hub and associated infrastructure, consisting of the following: (i) installation of 8no. electric vehicle charging bays and 4no. charging points which will replace 14no. existing spaces, (ii) Installation of new EV canopy with associated illuminated signage, (iii) new modular ESB Substation, (iv) new EV banner and other signage, (v) signature wall, (vi) relocation of existing lighting columns, new road markings and, (vii) all other associated drainage and site development works.
Circle K Manor Stone Service Station , Off Junction 3 on M8 Motorway , Tintore Ballacolla Co. Laois
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?