Ballymacken , Portlaoise , Co. Laois
CONDITIONALPlanning application 23144
Laois - Laois County Council
Proposed Development
construct two new material storage sheds and demolish two existing material storage sheds
View the full application file on the council's planning portal →Application Timeline
Application received
9 May 2023
Decision: CONDITIONAL
28 Jun 2023
Decision due
3 Jul 2023
Grant issued
31 Jul 2023
Application Details
- Location
- Ballymacken , Portlaoise , Co. Laois
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Laois County Council
- Site Area
- 530 ha
- Floor Area
- 530 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 9 May 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 28 June 2023
- Grant Date
- 31 July 2023
- Permission Expires
- 30 July 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
construct, operate and decommission a photovoltaic solar farm over an area of 2 hectares comprising of photovoltaic panels on ground mounted frames, a switch room building, Perimeter fencing, hardcore access tracks with underground ducting routes, landscaping, new site entrance and access road to solar farm and existing sawmill facility, surface water drainage with underground attenuation tank, revision of existing site boundaries along with all associated ancillary development works.
Ballymacken , Portlaoise , Co. Laois
extend duration on planning permission ref: 17/104
Ballymacken , Portlaoise , Co. Laois
erect a 500kw Wind Turbine 49 metre high with a blade diameter of 52 metre, a new access roadway connecting to existing private roadway/hardstanding with underground ducting connecting to existing ESB Substation, and all associated site works
Ballymacken , Portlaoise , Co. Laois.
erect a 500K Wind Turbine 49 metre high with a blade diameter of 52 metre, a new access roadway connecting to existing private roadway/hardstanding with underground ducting connecting to existing ESB Substation, and all associated site works
Ballymacken , Portlaoise , Co. Laois
erect a 500K Wind Turbine 50 metre high with a blade diameter of 52 metre, a new access roadway connecting to existing private roadway/hardstanding with underground ducting connecting to existing ESB Substation, and all associated site works
Ballymacken , Portlaoise , Co. Laois
construct a new material storage shed
Ballymacken , Portlaoise , Co. Laois
erect a 500kw Wind Turbine 49 metre high with a blade diameter of 52 metre, a new access roadway connecting to existing private roadway/hardstanding with underground ducting connecting to existing ESB Substation, and all associated site works
Ballymacken , Portlaoise , Co. Laois.
to construct, operate and decommission a photovoltaic solar farm over an area of 2 hectares comprising of photovoltaic panels on ground mounted frames, a switch room building, Perimeter fencing, hardcore access tracks with underground ducting routes, landscaping, new site entrance and access road to solar farm and existing sawmill facility, surface water drainage with underground attenuation tank, revision of existing site boundaries along with all associated ancillary development works. A Natura Impact Statement (NIS) has been submitted with this application.
Ballymacken , Portlaoise , Co. Laois
construct a new maintenance and workshop shed
Ballymacken , Portlaoise , Co Laois
construct a new material storage shed
Ballymackan , Portlaoise , Co Laois
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?