Proposed Development

for works associated with the proposed uprate of the existing 110 kV Overhead Line (OHL) between the existing Cushaling 110 kV substation in the townland of Ballykilleen, Co. Offaly & the existing Portlaoise 110 kV substation in the townlands of Clonminam & Kylekiproe, Co. Laois. The replacement (“restringing”) of the existing overhead line circuit conductor with a new higher capacity conductor incl. installation of a new fibre communication connection; Replacement of 8 no. steel towers & their foundations; Replacement of steel members at 1 no. tower; Full tower painting required at 3 no. locations; Shear block remedial works (raise & cap) at 6 no. tower locations; Replacement of wooden poles only at 15 no. locations; Replacement of wooden poles & crossarm at 5 no. locations; Replacement of crossarm only at 14 no. locations; Replacement of existing danger notices at various locations, as required; Replacement of hardware and fittings, such as insulators, insulator hardware, earthwire hardware and anti-climbing guards at various locations as required; Replacement of suspension clamps, vibrations dampers and compression assemblies at all locations as required; All associates temporary site development works to gain access to the existing structures including clearance of vegetation, disassembly & reassembly of gate posts/piers & removal & re instatement of existing fencing; other temporary associated & ancillary development works required for the purpose of the existing circuit, including temporary items, such as; guard poles, construction compounds (located in the townlands of Bracklone, Tullaghan, Morett, Clonaddodoran and Kyletalesha), clearance or management of vegetation, installation of silt traps, silt fences, stone tracks, ground protections mats & watercourse crossings. No additional structures are proposed along the existing circuit. Structure 203,which will be relocated approx. 101m back towards structure 202 due to its existing position on top of a gravel mound & there being potential for subsidence of the gravel in the long term. No alteration to the nature, extent, alignment, character, or voltage of the existing electricity infrastructure is proposed. In addition, works to support this uprate also include the Cushlaing-Portlaoise 110KV bay lead-in conductor uprate at the Portlaoise 110KV station. A Natura Impact Statement (NIS) has been submitted with this application. Full description of all works within Site Notice.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    24 Mar 2025

  2. Further information requested

    15 May 2025

  3. Further information received

    7 Aug 2025

  4. Decision: CONDITIONAL

    30 Sept 2025

  5. Decision due

    1 Oct 2025

  6. Appeal submitted

    29 Oct 2025

  7. Appeal decided: CONDITIONAL

    25 Feb 2026

Application Details

Location
Inchacooly Ullard (Controversyland) Clonanny Kilmullen Derrynafunshion Ballycarroll (Jamestown Electoral Division) Closeland or Cloneen Ballybrittas Emo Park Cappakeel Morett Killone Garryduff (Kilmurry Electoral Division) , Killenny (Kilmurry Electo
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Laois County Council
Site Area
119.8 ha

Timeline

Registration Date
24 March 2025
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
30 September 2025
Permission Expires
24 February 2031

An Coimisiún Pleanála Appeal

Appeal Reference
PL-500151-LS
Decision
CONDITIONAL
Submitted
29 October 2025
Decided
25 February 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

331m
21605N/A31 Aug 2021

extend an existing agricultural shed to the south west of the existing farmyard complex and associated siteworks

Cappakeel , Emo , Co. Laois

339m
19657CONDITIONAL28 Nov 2019

construct 2 number general purpose agricultural sheds and all ancillary services

Cappakeel , Emo , Portlaoise

360m
21646CONDITIONAL16 Sept 2021

extend an existing agricultural shed to the south west of the existing farmyard complex and associated siteworks

Cappakeel , Emo , Co. Laois

389m
18255CONDITIONAL26 Apr 2018

construct new dwelling house, new domestic garage, septic tank treatment system, percolation area and all associated site works

Cappakeel , Emo , Co. Laois

392m
2560098CONDITIONAL28 Feb 2025

for change of use of existing outbuilding to use as 3 no. short term letting units, to include 2 no. 1 bedroom units and 1 no. 2 bedroom unit, new wastewater treatment and percolation system and all associated ancillary site works

Cappakeel , Emo , Co. Laois

394m
2476CONDITIONAL4 Jun 2024

construct granny flat extension to existing dwellinghouse, by converting existing outbuildings and providing new hallway link, and all associated ancillary site works

Cappakeel , Emo , Portlaoise Co. Laois

449m
22434N/A15 Jul 2022

make alterations and additions at ground floor level comprising of the demolition of rear wall and extension with a combination of flat and pitched roofs to create a new living, dining and kitchen space, to the rear of the property

Coolfin , New Inn , Emo

464m
2560581N/A12 Sept 2025

construct an agricultural entrance and all associated and ancillary site works

Cappakeel , Emo , Co. Laois

464m
2560613CONDITIONAL23 Sept 2025

construct an agricultural entrance and all associated and ancillary site works

Cappakeel , Emo , Co. Laois

481m
23122CONDITIONAL17 Apr 2023

extend our workshop to the rear of the existing workshop and showrooms and to carry out all associated works at our premises

Cappakeel , New Inn Cross , Emo Portlaoise

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?