← Back to search

Court , Ballynacarriga , Kildimo Co. Limerick

N/A

Planning application 20169

Limerick - Limerick County Council

Proposed Development

construction of a two storey extension to the front and rear of existing dwelling, single storey extension to the rear elevation, alterations to existing front elevation, waste water treatment system and all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    27 Feb 2020

  2. Further information requested

    9 Jun 2020

  3. Application withdrawn

    9 Dec 2020

Application Details

Location
Court , Ballynacarriga , Kildimo Co. Limerick
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Limerick County Council

Timeline

Registration Date
27 February 2020
Status
DEEMED WITHDRAWN
Decision
N/A
Withdrawn
9 December 2020

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

4m
2024N/A16 Jan 2020

construction of a two storey extension to the front and rear of existing dwelling, single storey extension to the side elevation, alterations to existing front elevation, waste water treatment system and all associated site works

Court , Ballynacarriga , Kildimo Co. Limerick.

17m
22227CONDITIONAL28 Feb 2022

the installation of a wastewater treatment system and all associated site works

Court , Kildimo , Co. Limerick

26m
2141CONDITIONAL18 Jan 2021

a car port

Court , Kildimo , Co. Limerick

161m
20943CONDITIONAL18 Sept 2020

the construction of a dwelling house, garage, entrance, wastewater treatment system and all ancillary site works

Court , Kildimo , Co. Limerick.

174m
191136REFUSED20 Nov 2019

the construction of an extension to existing dwelling house and associated site works

Court , Kildimo , Co. Limerick.

178m
201241CONDITIONAL27 Nov 2020

construction of an extension to existing dwelling house(unit 1) consisting of an extension to the rear and porch to the front of existing house, construction of an extension to existing dwelling house(unit 2) consisting of porch to front of house, construction of an extension to existing dwelling house(unit 3) consisting of a porch annex & extended building line to front of house, construction of an extension to existing dwelling house(unit 4) consisting of a porch annex & extended building line to front of house, and all associated site works. Planning permission is also being sought for the installation of a new domestic wastewater treatment unit and polishing filter for each of the existing dwellings(units 1,2,3 & 4) together with all associated site works

Court , Kildimo , Co. Limerick

309m
191265CONDITIONAL19 Dec 2019

the demolition of an existing one bedroom cottage and the construction of a one storey dwelling house, detached domestic garage, wastewater treatment system, percolation area, entrance and all ancillary site works

Court , Kildimo , Co. Limerick.

457m
2461117CONDITIONAL13 Nov 2024

the construction of an entrance, dwelling house, domestic waste water treatment system & polishing filter together with all associated site works

Court , Kildimo , Co. Limerick

459m
22224N/A25 Feb 2022

the construction of an entrance, dwelling house, domestic wastewater treatment system with polishing filter together with all associated site works

Court , Kildimo , Co. Limerick

488m
24320705N/A4 Sept 2024

the proposed development of 9 no. wind turbines, 110kV substation and ancilliary development located in the townlands of Snatty, Hurdlestown, Oatfield, Drumsillagh, Sallybank, Gortacullin, Aharinaghbeg, Knockshanvo, Cloontra, Cloghoolia, Ballycullen and others, County Clare. And located in the townland

Court , Kildimo , Co. Limerick

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?