Derraulin , Bruree , Co. Limerick
CONDITIONALPlanning application 211523
Limerick - Limerick County Council
Proposed Development
demolition of existing extension to rear and existing front porch, construction of a new two storey extension to rear and single storey extension to front and installation of a new window opening in western gable, all to the existing dwelling
View the full application file on the council's planning portal →Application Timeline
Application received
3 Nov 2021
Further information requested
21 Dec 2021
Further information received
2 Feb 2022
Decision: CONDITIONAL
24 Feb 2022
Decision due
1 Mar 2022
Grant issued
1 Apr 2022
Application Details
- Location
- Derraulin , Bruree , Co. Limerick
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Limerick County Council
Timeline
- Registration Date
- 3 November 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 24 February 2022
- Grant Date
- 1 April 2022
- Permission Expires
- 31 March 2027
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
changes to planning permission (revised plans) that was previously granted under planning ref 16/901, the development consists of the construction of an extension to an existing dwelling house and ancillary site works
Derraulin , Bruree , Co. Limerick.
the construction of a new dwelling house, site entrance, wastewater treatment system, percolation area and all associated site works
Garryfine , Bruree , Co. Limerick
demolition of an existing agricultural shed and construction of an agricultural shed to include milking parlour, dairy, drafting area and machinery store, collection yard with slatted tank and bulk feed storage bin
Derraulin , Bruree , Co. Limerick
1) constructed detached domestic garage with loft storage and lean-to storage structure to rear, (2) constructed entrance and driveway, (3) elevational changes to existing dwelling including first floor gable windows on north and south elevations and (4) all ancillary site works
Ballyteige Lower , Bruree , Co. Limerick.
domestic garage attached to existing dwelling
Ballyclogh Lower , Bruree , Co. Limerick
the construction of a dwelling house, wastewater treatment system and percolation area, entrance and all ancillary site works
Garryfine , Bruree , Co. Limerick
the construction of an entrance, dwelling house, garage, domestic waste water treatment system with polishing filter together with all associated site works
Ballyteige Lower , Bruree , Co. Limerick
the construction of an entrance, dwelling house, garage, domestic waste water treatment system with polishing filter together with all associated site works
Ballyteige Lower , Bruree , Co. Limerick
the construction of an anaerobic digestion facility to produce renewable biomethane, CO2 (which will be captured), and a bio-based fertiliser from organic material. The total proposed gross floor area of the development (including internal plant areas and ancillary structures) will be c. 5,903 sq.m. The development will consist of the following: • Construction of 2 no. primary digesters (with an overall height of c. 9.1m), a pump house (with a gross floor area (GFA) of c. 279.8 sq.m), and 2 no. post digester tanks (with an overall height of c. 9.1m), located in the northeastern section of the site. • Construction of 2 no. prepits (c. 4.8m in height), a pasteurisation buffer tank (c. 4.8m in height), and a pasteurisation unit (with a maximum height of c. 4.2m), located west of the primary digesters, within the northern section of the site. • Construction of a digestate storage tank (c. 11.3 in height) located centrally on site, to the south of the primary and post digester tanks. • Construction of a digestate treatment building and a feedstock reception building (with a height of c. 12m and a GFA of c. 2,797.2 sq.m) with odour abatement system (with a height of c. 11m to odour abatement stack), located in the northwestern section of site. • Construction of combined heat and power (CHP) unit (c. 2.6m in height and c. 5.6m in height to flue, with a GFA of c. 38.53 sq.m), a biogas boiler (c. 2.6m in height and c. 5.6m in height to flue, with a GFA of c. 12.74 sq.m), a backup boiler (c. 2.6m in height), a gas treatment system (c. 4.2m in height), a biomethane compression system (c. 4.2m in height), and a safety flare (c. 11.3m in height), located south of the digestate storage tank, in the south-east section of the site. • Construction of a CO2 liquefactor (with an overall height of c. 10.7m to top of storage vessels), a propane tank compound accommodating 2 no. propane tanks (c. 1.6m in height), and an ESB substation (with a GFA of c. 23.5 sq.m and a height of c. 3.4m), located in the south-eastern section of the site. • Construction of roofed silage clamps (with a GFA of c. 2,424 sq.m and a height of c. 8.7m) and a fuel storage tank (c. 2m in height), located in the western section of the site. • Construction of a two storey office building (with a GFA of c. 327.4 sq.m and a height of c. 11m) within the western section of the site, adjacent to the site entrance. • Alterations to the adjacent local road including a new site entrance and access arrange
Cappanihane , Bruree , Co. Limerick
construction of a dwelling and detached garage, installation of a treatment unit & polishing filter and carrying out of all associated site works
Ballyclough Upper , Bruree , Co. Limerick.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?