← Back to search

Carmelite Cottages (rear of no.9) , Marsh Road Lagavooren , Drogheda Co. Louth

CONDITIONAL

Planning application 2460020

Louth - Louth County Council

Proposed Development

Permission for the following: 1. Construction of 3no. 3-storey townhouses along with car parking provisions, boundary treatments, hard & soft landscaping 2. All associated site development and infrastructure works. *Significant Further Information received on 04/12/2024*

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    15 Jan 2024

  2. Further information requested

    8 Mar 2024

  3. Further information received

    7 Aug 2024

  4. Decision: CONDITIONAL

    18 Dec 2024

  5. Decision due

    9 Jan 2025

  6. Grant issued

    27 Jan 2025

Application Details

Location
Carmelite Cottages (rear of no.9) , Marsh Road Lagavooren , Drogheda Co. Louth
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Louth County Council
Site Area
0.12 ha
Floor Area
504.75 sq m
Residential Units
3

Timeline

Registration Date
15 January 2024
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
18 December 2024
Grant Date
27 January 2025
Permission Expires
26 January 2030

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

21m
20183N/A13 Mar 2020

Permission for the construction of a first floor side extension to the existing house and for the construction of two number two storey bedroom dwelling houses and all ancillary site development works

No. 9 Carmelite Cottages , Marsh Road Drogheda , Co Louth

22m
19996N/A2 Dec 2019

Permission for the construction of two number two storey two bedroom dwelling houses and all associated site development works

9 Carmelite Cottages , Marsh Road , Drogheda

23m
18702CONDITIONAL31 Aug 2018

Permission for the construction of two number two storey two bedroom dwellinghouses and associated site develoment works.

9 Carmelite Cottages , Marsh Road , Drogheda

23m
18313N/A26 Apr 2018

Permission for the construction of a two storey dwelling house and associated site development works.

9 Carmelite Cottages , Marsh Road , Drogheda

23m
18108N/A14 Feb 2018

PERMISSION for the construction of a two storey dwelling house and associated site development works.

9 Carmelite Cottages , Marsh Road , Drogheda

40m
2460120N/A7 Mar 2024

Permission for first floor extension to the front/side of the existing dwelling house, demolition of existing outbuilding shed, in addition planning permission also sought for two number dwelling houses to the rear and side of No. 14 Carmelite Cottages. The new dwelling houses will be semi detached in form and will be detached from the existing dwelling house, connection into existing sewer network and all associated site development works

14 Carmelite Cottages , Drogheda , County Louth

40m
2560121CONDITIONAL6 Mar 2025

Permission for proposed first floor extension to the front/side of the existing dwelling house, demolition of existing outbuilding shed, in addition planning permission also sought for one number dwelling house to the rear and side of No. 14 Carmelite Cottages. The new dwelling will be detached from the existing dwelling house, connection into existing sewer network and all associated site development works at Carmelite Cottages, Drogheda, County Louth. *Significant Further Information Received on 30/01/2026 - Change in design of the proposed, the revision proposes 3 new houses, instead of one single new house, revised site plan, engineering details and other associated items.*

14 Carmelite Cottages , Drogheda , County Louth

40m
2460117N/A5 Mar 2024

Permission for first floor extension to the front/side of the existing dwelling house, demolition of existing outbuilding shed, in addition planning permission also sought for two number dwelling houses to the rear and side of No. 14 Carmelite Cottages. The new dwelling houses will be semi detached in form and will be detached from the existing dwelling house, connection into existing sewer network and all associated site development works

14 Carmelite Cottages , Drogheda , County Louth

41m
2360148N/A9 Jun 2023

Permission for a proposed first floor extension to the front/side of the existing dwelling house, demolition of existing outbuilding shed, in addition planning permission also sought for two number dwelling houses to the rear and to the side of No. 14 Carmelite Cottages. The new dwelling houses will be semi detached in form and will be detached from the existing dwelling house, connection into existing sewer network and all associated site development works

No. 14 Carmelite Cottages , Drogheda , County Louth

52m
22602CONDITIONAL28 Jul 2022

Permission for the development of electrical charging infrastructure for its Battery Electrical Multiple Units (BEMU) fleet at Drogheda MacBride Railway Station. Comprising of the construction of a modular 10kv ESB/traction substation in the lower car park of the railway station, overhead line charging facilities at 2 no. platforms and 1 no. depot track and electrical cables in ducts form the substation to the charging facilities, together with all necessary ancillary works. The proposed works include: - ESB/Traction substation, comprising two separate adjacent compounds (one for ESB and one for Iarnród Éireann) with - ESB compound comprisin ga building c.4.4m x 4.9m x 2.95m high, dedicated pedestrian and vehicular access, 2 no. dedicated car parking spaces and security fencing; - A number of car parking spaces within the lower car park will be removed to accommodate the proposed substation, reducing the available car parking spaces from 98 to 44 spaces; - Iarnród Éireann compound comprising up to 5 no. modular containerised units, c. 2.6m x 8.0m x 3.5m high, pedestrian access and security fencing; - Ancillary works including landscaping, drainage and utilities; - Electrical cabling works, underground and partially buried in cable troughs between the ESB/Traction substation and overhead line charging infrastructure; - Overhead Line Charging Infrastructure; - Provision of overhead line charging infrastructure at 2 no. platforms and 1 no. depot track; - These structures will be galvanised metal structures from 12 masts and will comprise 2 portal frames, 4 double cantilever and 4 single cantilevers; - Ancillary works, including minor relocation of services, drainage and replacement of steel wire mesh protection on the private access staff pedestrian overbridge. The proposed development is within the curtilage of protected structures, The Drogheda MacBride Station, the associated station complex as well as the Boyne Viaduct: Station buildings include shed, turntable RPS - DB-055; Boyne Viaduct RPS - DB-176. A Natura Impact Statement accompanies this application **Significant further information received on 13.12.22**

Drogheda MacBride Railway Station , Marsh Road , Drogheda Co Louth