← Back to search

DRUMCONLAN , CASTLEBAR , CO. MAYO

CONDITIONAL

Planning application 20624

Mayo - Mayo County Council

Proposed Development

REALIGNMENT OF PART OF EXISTING IDA BUSINESS & TECHNOLOGY PARK INTERNAL ROADWAY, THE DIVERSION/REROUTING OF EXISTING SERVICES WITHIN THE CONFINES OF THE IDA BUSINESS & TECHNOLOGY PARK, THE ALTERATION OF GROUND LEVELS TO THE SOUTH BOUNDARY OF MEISSNER FILTRATION PRODUCTS PROPERTY IMMEDIATELY WEST OF THE IDA BUSINESS & TECHNOLOGY PARK ENTRANCE ROUNDABOUT ON THE N60. ADDITIONAL WORKS TO INCLUDE ALL LANDSCAPING AND GROUND WORKS ASSOCIATED WITH SAME.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    4 Sept 2020

  2. Decision: CONDITIONAL

    27 Oct 2020

  3. Decision due

    29 Oct 2020

  4. Grant issued

    2 Dec 2020

Application Details

Location
DRUMCONLAN , CASTLEBAR , CO. MAYO
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Mayo County Council

Timeline

Registration Date
4 September 2020
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
27 October 2020
Grant Date
2 December 2020
Permission Expires
1 December 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

43m
22318CONDITIONAL27 Apr 2022

The construction of 16,374 square metres combined two and three storey administrative office and warehousing facility expansion, comprised of an office building, roof plant area and construction of warehouse, packaging, shipping & receiving areas including 215 no. car parking spaces, 29 no. Electrical Vehicle Charging Stations, PV solar panels on roof, additional plant equipment, proposed access barriers, signage and all associated site services, landscaping and groundworks.

Castlebar Business & Technology Park , Drumconlan , Castlebar

92m
19810CONDITIONAL15 Oct 2019

PROVISION OF A 3.4M HIGH INSULATED EXTERNAL BOILER HOUSE STRUCTURE AND 5M HIGH EXHAUST FLUE TO THE NORTH WEST OF THE SITE, THE REDUCTION AND ALTERATON OF THE PROPOSED EXTERNAL HARD STANDING AREA ALONG WITH THE OMISSION OF 1 NO. EXTERNAL CHILLER AND PLINTH UPSTAND AND THE RELOCATION OF 1 NO. EXTERNAL CHILLER AND PLINTH UPSTAND. ADDITIONAL WORKS TO INCLUDE ALL LANDSCAPING AND GROUND WORKS ASSOCIATED WITH SAME

CASTLEBAR BUSINESS AND TECHNOLOGY PARK , DRUMCONLAN , CASTLEBAR

101m
19221CONDITIONAL28 Mar 2019

ADDITION OF 415 SQM OF STAFF FACILITIES WITHIN THE EXISTING BUILDING AT FIRST FLOOR LEVEL, A NEW DOUBLE EXTERNAL PERSONNEL DOOR AT GROUND LEVEL AND 2 NO. NEW EXTERNAL LOUVRES ABOVE FIRST FLOOR LEVEL TO THE WESTERN BUILDING ELEVATION, THE ADDITION OF A NEW LOUVRED SCREEN ENCLOSURE AT ROOF LEVEL, THE EXTENSION OF THE EXISTING EXTERNAL HARD STANDING AREA TO THE NORTHWEST OF THE SITE, THE PROVISION OF 2 NO. EXTERNAL CHILLERS AND PLINTH UPSTANDS WITH A 2.4M HIGH PALISADE FENCE ENCLOSURE TO THE NORTHWEST OF THE SITE, THE PROVISION OF A 50M LONG PIPE BRIDGE, 10M OF WHICH WILLL RUN AT 7.5M ABOVE GROUND LEVEL, AND THE ERECTION OF 3 NO. FLAG POLES AND SITE SIGNAGE TO THE SITE ENTRANCE, ADDITIONAL WORKS TO INLCUDE ALL LANDSCAPING AND GROUND WORKS ASSOCIATED WITH SAME

CASTLEBAR BUSINESS AND TECHNOLOGY PARK , DRUMCONLAN , CASTLEBAR

126m
20436CONDITIONAL6 Jul 2020

CONSTRUCT A NEW MEZZANINE FLOOR WITHIN EXISTING INDUSTRIAL BUILDING TO BE USED FOR MANUFACTURING/STORAGE AND THE PROVISION OF ADDITIONAL CAR PARKING AND ALL ANCILLARY SITE WORKS.

CASTLEBAR TECHNOLOGY PARK , DRUMCONLAN , CASTLEBAR

128m
17329CONDITIONAL4 May 2017

CONSTRUCT NEW INDUSTRIAL BUILDING CONSISTING OF OFFICE SPACE, STAFF FACILITIES OVER TWO FLOORS AND LIGHT MANUFACTURING SPACE ALONG WITH A NEW ESB SUBSTATION, CAR PARKING, CYCLE SHELTER, COMPOUND FOR GAS STORAGE, LANDSCAPING, SECURITY FENCE TO SITE BOUNDARIES ALONG WITH ALL ANCILLARY SITE WORKS

CASTLEBAR TECHNOLOGY PARK , DRUMCONLAN , CASTLEBAR

142m
21193CONDITIONAL5 Mar 2021

CONSTRUCTION OF A TWO STOREY MAINTENANCE WORKSHOP CIRCA 7.5M HIGH INCLUDING ANCILLARY OFFICE AREA AT FIRST FLOOR LEVEL AS AN EXTENSION TO THE MAIN BUILDING TO BE SITUATED ON THE EAST SIDE OF THE MAIN BUILDING INCLUDING ALL ASSOCIATED SITE WORKS AND SERVICES

MONEEN ROAD , DRUMCONLAN , CASTLEBAR

171m
19706CONDITIONAL6 Sept 2019

CHANGE OF USE OF EXISTING MANUFACTURING TO GROUND FLOOR OFFICE SPACE, TOGETHER WITH A FIRST FLOOR MEZZANINE FLOOR FOR WAREHOUSING AT REAR OF EXISTING BUILDING, P16/572 AND P07/739 REFERS. THESE WORKS TO BE CARRIED OUT TOGETHER WITH ASSOCIATED SITE SERVICES

CASTLEBAR TECHNOLOGY PARK , MONEEN ROAD , DRUMCONLAN

197m
2360419CONDITIONAL10 Oct 2023

Planning permission to construct dwellinghouse, outbuildings and vehicular entrance with connection to public foul sewer and all ancillary site services

Ashwood , Drumconlon , Castlebar Co Mayo

201m
18308CONDITIONAL3 May 2018

CONSTRUCT DWELLING HOUSE, OUTBUILDINGS AND VEHICULAR ENTRANCE WITH CONNECTION TO PUBLIC FOUL SEWER INCLUDING ALL ANCILLARY SITE SERVICES

ASHWOOD , DRUMCONLON , CASTLEBAR

204m
18653CONDITIONAL24 Aug 2018

A 21M MULTI USER FREE STANDING SUPPORT STRUCTURE CARRYING TELECOMMUNICATIONS EQUIPMENT, TOGETHER WITH ASSOCIATED EXCHANGE CABINETS, FENCING AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

CASTLEBAR RETAIL PARK , KNOCKRAWER , BREAFFY ROAD