← Back to search

KILLEIGH VILLAGE , KILLEIGH , CO OFFALY

CONDITIONAL

Planning application 17339

Offaly - Offaly County Council

Proposed Development

CONSTRUCTION OF 5 NO. TWO-STOREY TOWNHOUSES (4 NO. 3-BED AND 1 NO. 5-BED HOUSES), NEW VEHICULAR ACCESS ROADWAY AND ALL ASSOCIATED SITE WORKS AND SERVICES.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    8 Sept 2017

  2. Further information requested

    2 Nov 2017

  3. Further information received

    16 Jan 2018

  4. Decision: CONDITIONAL

    6 Feb 2018

  5. Decision due

    12 Feb 2018

  6. Grant issued

    22 Mar 2018

Application Details

Location
KILLEIGH VILLAGE , KILLEIGH , CO OFFALY
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Offaly County Council
Site Area
0.0712 ha
Floor Area
2760 sq m
Residential Units
5

Timeline

Registration Date
8 September 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
6 February 2018
Grant Date
22 March 2018
Permission Expires
30 June 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

28m
2660349CONDITIONAL3 Jul 2026

the addition of an off-licence with all ancillary internal modifications in the existing shop

Killeigh , Tullamore , Offaly

43m
18179CONDITIONAL23 Apr 2018

THE REMOVAL OF EXISTING PREFABRICATED DWELLING AND CONSTRUCTION OF A NEW DWELLING HOUSE AND ALL ASSOCIATED SITE WORKS AND SERVICES

KILLEIGH , CO OFFALY

47m
20443CONDITIONAL18 Sept 2020

CHANGE OF USE FROM FORMER HEALTH CENTRE TO PRE SCHOOL AND RETENTION OF THE FACILITY INCLUDING EXISTING BUILDING SIGNAGE AND ANCILLARY SITE WORKS

KILLEIGH COMMUNITY PRE-SCHOOL , KILLEIGH , CO. OFFALY

63m
19320N/A3 Jul 2019

CONVERSION OF OUTBUILDINGS TO SEPERATE LIVING ACCOMMODATION

KILLEIGH , CO OFFALY

63m
17512CONDITIONAL21 Dec 2017

CONSTRUCTION OF TWO NUMBER DWELLING HOUSES, CONNECTION TO SERVICES, ALTERATION TO EXISTING SITE ENTRANCE AND ASSOCIATED SITE WORKS

KILLEIGH , CO. OFFALY

63m
2560122CONDITIONAL14 Apr 2025

as built conversion of original outhousing and extension into a self-contained dwelling including associated site works.

Killeigh , Co. Offaly , Ireland

63m
20436REFUSED15 Sept 2020

CONVERSION OF OUTBUILDINGS TO SEPARATE LIVING ACCOMMODATION, PERMISSION FOR CONSTRUCTION OF 3 NO.TWO STOREY HOUSES, COMPRISING OF 2 NO. END OF TERRACE HOUSES AND 1 MID-TERRACED HOUSE, ALTERATIONS TO PUBLIC FOOTPATH TO IMPROVE SIGHT DISTANCE AT ENTRANCE AND ALL ASSOCIATED SERVICES AND CAR PARKING

KILLEIGH , CO. OFFALY

116m
2560476CONDITIONAL9 Oct 2025

the refurbishment of dwelling including re-slating of roof with repairs to roof timbers and chimneys, replacement of rainwater goods. Proposed new windows, repairs to lime render including removal of sand and cement render. Proposed removal of dilapidated gable at rear and lowering of abutting lean-to wall at front, stitch repairs to cracks in structure, proposed lowering of ground levels around house, refurbishment of existing rear extension with a new roof, external insulation and relocation of a window. Proposed new opening in rear elevation for double doors and new opening in west elevation for new window. Proposed demolition of concrete out-house. To front, new low boundary wall with railings and pedestrian gate to front garden and new vehicular gates. Internally, removal of all vegetation and non-original fixtures and fittings, replacement of all rotten and damaged timbers and treatment of all timbers for fungal and insect infestation, repair to timber floors including joists, floorboards and skirtings, insulation between ground floor joists, removal of non-original coloured concrete floor slab in hall and replacement with new insulated floor slab, repair to lime plaster and breathable insulation to walls, repair to ceilings and cornices, insulation to attic floor and new attic hatch. New bathrooms and utility room in extension, new en-suite and wardrobes in master bedroom, new kitchen and joinery throughout, new plumbing and electrics throughout, new decoration including internal and external painting in breathable paint. All associated site works including services, drainage and hard and soft landscaping. This property is a Protected Structure and formerly an RIC Barracks

Dwelling at Main Street , Killeigh Village , Killeigh Co Offaly

166m
22389N/A5 Aug 2022

CONSTRUCTION OF A NEW SINGLE STOREY EXTENSION TO THE EXISTING PRIMARY SCHOOL CONSISTING OF 2 CLASS SPECIAL EDUCATION NEEDS UNIT INCLUDING REMEDIAL WORKS AND ALL ANCILLARY AND ASSOCIATED SITE WORKS TO INCLUDE LANDSCAPING, EXTERNAL PLAY AREAS AND ADDITIONAL PARKING SPACES

SCOIL SHINCHILL KILLEIGH , TULLAMORE CO. OFFALY , R35 FF20

166m
22437CONDITIONAL25 Aug 2022

CONSTRUCTION OF A NEW SINGLE STOREY EXTENSION TO THE EXISTING PRIMARY SCHOOL CONSISTING OF 2 CLASS SPECIAL EDUCATION NEEDS UNIT INCLUDING REMEDIAL/DEMOLITION WORKS AND ALL ANCILLARY AND ASSOCIATED SITE WORKS TO INCLUDE LANDSCAPING, EXTERNAL PLAY AREAS AND ADDITIONAL PARKING SPACES

SCOIL SHINCHILL KILLEIGH , TULLAMORE CO. OFFALY , R35 FF20

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?