CLONOGHIL UPPER , BIRR , CO. OFFALY
CONDITIONALPlanning application 21492
Offaly - Offaly County Council
Proposed Development
BUILDING NEW DWELLING HOUSE, DOMESTIC GARAGE/FUEL SHED, INSTALL SEPTIC TANK WITH PERCOLATION AREA AND ALL ANCILLARY SITE WORKS
View the full application file on the council's planning portal →Application Timeline
Application received
9 Aug 2021
Further information requested
1 Oct 2021
Further information received
19 Oct 2021
Decision due
15 Nov 2021
Decision: CONDITIONAL
15 Nov 2021
Grant issued
21 Dec 2021
Application Details
- Location
- CLONOGHIL UPPER , BIRR , CO. OFFALY
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Offaly County Council
- Site Area
- 0.302 ha
- Floor Area
- 379 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 9 August 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 15 November 2021
- Grant Date
- 21 December 2021
- Permission Expires
- 20 December 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
CONTINUED USE OF THE EXISTING 30 METRE HIGH, FREE STANDING MONOPOLE COMMUNICATION STRUCTURE, CARRYING ANTENNAE AND COMMUNICATION DISHES WITHIN AN EXISTING 2.4 METRE HIGH PALISADE FENCE COMPOUND PREVIOUSLY GRANTED TEMPORARY PERMISSIN LPA REF 12/102
ESB TELECOMS LTD TELECOMMUNICATION COMPOUND AT ESB BIRR 38kV SUBSTATION , CLONOGHIL UPPER , BIRR
CONSTRUCTION OF 7NO. INDUSTRIAL UNITS, ENTRANCE AND ALL ANCILLARY SITE WORKS LOCATED TO THE REAR AND SIDE OF OUR EXISTING INDUSTRIAL UNITS
@ UNITS 1-6 SYNGCFIELD INDUSTRIAL ESTATE CLONGHIL UPPER , BIRR , CO. OFFALY
THE CONSTRUCTION OF 7 NO. INDUSTRIAL UNITS, ENTRANCE AND ALL ANCILLARY SITE WORKS LOCATED TO THE REAR AND SIDE OF EXISTING INDUSTRIAL UNITS
UNITS 1-6 SYNGEFIELD INDUSTRIAL ESTATE , CLONOGHIL UPPER , BIRR CO. OFFALY
CHANGES TO ORIGINAL PLANNING PERMISSION REFERENCE NUMBER PD1049 FOR THE CONSTRUCTION OF A SINGLE STOREY FLAT ROOF EXTENSION TO THE REAR OF THE EXISTING DWELLING AS-BUILT WITH ASSOCIATED SITE WORKS
AONACH SYNGEFIELD , BIRR , CO. OFFALY
THE REFURBISHMENT AND ALTERATIONS TO THE EXISTING DWELLING WHICH WILL INCLUDE THE FOLLOWING: (A) THE REMOVAL OF EXISTING CHIMNEY STACKS AND REPLACEMENT OF EXISTING ROOF TO INCLUDE ROOF LIGHTS AND REAR DORMER WINDOW TO PROVIDE FOR ATTIC CONVERSION (B) REPLACEMENT OF ALL EXISTING WINDOWS & DOORS WHICH INCLUDE ALTERATIONS TO REAR EXISTING WINDOW AND DOOR SIZE/POSITIONS (C) THE DEMOLITION OF 1NO. EXISTING DOMESTIC GARAGE AND CONSTRUCTION OF 1NO. NEW DOMESTIC GARAGE (D) ALL ASSOCIATED SITE DEVELOPMENT WORKS TO COMPLETE THE DEVELOPMENT
SYNGEFIELD , CLONOGHILL UPPER , BIRR CO. OFFALY
THE INSTALLATION OF A ROOFTOP SOLAR PHOTOVOLTAIC ARRAY (1,339.9 SQ.M) ON EXISTING FACTORY BUILDINGS AND ALL ASSOCIATED ELECTRICAL INFRASTRUCTURE
BIRR ENTERPRISE CENTRE SYNGEFIELD , BIRR CO.OFFALY , R42EK09
THE INSTALLATION OF A ROOFTOP SOLAR PHOTOVOLTAIC ARRAY ( 1,339.3 SQ.M ) ON EXISTING FACTORY BUILDINGS AND ALL ASSOCIATED ELECTRICAL INFRASTRUCTURE. THIS DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
BIRR ENTERPRISE CENTRE SYNGEFIELD , BIRR , CO.OFFALY
THE INSTALLATION OF A ROOFTOP SOLAR PHOTOVOLTAIC ARRAY (RED III) (1,339.3 SQ.M) ON EXISTING FACTORY BUILDINGS AND ALL ASSOCIATED ELECTRICAL INFRASTRUCTURE. THIS DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE RENEWABLE ENERGY DIRECTIVE III ( DIRECTIVE (EU) 2023/2413) AND IT IS IMPORTANT TO NOTE THAT THE PLANNING APPLICATION MAY BE SUBJECT TO SECTION 34D OF THE PLANNING AND DEVELOPMENT ACT 2000, AS AMENDED. WHEN A NOTICE ISSUES IN ACCORDANCE WITH SECTION 34D(B), THE PROVISIONS OF ARTICLE 26A OF THE PLANNING AND DEVELOPMENT REGULATIONS 2001 TO 2025 SHALL APPLY
BIRR ENTERPRISE CENTRE SYNGEFIELD , BIRR , CO.OFFALY
THE INSTALLATION OF A ROOFTOP SOLAR PHOTOVOLTAIC ARRAY (1,339.3 SQ.M) ON EXISTING FACTORY BUILDINGS AND ALL ASSOCIATED ELECTRICAL INFRASTRUCTURE
BIRR ENTERPRISE CENTRE , SYNGEFIELD BIRR , CO.OFFALY
a new dwelling house, domestic garage, new site entrance, treatment system and percolation area and all associated siteworks
Clonoghil Upper , Birr , Co. Offaly
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?