Proposed Development
- 1)CONSTRUCTION OF A NEW FARM BUILDING FOR THE HOUSING OF LIVESTOCK OVER AND INCLUDING AN UNDERGROUND SLATTED SLURRY STORAGE TANK, COMPLETED WITH ASSOCIATED SITEWORKS
- 2)CONSTRUCTION OF A NEW FARM BUILDING FOR THE HOUSING OF LIVESTOCK INCLUDING LIVESTOCK HANDLING UNIT, COMPLETED WITH ASSOCIATED SITEWORKS
- 3)CONSTRUCTION OF A NEW FARMYARD DUNGSTEAD MANURE PIT, COMPLETED WITH ASSOCIATED SITEWORKS,
- 4)CONSTRUCTION OF A NEW ENTRANCE INTO FARMYARD, COMPLETED WITH ASSOCIATED SITEWORKS
Application Timeline
Application received
9 Nov 2021
Application withdrawn
19 Jan 2022
Application Details
- Location
- DERRYIRON , RHODE , CO. OFFALY
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Offaly County Council
- Site Area
- 0.38 ha
Timeline
- Registration Date
- 9 November 2021Other applications received that week
- Status
- WITHDRAWN
- Decision
- N/A
- Withdrawn
- 19 January 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
(1) CONSTRUCT A NEW FARM BUILDING FOR THE HOUSING OF LIVESTOCK OVER AND INCLUDING AN UNDERGROUND SLATTED SLURRY STORAGE TANK, COMPLETED WITH ASSOCIATED SITEWORKS; (2) PERMISSION TO CONSTRUCT A NEW FARM BUILDING FOR THE HOUSING OF LIVESTOCK INCLUDING LIVESTOCK HANDLING UNIT, COMPLETED WITH ASSOCIATED SITEWORKS; (3) PERMISSION TO CONSTRUCT A NEW FARMYARD DUNGSTEAD MANURE PIT, COMPLETED WITH ASSOCIATED SITEWORKS; AND (4) PERMISSION TO CONSTRUCT A NEW ENTRANCE INTO FARMYARD, COMPLETED WITH ASSOCIATED SITEWORKS
DERRYIRON , RHODE , CO. OFFALY
CONTINUED USE OF AN EXISTING GUYED WIND MONITORING MAST, WITH INSTRUMENTS, 100M IN HEIGHT ON ITS LANDS AT BALLYBEG BOG, DERRYIRON, CO OFFALY FOR A FURTHER PERIOD OF THREE YEARS. THE PURPOSE OF THE MAST IS TO ASSESS THE SUITABILITY OF THE COMPANY'S ADJACENT LANDS FOR WIND FARM DEVELOPMENT. PREVIOUS PLANNING APPLICATION REFERENCE NUMBER:PL13/242
BALLYBEG BOG , DERRYIRON , CO OFFALY
CONTINUED USE OF AN EXISTING GUYED WIND MONITORING MAST, WITH INSTRUMENTS, 100M IN HEIGHT FOR A FURTHER PERIOD OF THREE YEARS. THE PURPOSE OF THE MAST IS TO ASSESS THE SUITABILITY OF THE COMPANY'S ADJACENT LANDS FOR WIND FARM DEVELOPMENT. PREVIOUS PLANNING APPLICATION REFERENCE NUMBERS: PL13/242, PL19/315 (OFFALY COUNTY COUNCIL) AND PL19.243080 (AN BORD PLEANÁLA)
BALLYBEG BOG , DERRYIRON , CO. OFFALY
CONTINUED USE OF AN EXISTING GUYED WIND MONITORING MAST, WITH INSTRUMENTS, 100M IN HEIGHT FOR A FURTHER PERIOD OF THREE YEARS. THE PURPOSE OF THE MAST IS TO ASSESS THE SUITABILITY OF THE COMPANY'S ADJACENT LANDS FOR WIND FARM DEVELOPMENT. PREVIOUS PLANNING APPLICATION REFERENCE NUMBERS: PL13/242, PL19/315 (OFFALY COUNTY COUNCIL) AND PL19.243080 (AN BORD PLEANALA)
BALLYBEG BOG , DERRYIRON , CO. OFFALY
to demolish part of, alter, renovate and extend existing dwelling. Permission is also sought to construct a garage, alter existing entrance, install a new wastewater treatment system and polishing filter & decommission existing septic tank and all associated site works
Coolcor , Rhode , Co.Offaly.
to demolish part of, alter, renovate and extend existing dwelling. Permission is also sought to construct a garage, alter existing entrance, install a new wastewater treatment system and polishing filter & decommission existing septic tank and all associated site works
Coolcor , Rhode , Co.Offaly.
DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE AND UTILISATION TECHNOLOGY TO PROVIDE RENWABLE ENERGY AND ELECTRICAL GRID SUPPORT SERVICES ON A 2.45-HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) OPEN AREA FEEDSTOCK RECEPTION BUNKERS (GROSS AREA OF 425.58SQM), WHICH WILL PROVIDE FOR THE INTAKE AND TEMPORARY STORAGE OF BIOMASS MATERIAL FOR GASIFICATION, (II) OFFICE, WELFARE AND CONTROL ROOM BUILDING (GROSS AREA OF 110.90SQM AND 5.145M), (III) GASIFICATION PLANT (GROSS AREA OF 1,178SQM AND HEIGHT OF 20.87M)) WHICH WILL CONVERT BIOMASS INTO SYNTHETIC GAS (SYNGAS), (IV) GASIFICATION CONTROL BUILDING (GROSS AREA OF 36.97SQM AND HEIGHT OF 3.05M), (V) METHANATION UNIT (GROSS AREA OF 429SQM AND HEIGHT OF 12.83M) WHICH WILL CONVERT SYNGAS INTO RENEWABLE GAS (RNG), (VI) RNG FILLING AREA (GROSS AREA OF 451.63SQM), (VII) 2NO. BUNDED THERMAL ENERGY STORAGE TANKS (GROSS AREA OF 78.12SQM AND HEIGHT OF 10M), (VIII) GAS ENGINE COMPOUND (GROSS AREA OF 246.44SQM) CONTAINING 5NO. CONTAINERISED COMBINED HEAT AND POWER (CHP) GAS ENGINES (EACH 5.55M IN HEIGHT), (IX) ELECTRICAL SUBSTATION (GROSS AREA OF 910.8SQM) CONTAINING SWITCHYARD, ESB SUBSTATION BUILDING (GROSS AREA OF 110.62SQM AND HEIGHT OF 5.96M), ANCILLARY ELECTRICAL PLANT AND BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS TO THE SOUTH OF THE DEVELOPMENT SITE, (X) AN OPEN AREA COMPOUND CONTAINING SOLID OXIDE FUEL ELECTROLYSIS CELL (SOFEC) ENCLOSURES WHICH WILL CONVERT CARBON DIOXIDE, STEAM AND METHANE INTO RENEWABLE ENERGY, (XI) 2NO. STORE CONTAINERS, CONTAINERISED STEAM ENGINE AND CONTAINERISED HEAT RECOVERY PLANT (EACH OF GROSS AREA OF 29.77M AND HEIGHT OF 2.9M), (XII) SYNGAS AND FUEL STORAGE TANKS (GROSS AREA OF 295SQM), AND (XIII) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMETER LANDSCAPED SOIL BERMS WITH TREE SCREENING, PERIMETER FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT THE DEVELOPMENT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUSINESS PARK PROVIDING ACCESS TO THE R400, CAR PARKING, LIGHTING, INTERNAL ACCESS ROADS, WEIGHBRIDGE, CARBON FILTER, PROCESS WATER AND FIREFIGHTING WATER STORAGE TANKS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER
COOLCOR , RHODE , CO. OFFALY
DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE AND UTILISATION TECHNOLOGY TO PROVIDE RENWABLE ENERGY AND ELECTRICAL GRID SUPPORT SERVICES ON A 2.45-HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) OPEN AREA FEEDSTOCK RECEPTION BUNKERS (GROSS AREA OF 425.58SQM), WHICH WILL PROVIDE FOR THE INTAKE AND TEMPORARY STORAGE OF BIOMASS MATERIAL FOR GASIFICATION, (II) OFFICE, WELFARE AND CONTROL ROOM BUILDING (GROSS AREA OF 110.90SQM AND 5.145M), (III) GASIFICATION PLANT (GROSS AREA OF 1,178SQM AND HEIGHT OF 20.87M)) WHICH WILL CONVERT BIOMASS INTO SYNTHETIC GAS (SYNGAS), (IV) GASIFICATION CONTROL BUILDING (GROSS AREA OF 36.97SQM AND HEIGHT OF 3.05M), (V) METHANATION UNIT (GROSS AREA OF 429SQM AND HEIGHT OF 12.83M) WHICH WILL CONVERT SYNGAS INTO RENEWABLE GAS (RNG), (VI) RNG FILLING AREA (GROSS AREA OF 451.63SQM), (VII) 2NO. BUNDED THERMAL ENERGY STORAGE TANKS (GROSS AREA OF 78.12SQM AND HEIGHT OF 10M), (VIII) GAS ENGINE COMPOUND (GROSS AREA OF 246.44SQM) CONTAINING 5NO. CONTAINERISED COMBINED HEAT AND POWER (CHP) GAS ENGINES (EACH 5.55M IN HEIGHT), (IX) ELECTRICAL SUBSTATION (GROSS AREA OF 910.8SQM) CONTAINING SWITCHYARD, ESB SUBSTATION BUILDING (GROSS AREA OF 110.62SQM AND HEIGHT OF 5.96M), ANCILLARY ELECTRICAL PLANT AND BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS TO THE SOUTH OF THE DEVELOPMENT SITE, (X) AN OPEN AREA COMPOUND CONTAINING SOLID OXIDE FUEL ELECTROLYSIS CELL (SOFEC) ENCLOSURES WHICH WILL CONVERT CARBON DIOXIDE, STEAM AND METHANE INTO RENEWABLE ENERGY, (XI) 2NO. STORE CONTAINERS, CONTAINERISED STEAM ENGINE AND CONTAINERISED HEAT RECOVERY PLANT (EACH OF GROSS AREA OF 29.77M AND HEIGHT OF 2.9M), (XII) SYNGAS AND FUEL STORAGE TANKS (GROSS AREA OF 295SQM), AND (XIII) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMETER LANDSCAPED SOIL BERMS WITH TREE SCREENING, PERIMETER FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT THE DEVELOPMENT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUSINESS PARK PROVIDING ACCESS TO THE R400, CAR PARKING, LIGHTING, INTERNAL ACCESS ROADS, WEIGHBRIDGE, CARBON FILTER, PROCESS WATER AND FIREFIGHTING WATER STORAGE TANKS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER. A NATURA IMPACT STATEMENT (NIS) HAS BEEN PREPARED AND ACCOMPANIES THE PLANNING APPLICATION
COOLCOR , RHODE , CO OFFALY
a domestic shed / fuel store and any associated works
Knockdrin , Rhode , Co. Offaly
(i) one new super capacitor container, (ii) two new two-storey modular DC containers, (iii) one new control room container, (iv) one new transformer and concrete bund, (v) one new IPP module, (vi) one new ESB MV substation module, (vii) one new PCS module, (viii) internal site access roads and connection to Rhode Green Energy Park road network, (ix) all civil engineering and electrical engineering work, including temporary construction compound, surface water and foul water drainage, landscaping, lighting and security fencing
Coolcor , Rhode , County Offaly
The submission window has closed
Observations on this application closed on Monday 13 December 2021, five weeks after it was received. The authority cannot accept a late submission.