← Back to search

Clonin , Co. Offaly , Ireland

N/A

Planning application 2460044

Offaly - Offaly County Council

Proposed Development

a ten-year permission for construction of a new site entrance and access track to serve the already consented development refs; PL2/16/246 & 19/194.

View the full application file on the council's planning portal →

Application Details

Location
Clonin , Co. Offaly , Ireland
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Offaly County Council
Site Area
0.21 ha

Timeline

Registration Date
16 February 2024
Status
INCOMPLETED APPLICATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

6m
23413N/A8 Nov 2023

A TEN- YEAR LIFECYCLE FOR CONSTRUCTION OF A NEW SITE ENTRANCE AND ACCESS TRACK TO SERVE THE ALREADY CONSENTED DEVELOPMENT REFS; PL2/16/246 & 19/194

CLONIN , CO. OFFALY

6m
2460067CONDITIONAL7 Mar 2024

a ten-year permission for construction of a new site entrance and access track to serve the already consented development refs; PL2/16/246 & 19/194

Clonin Rhode , Co. Offaly , Ireland

122m
22664CONDITIONAL21 Dec 2022

EIRGRID PLC (WITH THE CONSENT AND APPROVAL OF THE ELECTRICITY SUPPLY BOARD (ESB)), INTENDS TO APPLY FOR PERMISSION FOR DEVELOPMENT AT SITE OF APPROXIMATELY 1 HECTARE AT DERRYIRON 110KV SUBSTATION, CLONIN, RHODE, CO. OFFALY. DEVELOPMENT CONSISTING OF WORKS TO UPGRADE THE EXISTING SUBSTATION INCLUDING: THE INSTALLATION OF ADDITIONAL AIR INSULATED SWITCHGEAR ELECTRICAL APPARATUS (APPROXIMATELY 7M IN HEIGHT) TO FACILITATE THE PROVISION OF A 110KV BUSBAR; INSTALLATION OF 3 NO. ADDITIONAL BAYS (EACH CONSISTING OF BUSBAR DISCONNECTS, SECTIONALISERS, CIRCUIT BREAKERS, CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS, LINE TRAPS, COUPLING CAPACITORS AND OTHER ELECTRICAL APPARATUS); AN EXTENSION TO THE NORTH OF THE EXISTING CONTROL BUILDING (APPROXIMATELY 73 SQUARE METERS) TO PROVIDE ACCOMMODATION FOR CABINETS, OTHER ELECTRICAL APPARATUS AND A BATTERY ROOM; INSTALLATION OF 2 NO. CIRCUIT BYPASS ARRANGEMENTS (APPROXIMATELY 14M AND APPROXIMATELY 4M IN HEIGHT, RESPECTIVELY) TO FACILITATE NORMAL OPERATION OF THE SUBSTATION DURING CONSTRUCTION; AND AN EXTENSION TO THE HARDSTAND COMPOUND (APPROXIMATELY 0.03 HECTARES). THE DEVELOPMENT WILL ALSO CONSIST OF: ALL ANCILLARY AND ASSOCIATED ELECTRICAL WORKS TO FACILITATE THE PROPOSED DEVELOPMENT; AND ALL OTHER ASSOCIATED SITE EXCAVATION, INFRASTRUCTURAL AND SITE DEVELOPMENT WORKS ABOVE AND BELOW GROUND, INCLUDING SITE PREPARATION WORKS, SITE CLEARANCE AND LEVELLING; HARDSTANDING, INTERNAL ACCESS TRACKS AND TEMPORARY CONSTRUCTION COMPOUND; EARTHGRID, SURFACE WATER DRAINAGE NETWORK; PALISADE FENCING (APPROXIMATELY 2.7M HIGH) AND GATES; AND LANDSCAPING.

DERRYIRON 110KV SUBSTATION , CLONIN RHODE , CO. OFFALY

128m
2560345CONDITIONAL31 Jul 2025

A 10-year planning permission for works to the existing Derryiron 110 kilovolt (kV) electricity substation comprising (i) an increase to the footprint of the substation compound by 190 square metres (m2) arising from the realignment of the existing palisade fence; (ii) the installation of electrical equipment including circuit breakers, cable sealing ends and voltage transformers; (iii) the installation of approximately 20m of 110kV underground electricity line; and, (iv) all associated ancillary site development works. This planning application is accompanied by an Appropriate Assessment Screening Report

Clonin , Rhode , Co. Offaly

129m
2560299N/A10 Jul 2025

A 10-year planning permission for works to the existing Derryiron 110 kilovolt (kV) electricity substation comprising (i) an increase to the footprint of the substation compound by 190 square metres (m2) arising from the realignment of the existing palisade fence; (ii) the installation of electrical equipment including circuit breakers, cable sealing ends and voltage transformers; (iii) approximately 20m of 110kV underground electricity line; and, (iv) all associated ancillary site development works. This planning application is accompanied by an Appropriate Assessment Screening Report.

Clonin , Rhode , Co. Offaly

151m
2560110N/A3 Apr 2025

an Operations Building with a floor area of approximately 285m2. The Operations Building will consist of: - 1 No. Kitchen/Mess - 1 No. Locker Room including welfare facilities - 1 No. Accessible Toilet - 1 No. Toilet - 3 No. Offices - 1 No. Workshop/Store - 2 No. Server/IT store - 1 No. Meeting room - 1 No. External compound - 6 No. Permanent storage containers - Roof mounted solar panels - Connection to existing water, storm water and sewage infrastructure at Rhode Green Energy Park - Temporary cabins to be used during the construction phase - External parking, EV charging, lighting, CCTV, fencing etc. and ancillary site works.

Coolcor , Rhode , Co. Offaly

151m
2560129CONDITIONAL17 Apr 2025

an Operations Building with a floor area of approximately 285m2. The Operations Building will consist of: - 1 No. Kitchen/Mess - 1 No. Locker Room including welfare facilities - 1 No. Accessible Toilet - 1 No. Toilet - 3 No. Offices - 1 No. Workshop/Store - 2 No. Server/IT store - 1 No. Meeting room - 1 No. External compound - 6 No. Permanent storage containers - Roof mounted solar panels - Connection to existing water, storm water and sewage infrastructure at Rhode Green Energy Park - Temporary cabins to be used during the construction phase - External parking, EV charging, lighting, CCTV, fencing etc. and ancillary site works

Coolcor , Rhode , Co. Offaly

178m
19161CONDITIONAL10 Apr 2019

DEVELOPMENT OF AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE 20MW OF SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A 0.95 HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) AN OPEN AREA BATTERY ENERGY STORAGE SYSTEM (BESS) COMPOUND (AREA OF 563 SQM) CONTAINING 8 NO. BATTERY AND CONTROL SYSTEM ENCLOSURES (C. 12.2M LONG X 2.5M WIDE X 4M HIGH), (II) SINGLE STOREY SWITCHGEAR BUILDING (C. 18M LONG X 15M WIDE X 3M HIGH) CONTAINING ELECTRICIAL PLANT AND CONTROL ROOM, (III) BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT VIA OVERHEAD CABLE TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS ADJOINING THE SITE TO THE SOUTH, AND (IV) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMIETER PALISADE FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUISINESS PARK PROVIDING ACCESS TO THE R400, LANDSCAPING, LIGHTING, CAR PARKING, INTERNAL ACCESS ROADS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER

COOLCOR , RHODE , CO. OFFALY

224m
2460472N/A28 Nov 2024

(i) two new capacitor containers each measuring 13.7m x 2.7m x 2.9m placed on an existing concrete slabs, (ii) one new inverter container measuring 5.9m x 2.35m x 2.37m placed on an existing concrete slab, (iii) access to the site is from the L-10093-2 which connects the R400 regional road, (v) all civil engineering and electrical engineering works to provide for connection to the electricity distribution network on site via the existing medium voltage substation within the site.

Coolcor , Rhode , County Offaly

224m
2460479CONDITIONAL3 Dec 2024

(i) two new capacitor containers each measuring 13.7m x 2.7m x 2.9m placed on existing concrete slabs, (ii) one new inverter container measuring 5.9m x 2.35m x 2.37m placed on an existing concrete slab, (iii) access to the site is from the L-10093-2 which connects the R400 regional road, (v) all civil engineering and electrical engineering works to provide for connection to the electricity distribution network on site via the existing medium voltage substation within the site.

Coolcor , Rhode , County Offaly

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.