Galros East Whigsborough Ballycollin , and Eglish , County Offaly
N/APlanning application 2660563
Offaly - Offaly County Council
Proposed Development
RENEWABLE ENERGY DIRECTIVE III (RED III) DEVELOPMENT.The proposed development (to be known as ‘Cush Wind Farm Phase II’) for which planning permission is sought will comprise: I.Three (3 no.) wind turbines with an overall ground-to-blade tip height ranging from 199.1 metres to 200 metres, a rotor diameter ranging from 158 metres to 175 metres, and a hub height ranging from 111.6 metres to 120.9 metres; II. Associated turbine foundations, crane hardstanding areas and temporary turbine component storage and assembly areas; III. Approximately 1.7 kilometres of new internal wind farm access tracks; IV.An electrical switch room building with a gross floor area of approximately 96.2 square metres, within a compound of approximately 429 square metres, enclosed by approximately 2.6 metre high palisade fencing and gates; V. Underground electrical and communications cabling connecting the proposed turbines to the adjoining permitted Cush Wind Farm (An Coimisiún Pleanála Reference ABP-318816-24) and to the proposed electrical switch room; VI. One (1 no.) site entrance from the L300321 local road to serve the electrical switch room; VII. Use of the construction phase site entrance from the N62 national road, the operation phase site entrance from the L300321 local road, and the temporary construction compounds permitted as part of Cush Wind Farm; VIII. All associated and ancillary site development, excavation, construction, landscaping, spoil deposition and reinstatement works, including the provision of site drainage infrastructure and environmental mitigation measures; and IX. A 35-year operational life from the date of commissioning of the entire proposed development. The site of the proposed development has a total area of approximately 87 hectares. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been prepared in respect of the proposed development and accompany the planning application. The EIAR and NIS also assess the proposed development in combination with the following off-site associated infrastructure and works: •A grid connection comprising approximately 5 kilometres of 33 kV underground electricity line connecting the proposed electrical switch room in Eglish to the national electricity network, through the townlands of Eglish, Ballynaguilsha, Shanacloon, Cloncarban, Clonbeale Beg Glebe and Mullanafawnia, County Offaly. • Accommodation works along the turbine component haul route from the Port of Galway to the win
Application Timeline
Application received
28 Oct 2026
Decision due (upcoming)
22 Dec 2026
Application Details
- Location
- Galros East Whigsborough Ballycollin , and Eglish , County Offaly.
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Offaly County Council
- Site Area
- 87.12 ha
Timeline
- Registration Date
- 28 October 2026Other applications received that week
- Status
- NEW APPLICATION
- Decision
- N/A
- Decision Due
- 22 December 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
an extension and alterations to an existing dwelling, new detached garage, new site entrance, treatment system and percolation area and all associated site works
Whigsborough , Fivealley , Birr Co. Offaly
(I) THE CONTINUED OPERATION OF THE EXISTING 80 METRE METEOROLOGICAL MAST, WHICH WAS ERECTED AS EXEMPTED DEVELOPMENT IN ACCORDANCE WITH CLASS 20A, SCHEDULE 2, OF THE PLANNING AND DEVELOPMENT REGULATIONS 2001 (AS AMENDED), AND ALL ANCILLARY INFRASTRUCTURE AND ASSOCIATED SITE DEVELOPMENT AND REINSTATEMENT WORKS; AND (II) THE INCREASE IN HEIGHT OF THE EXISTING METEOROLOGICAL MAST FROM 80 METRES TO A HEIGHT OF 100 METRES. THE OPERATIONAL LIFETIME OF THE PROPOSED DEVELOPMENT WILL BE UP TO FIVE YEARS. THIS PLANNING APPLICATION IS ACCOMPANIED BY AN APPROPRIATE ASSESSMENT SCREENING REPORT
GALROS WEST , COUNTY OFFALY
(I) THE EXISTING 80 METRE METEOROLOGICAL MAST, WHICH WAS ERECTED AS EXEMPTED DEVELOPMENT IN ACCORDANCE WITH CLASS 20A, SCHEDULE 2, OF THE PLANNING AND DEVELOPMENT REGULATIONS 2001 (AS AMENDED), AND ALL ANCILLARY INFRASTRUCTURE AND ASSOCIATED SITE DEVELOPMENT AND REINSTATEMENT WORKS; AND (II) PERMISSION TO INCREASE THE HEIGHT OF THE EXISTING METEOROLOGICAL MAST FROM 80 METRES TO A HEIGHT OF 100 METRES. THE OPERATIONAL LIFETIME OF THE PROPOSED DEVELOPMENT WILL BE UP TO FIVE YEARS. THIS PLANNING APPLICATION IS ACCOMPANIED BY AN APPROPRIATE ASSESSMENT SCREENING REPORT
GALROS WEST FIVEALLEY , BIRR , CO. OFFALY
CONSTRUCTION OF A NEW DWELLING HOUSE, FORM NEW ENTRANCE, INSTALL EFFLUENT TREATMENT UNIT WITH PERCOLATION AREA & ALL ASSOCIATED SITE WORKS
GALROS EAST , FIVEALLEY , BIRR CO OFFALY
CONSTRUCTION OF A NEW SINGLE STOREY DWELLING, NEW VEHICULAR ENTRANCE, DRIVEWAY, WASTE WATER TREATMENT SYSTEM, STORM WATER SOAKAWAYS, AND ALL ASSOCIATED SITE WORKS
EGLISH FIVEALLEY , BIRR , CO. OFFALY
DOMESTIC GARAGE, FUEL SHED AND ALL ASSOCIATED SITE WORKS AND SERVICES
COOLOGE FIVEALLEY , BIRR , CO. OFFALY
A) demolition of the existing side extension; B) construction of a new front porch; and C) construction of a new two storey extension to the rear and a single-storey extension to the side. Permission is also sought for a new treatment system and percolation area and a new site entrance together with all associated site works.
Coologe , Fivealley , Birr
A) demolition of the existing side extension; B) construction of a new front porch; and C) construction of a new two storey extension to the rear and a single-storey extension to the side. Permission is also sought for a new treatment system and percolation area and a new site entrance together with all associated site works
Coologe , Fivealley , Birr
CONSTRUCTION OF A DWELLING HOUSE, DETACHED DOMESTIC GARAGE, INSTALLATION OF SEPTIC TANK WITH PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
COOLOGE FIVEALLEY , BIRR , CO. OFFALY
AN EXTENSION TO THE EXISTING DWELLING, ALTERATIONS TO THE EXISTING DWELLLING AND ALL ASSOCIATED SITE WORKS
BOOLINARIG BIG , BIRR , CO. OFFALY
Affected by this application?
Open for submissionsObservations close on Tuesday 1 December 2026, five weeks from the date the application was received. The fee is €20, and only planning grounds count.
Check if you have grounds — freeTwo questions, no payment: we'll tell you whether what concerns you is something the council can actually take into account.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?