Proposed Development

an electricity storage facility comprising a Battery Energy Storage System (BESS) within a total site area of 16.26ha. The development will include one electrical compound, battery storage enclosures (BSEs), power conversion systems on concrete support structures, auxiliary transformers, spares containers, LV switchgear room, aggregation panel with LV pillars, compound fencing, attenuation pond, fire tanks, indicative buried 33kV buried cable with watercourse crossing to switch room in approved substation under ACP reference 323988, upgraded entrance, new and upgraded access tracks, crane hardstanding, associated electrical ducting, stock fencing, gates, lighting /CCTV poles and system, landscaping works, all other ancillary and miscellaneous site works including site clearance. This application seeks a 10-year permission from the date of grant for construction of the Proposed development and an operational life of 40 years from the date of commissioning of the Proposed Development. A Natura Impact Statement (NIS) has been submitted with this application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    6 Nov 2026

  2. Decision due (upcoming)

    9 Jan 2027

Application Details

Location
Ballyteige Little , and Ballyteige Big , Co.Offaly
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Offaly County Council
Site Area
16.26 ha

Timeline

Registration Date
6 November 2026Other applications received that week
Status
NEW APPLICATION
Decision
N/A
Decision Due
9 January 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
2660529N/A9 Oct 2026

the Construction of an electricity storage facility comprising a Battery Energy Storage System (BESS), within a total site area of up to 16.26ha, to include one electrical compound, battery storage enclosures (BSEs), power conversion systems on concrete support structures, auxiliary transformer, spares container, LV switchgear room, aggregation panel with LV pillar, attenuation pond, fire tanks, indicative buried 33kV buried cable with watercourse crossing to switch room in approved substation under ACP reference 323988, upgraded entrance, new and upgraded access tracks, crane hardstanding, associated electrical ducting, palisade security fencing, stock proof fencing, gates and CCTV system, landscaping works, lighting poles and all other ancillary and miscellaneous site works including site clearance. A Natura Impact Statement accompanies this application and is available for inspection at the planning authority's offices

Site on the Wood of O/Ballyteige , Tullamore , Ballyteige Little and Ballyteige Big Co. Offaly

665m
2165N/A12 Feb 2021

A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES, TO INCLUDE A SINGLE STOREY ELECTRICAL SUBSTATION BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, A TEMPORARY CONSTRUCTION COMPOUND, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS

BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL , TULLAMORE , CO. OFFALY

672m
2560659N/A18 Dec 2025

an amendment to a previously consented development (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares. This planning application is accompanied by a Natura Impact Statement (NIS) This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

Townlands of Ballyteige Little Wood of O Corndarragh Derrynagall or Ballydaly Ardan and Puttaghan , County , Offaly

672m
2660071CONDITIONAL11 Feb 2026

an amendment to a previously consented development (RED III) (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares and comprises of a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III). This planning application is accompanied by a Natura Impact Statement (NIS). This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore , County , Offaly

672m
2660044N/A29 Jan 2026

the amendment to a previously consented development (Planning Reference 2198 by Offaly County Council) comprising of; (i) removal of the 38kV substation and infrastructure within the most northern field (Field 1), (ii) internal access track reduced from c.3.4km to c. 3.2km,relocated and tweaked to include turning areas, (iii) replacement of string inverters instead of combined central inverters and MV transformers, the central MV transformers remain, and increase from 11No. to 12 No., however there will be a reduction in their associated hardstanding areas and the number of string inverters is 128, (iv) table layout updated (reduced), (v) PV angle tilt reduced from 10º and 40º to 10º and 30º, (vi) separation area between infrastructure and OHL towers increased, (vii) an additional badger sett buffer added (viii) temporary construction compound has been relocated from Field 1 to Field 4, (ix) alter Condition No. 10 to increase the boundary fencing from 1.8m-2m high to 2.4m high and reduce in the perimeter fence length, (x) CCTV number increase from 81 to 118 and their locations have been amended, (xi) adjustment of the development period from 5 years to 10 years, and (xii) alter Condition No. 11 to change the operational lifetime from 35 years to 40 years. The planning application area comprises of 60.53hectares and comprises of a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III). This planning application is accompanied by a Natura Impact Statement (NIS). (RED III) This development is covered by the provision of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Townlands of Ballyteige Little Ballyteige Big and Colehill Tullamore , County , Offaly

672m
2198CONDITIONAL3 Mar 2021

A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES, TO INCLUDE A SINGLE STOREY ELECTRICAL SUBSTATION BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, A TEMPORARY CONSTRUCTION COMPOUND, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS

BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL , TULLAMORE , CO. OFFALY

844m
17152N/A3 May 2017

A SLATTED CATTLE SHED WITH UNDERGROUND SLURRY STORE/ SLATTED TANK AND ASSOCIATED CONCRETE WORKS

WOOD OF O ,

845m
17201CONDITIONAL7 Jun 2017

A SLATTED CATTLE SHED WITH UNDERGROUND SLURRY STORE/ SLATTED TANK, AND ASSOCIATED CONCRETE WORKS

WOOD OF O , TULLAMORE , CO. OFFALY

916m
2534N/A4 Apr 2025

THE EXISTING MOBILE HOME STRUCTURE AND EXISTING FOUL WATER HOLDING TANK AND ALL ASSOCIATED EXISTING SITEWORKS AS A THREE-YEAR TEMPORARY DEVELOPMENT. PERMISSION FOR THE CONSTRUCTION OF A DORMER STYLE DWELLING WITH DETACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS

BALLYTEIGE LITTLE , BALLYCOMMON , CO.OFFALY.

916m
20533CONDITIONAL30 Oct 2020

CONSTRUCTION OF A TWO-STOREY DWELLING WITH ATTACHED GARAGE, SEPTIC TANK AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS

BALLYTEIGUE LITTLE , BALLYCOMMON , CO OFFALY

Affected by this application?

Open for submissions
18days left to make a submission

Observations close on Thursday 10 December 2026, five weeks from the date the application was received. The fee is €20, and only planning grounds count.

Check if you have grounds — free

Two questions, no payment: we'll tell you whether what concerns you is something the council can actually take into account.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?