← Back to search

Dunneill Wind Farm , Located in the townland Crowagh or Dunneill Mountain , Ballyglass (ED Dromore) and Tawnadremira

CONDITIONAL

Planning application 22291

Sligo - Sligo County Council

Proposed Development

development consisting of a fifteen (15) year continuation of the operational life of the existing wind farm (SCC Reg. Ref. PL03/619 & ABP Pl. Ref. 21.204790, as amended by SCC Reg. Ref PL10/371 and PL10/388) from the date of expiration (March 2024) of the current permissions. No modifications are proposed to the existing windfarm which comprises the following elements: (a) 13 no. existing Vestas V52 850 kilowatt (kW) wind turbines with a maximum overall blade tip height of 75 metres (m) (b) Existing 1 no. onsite 20 kilovolt (kv) electrical substation compound which includes a control building, welfare facilities, associated electrical plant and equipment, security fencing, associated underground cabling and a foul waste holding tank (c) Existing 1 no. permanent meteorological mast with a height of 50m and an associated concrete platform/base; (d) All associated existing underground electrical and communications cabling connecting the turbines to the on-site substation; (e) Existing site access tracks of circa 3.3 kilometres (km) total length, 3 no. car parking spaces and 13 no. turbine hardstands; (f) 2 No. existing gated site entrances from an unnamed third-class public road which dissects the windfarm site into north and south; (g) Existing site drainage; and (h) All existing ancillary infrastructure, associated site fencing and signage. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been prepared in respect of the proposed development and accompanies this application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Aug 2022

  2. Further information requested

    20 Oct 2022

  3. Further information received

    2 Mar 2023

  4. Decision: CONDITIONAL

    25 Apr 2023

  5. Decision due

    26 Apr 2023

  6. Grant issued

    2 Jun 2023

Application Details

Location
Dunneill Wind Farm , Located in the townland Crowagh or Dunneill Mountain , Ballyglass (ED Dromore) and Tawnadremira
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Sligo County Council

Timeline

Registration Date
26 August 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
25 April 2023
Grant Date
2 June 2023
Permission Expires
23 October 2039

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?