Ballyweelin , Rosses Point , Sligo
CONDITIONALPlanning application 2660392
Sligo - Sligo County Council
Proposed Development
- 1.Construction of a two-storey dwelling house
- 2.Provision of a new site entrance via an existing private laneway
- 3.Provision of new tertiary wastewater treatment system
- 4.And all associated site works
Application Timeline
Application received
24 Sept 2026
Decision: CONDITIONAL
12 Nov 2026
Decision due
18 Nov 2026
Application Details
- Location
- Ballyweelin , Rosses Point , Sligo
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Sligo County Council
- Site Area
- 0.13 ha
- Floor Area
- 0.13 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 24 September 2026Other applications received that week
- Status
- DECISION MADE
- Decision
- CONDITIONAL
- Decision Date
- 12 November 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
to build a domestic shed
Ballyweelin , Rosses Point , Co. Sligo
Permission for retention of sunroom extension constructed to the side of existing dwelling house, Permission for retention of domestic shed constructed on site and all associated works
Coney View , Ballyweelin , Rosses Point Co. Sligo
Permission for retention of bay window and porch constructed to the front of existing dwelling house and all associated works
Mountlands , Ballyweelin , Co. Sligo
construction of a two-storey dwelling house, a proprietary effluent treatment system, and all associated site works, including the use of the existing site entrance
Ballyweelin , Rosses Point , Co. Sligo
The development consists of the construction of a two-storey dwelling house (H-6,400 m (OD-16,800 m )), a proprietary effluent treatment system, and all associated site works, including the use of the existing site entrance.
Ballyweelin , Rosses Point , Co. Sligo
for development consisting of (1) the erection of a new extension to the rear (north) elevation of our existing dwelling house, (2) new bay window to the (east) side elevation at ground floor, (3) remodelling of existing front porch, *(4) alteration to dwelling & garage fenestration, (5) remodel existing vehicular entrance & erect new piers & (6) upgrade existing effluent treatment system, together with all associated site development works
Ballyweelin Td , Rosses Point , Sligo
Retention - The application seeks to retain the existing structure, which serves as a residential dwelling with amenities for single-family occupancy. The development includes two- storey dwelling house to associated work. Original application was GRANTED for a stepped level two-storey design with large open terrace on both ground and first floor levels overlooking the large garden to the rear (South) of the dwelling house. This design was then simplified once construction began in early 1974 to a more conventional two-storey design to allow for better heat retention and energy efficiency. It was felt at the time of construction the stepped level design would lead to large flat roof areas over the ground floor bedrooms which would be difficult to heat and result in high energy costs. This was the only primary reason for the design change. The second significant design change was the removal of a spiral staircase for a traditional straight flight of stairs between ground and first floor.
Ballyweelin , Rosses Point , Sligo
I, JOHN MULLANEY, intend to apply for planning permission for retention of existing dwelling house and all associated works which differs in plan and elevation from that permitted under PL 74/4703 at BALLYWEELIN, ROSSES POINT, CO. SLIGO, F91FK26. The development consists of an EXISTING STRUCTURE TO BE RETAIN WHICH SERVES AS A RESIDENTIAL SINGLE FAMLY DWELLING WITH ALL ASSOCIATED WORKS. Original application was GRANTED for a stepped level two-storey design with large open terrace on both ground and first floor levels overlooking the large garden to the rear (South) of the dwelling house. This design was then simplified once construction began in early 1974 to a more conventional two-storey design to allow for better heat retention and energy efficiency. It was felt at the time of construction the stepped level design would lead to large flat roof areas over the ground floor bedrooms which would be difficult to heat and result in high energy costs. This was the only primary reason for the design change. The second significant design change was the removal of a spiral staircase for a traditional straight flight of stairs between ground and first floor.
Ballyweelin , Rosses Point , Sligo
I, JOHN MULLANEY, intend to apply for planning permission for retention of existing dwelling house and all associated works which differs in plan and elevation from that permitted under PL 74/4703 at BALLYWEELIN, ROSSES POINT, CO. SLIGO, F91FK26. The development consists of an EXISTING STRUCTURE TO BE RETAIN WHICH SERVES AS A RESIDENTIAL SINGLE FAMLY DWELLING WITH ALL ASSOCIATED WORKS. The planning application may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the planning authority during its public opening hours. A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee, €20, within the period of 5 weeks beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions, or may refuse to grant permission.
Ballyweelin , Rosses Point , Sligo
retention of existing dwelling house and all associated works which differs in plan and elevation from that permitted under PL 74/4703. The development consists of an existing structure to be retain which serves as a residential single family dwelling with all associated works
Ballyweelin , Rosses Point , Sligo
The submission window has closed
A decision issued on this application, so observations can no longer be made. Anyone who made a submission during the five-week window can appeal to An Coimisiún Pleanála within four weeks of the decision — until Thursday 10 December 2026 — for a fee of €220.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?