Site 14B1, Road 3A, Phase 3, Greenogue Ind. Est., Rathcoole, Co. Dublin
Withdraw the ApplicationPlanning application S02A/0073
Dublin - South Dublin County Council
Proposed Development
Construct a yard for the dry recylcing of waste timber to manufacture pulp substitute fibre together with office, store, service utilities and site development works, sub- station, 6m high screen wall, landscaping, planting, paving and parking.
Application Timeline
Application received
19 Jul 2002
Decision: Withdraw the Application
30 Sept 2003
Application Details
- Location
- Site 14B1, Road 3A, Phase 3, Greenogue Ind. Est., Rathcoole, Co. Dublin.
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 4856 ha
- Floor Area
- 69 sq m
Timeline
- Registration Date
- 19 July 2002
- Status
- Decision
- Decision
- Withdraw the Application
- Decision Date
- 30 September 2003
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retention of 3,913m.sq. yard complete with mobile machinery and materials stockpiles for the dry recycling of waste timber for export off site together with weighbridge, 47m.sq. single storey office (3.5m high), entrance, site development works and 6m high screen wall including water misting dust suppression system together with full permission to construct a 23m.sq. single storey store (5.75m high) and complete landscaping/planting. This application is accompanied by an Environmental Impact Statement.
Site 14B1, Road 3A, Phase 3, Greenogue Industrial Estate, Rathcoole, Co. Dublin
A new hazardous medical waste processing facility, including a change of use of the existing building (Building B) on site from general waste disposal to hazardous medical waste processing, and the extension of the current operating hours to 24/7 The demolition/removal of the existing outbuildings/structures including 2 no. storage units, an office and staff room canteen; The construction of an extension (c. 966 sqm) to the existing building c.1,577 sqm on site (Building B) and associated outbuildings including a new boiler house and storage areas; The construction of a new building (c. 984 sqm) to the northwest of the site (Building A); The construction of a new 2 storey office building (c. 287 sqm) to the southeast of the site; Provision of 26 no. car parking spaces, 5 no. truck parking spaces and 18 no. bicycle stands (30 no. spaces) to serve the proposed development; All ancillary landscaping, boundary treatments, associated infrastructure, internal roads, associated processing and treatment plant, weighbridges, pv panels, and site development works to support the development. The operation of the proposed development will require an Industrial Emissions Licence (IEL) from the Environmental Protection Agency. A Review of the existing IEL relating to the site will be sought from the Environmental Protection Agency in relation to the proposed development. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) will be submitted to the Planning Authority with the planning application and the EIAR and NIS will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authority.
Unit 14B, Grant’s Way, Greenogue Business Park, Rathcoole, Co Dublin, D24 FV02
Amalgamation of Units 14A and 14B to create a single waste processing facility as follows: (1) demolition of a 60m long by 6m high internal wall, single storey site office and store and the removal of 3 portacabin offices; (2) change of use from timber recycling to hazardous waste processing and construction of a new hazardous waste processing Building A (1,831sq.m) with a 14.58 ridge height all at Unit 14A; (3) processing of hazardous waste within existing waste processing Building B and the construction of an extension (1,000sq.m) with a 14.60m ridge height to Building B; new two storey offices (288sq.m) with a 8.5m ridge height; new weighbridge and weighbridge office (40sq.m) and alterations to existing site layout to provide 25 car parking spaces, 4 truck parking spaces and 24 bicycle stands all at Unit 14B; (4) new internal circulation road and the relocation of existing weighbridge; new weighbridge; alterations to the surface water drainage systems; (5) installation of an aqueous waste treatment plant in the new waste processing Building A; (6) installation of a sewage sludge treatment plant in the extended waste processing Building B and associated odour control unit (32sq.m) with 18m high stack; (7) installation of a waste oil recovery plant in the extended waste processing Building B and associated natural gas boiler house and stores (102sq.m) with 16m high stack; (8) installation of a waste oil re-refining plant and storage tanks in the extended processing Building B and associated de-asphalting and fractionating columns (60sq.m total floor area) both with 16m high stacks and all ancillary and associated works; the proposed development entails a phased transition, hazardous waste and non-hazardous waste will be accepted and processed simultaneously at the waste facility and the total quantum of waste accepted will not exceed 95,000 tonnes per annum as permitted at the existing licenced waste facility; the proposed development will require a review of the Industrial Emissions Licence granted by the Environmental Protection Agency; an Environmental Impact Assessment Report (EIAR) is submitted with the application.
Units 14A & 14B, Greenogue Industrial Estate, Rathcoole, Co. Dublin
An increase in the volume of waste accepted at it's facility to 95,000 tonnes per annum. This project is the subject of an application to the Environmental Protection Agency for a waste licence to include waste recovery and disposal activities as per the third and fourth schedules of the Waste Management Act 1996 and the European Communities (Amendment of the Waste Management Act, 1996) Regulations, 1998 (S.I. 166 of 1998) all of which are described in detail in an accompanying Environmental Impact Statement (EIS), which is being submitted to the planning authority with this application.
Site 14B, Phase 3, Road 3A, Greenogue Industrial Estate, Rathcoole, Co. Dublin.
Retention of works at present under construction as follows: a) Omission of 233m.sq. integral ancillary office accommodation on three floors from within warehouse and revision to elevations. b) Provision of 175m.sq. ancillary office accommodation in 3 storey (9.25m high) freestanding prefabricated block in yard area. c) Provision of additional site entrance and weighbridge. d) Provision of truck marshalling, refuelling and skip storage areas. e) Relocation/alteration of/to washbay, weighbridge, car parking, yard area, drainage and landscaping to suit items b to d above. (Reg Reference No. S01A/0868) warehouse unit.
Site 14B, Phase 3, Road 3A, Greenogue Industrial Estate, Rathcoole, Co. Dublin
Development of temporary office for 5 years comprising of 162m.sq. of prefabricated free standing ancillary office accommodation in 2 no. adjacent blocks. (i) Block 1A to consist of 58m.sq. of ancillary office on 2 no. floors, 116m.sq. total, 6.15m high including external access stairs to side. (ii) Block 1B to consist of 46m.sq. of ancillary office on ground floor only, 3.15 high to approved (Reg. No. S01A/0868) warehouse unit and subsequent retention (Reg. No. SD03A/0581).
Site 14B, Phase 3, Road 3A, Greenogue Industrial Estate, Rathcoole, Co. Dublin
Waste transfer and recycling facility including: erection and use of a 1729m2 warehouse building including 233sq.m of ancillary office accommodation on 3 floors, for receiving, unloading, storing, loading and transferring wastes; skip storage, weighbridge; civic amenity area/bring centre for use by the public; truck wash area; hardstands; security gate; parking: drainage systems and retention tanks; landscaping and all ancillary services and works on a 0.603HA site.
Site 14B, Phase 3, Road 3A, Greengoue Industrial Estate, Rathcoole, Co. Dublin.
Construct a temporary proprietry foul treatment plant and associated percolation area.
Greenogue Industrial Estate, Phase 3, Rathcoole, Co. Dublin
Rilta Environmental Ltd. operates a waste transfer station for the handling of hazardous and non-hazardous wastes at Site 14A Geeenogue Business Park under planning permission SD02A/0301. The site encompasses 0.5ha and comprises a main warehouse, hazardous chemical store, offices, three covered tanker bays, a covered dispatch area and a weighbridge. The current permission authorises the acceptance, storage and packaging of 60,000 tonnes of waste comprising 27,000 tonnes of non-hazardous, commercial and industrial, construction and demolition wastes, sewage and industrial sludges, and 33,000 tonnes of hazardous waste. Rilta intends to accept, package and temporarily store air pollution control residue (APCR), before exporting it for disposal. This material will be classified as hazardous and the annual acceptance rate will be 30,000 tonnes. APCR will make up the bulk of the 33,000 of the currently authorised hazardous waste, and it is not proposed to increase either the quantity of hazardous waste (33,000) or the overall quantity of waste (60,000 tonnes) that is currently approved. There will be no change to the waste acceptance and handling procedures. All wastes will continue to be off-loaded, packaged and stored inside the main warehouse and will not be visible from any public road contiguous or adjacent to the curtilage of the building. It is not proposed to change the operational hours and, as the APCR will replace the other hazardous wastes already approved,there will be no increase in traffic movements to and from the facility.
Site 14 A1, Greenogue Business Park, Rathcoole, Co. Dublin.
Installation of roof mounted solar panels to existing waste transfer station and all ancillary works and services.
Site 14B, Greenogue Industrial Estate, Rathcoole, Co. Dublin.