Merrywell Business Park, Ballymount, Dublin 22
Grant Permission & Grant RetentionPlanning application SD10A/0163
Dublin - South Dublin County Council
Proposed Development
Minor extensions and modifications to previously approved development under Reg. Ref. SD08A/0828 to include increase in height by one storey 1 no. escape stairs, provision of access walkway across, roof to plant area, extension to cash and carry and office area at ground, first and second floor levels, provision of 3 no. speciality shop unit c.20sq.m. each, retention of use of existing ground floor office area as cash and carry use, provision of new ESB transformer room and switch room, alterations to boundary fence and minor modifications to on site roads and carparking.
View the full application file on the council's planning portal →Application Timeline
Application received
4 Jun 2010
Decision due
28 Jul 2010
Decision: Grant Permission & Grant Retention
29 Jul 2010
Grant issued
14 Sept 2010
Application Details
- Location
- Merrywell Business Park, Ballymount, Dublin 22
- Applicant
- N/A
- Application Type
- Permission and Retention
- Planning Authority
- South Dublin County Council
- Site Area
- 17800 ha
- Floor Area
- 706 sq m
Timeline
- Registration Date
- 4 June 2010
- Status
- Decision
- Decision
- Grant Permission & Grant Retention
- Decision Date
- 29 July 2010
- Grant Date
- 14 September 2010
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Extensions to existing warehouse facility to include new storage and refrigeration areas, ancillary offices and staff facilities, cash and carry facility with customer coffee shop, re-arrangement of on-site roads and carparking areas, 2.5m high fenced plant compound and 2 no. illuminated signs.
Merrywell Business Park, Ballymount, Dublin 22
Minor extensions and modifications to previously approved development under Reg. Ref. SD08A/0828 to include increase in height by one storey 1 no. escape stairs; provision of access walkway across roof to plant area; extension to Cash and Carry and office area at ground, first and second floor levels; provision of 3 no. speciality shop unit c.20sq.m. each; change of use of existing ground floor office area to Cash and Carry use; provision of new ESB transformer room and switch room; alterations to boundary fence and minor modifications to on site roads and car parking.
Merrywell Business Park, Ballymount, Dublin 22
1) The expansion of the existing Warehouse facility through the construction of a 2320m2 x 1Sm high single storey structure to the West of and adjoining the existing facility. This extension shall house ambient and temperature controlled storage zones and shall be served by three Articulated Vehicle loading docks on its Northern elevation as well as on grade loading doors on the Western Elevation. The building shall be clad in plastisol coated insulated metal cladding and shall house solar panels on its roof. 2 )The rationalisation of the existing delivery vehicle loading area through the expansion of the existing loading docks on the Northern elevation measuring 536.28m2 x 6.9m high and containing individual Rigid vehicle loading docks. The building shall be ct4 in plastisol coated insulated metal cladding. 3) The extension of the existing yard area on the Western side of the site to accommodate Vehicle loading and the relocation of the existing Compactor Building and workshop to the South West comer of the site 4) The extension of the existing Staff and Visitor car park on the Eastern side of the site 5) Alteration to Boundary treatment to Robinwood Road through the realignment of the existing wall and the installation of a new pedestrian and bicycle access at the North West Comer of the site. 6) The installation of two levels of new fenestration to the Eastern Elevation of the existing building. 7) The installation of a new underground surface water attenuation system beneath the new Western yard complete with petrol interceptor and hydro brake to augment the existing site systems.
Merrywell Business Park, Ballymount Road Lower, Dublin 12
MV electrical upgrade to serve the existing facility. Construction of two separate electrical building structures: 1) Low Voltage Switch room consisting of the Clients Transfor1ner room and a new LV Switch room measuring 8.095m x 4.380m x 3.120m high single storey, located to the east of and adjoining the existing facility. 2) ESB Electrical substation consisting of the ESB Substation and the Clients Medium Voltage Switch room measuring 8.095m x 4.380m x 3.120m high single storey, located to the east of the existing facility. Both structures will be standalone and constructed with 415mm cavity blockwork. The external finish will be rendered or otherwise suitably finished masonry in a neutral colour. The roofs will be constructed in reinforced concrete. The ESB Electrical substation will accommodate their MV switchgear and equipment necessary to upgrade and reinforce the existing electricity supply to facilitate the operation of a proposed extension and the second room will house the Clients MV switchgear and MV meter. The LV room will house associated low voltage distribution equipment, and the transformer room will house the Clients MV/LV 630 KVA transformer. The development is ancillary to and required to support the proposed extension to the existing facility. All associated works, including cabling and connections, will be contained within the site boundary.
Asia Market, Merrywell Business Park, Ballymount Road Lower, Co. Dublin, D12 W327
Part off-licence use in existing retail unit.
Asia Market, Merrywell Business Park, Ballymount Road Lower, Dublin 12
Construction of single storey retail extension to rear of existing cash and carry facility and reconfiguration of staff facilities at ground floor level to incorporate a proposed unisex wheelchair disabled accessible wc; male and female wc's and revised staff canteen; construction of single storey metal panel/glazed porch extension to front of building with minor material alteration to existing cash and carry facility; installation of additional car parking area with associated site development works.
Merrywell Business Park, Ballymount, Dublin 22
Revised Phase 2 portion of development of formerly approved production, packaging and warehouse facility with two storey ancillary offices and staff accommodation, water storage and diesel tanks and other associated plant, pump house, holding tank, truck wash and fuelling bays, bicycle shed, car parks, marshalling area, boundary walls and fences, entrance gates and 5 no. illuminated signs to be built in two phases Reg. Ref. S95A/0472 at JS Lister and Beemount Properties industrial lands.
Lower Ballymount Road, Ballymount, Dublin 22.
Revisions to previously approved permission for production, packaging and warehousing facility with ancillary offices and associated plant and site works to be built to two phases Reg. Ref. S02A/0156 and S95A/0472, to include omission of Phase 2 portion of development which included production, packaging facilities with two ancillary storey offices, staff accommodation, plant, holding tank, truck wash and fuelling bays, car parking and marshalling yards; sub-division of the site into two lots, lot on consisting of 4.048 acres for industrial/warehouse uses and lot 2 consisting of 4.416 acres with the existing Phase 1 warehouse and ancillary offices, car park and marshalling yard and construction of 2.4m high palisade fence along the boundary between the two sites; existing vehicle and pedestrian access to be retained for access to lot 1 and 2 sites with associated right of way for services and access.
Merrywell Industrial Estate, Lower Ballymount Road, Ballymount, Dublin 22.
Change of use and renovation of existing shed to new sandwich bar/delicatessen and to provide off-street car parking and new site entrance.
St. Anthony's, Robinhood Road, Fox and Geese, Dublin 22.
Detached industrial unit comprising 960sq.m of workshop area plus 720sq.m stores/offices/staff facilities on two floors totalling 1680sq.m together with hardstanding area, diesel storage tanks, wash bay facilities, site boundary walls/fencing and all associated site development works.
Merrywell Industrial Estate, Lower Ballymount Road, Dublin 12.