Site 527 & 528, Greenogue Business Park, Rathcoole, Co. Dublin

Granted

Planning application SD20A/0046

Dublin - South Dublin County Council

Proposed Development

Minor alterations to the existing warehouse building including a new canopy to the south; three new level access doors on the south elevation and external waste platform; provision of hardstanding and use of the south of the site for operational parking; removal of the existing fencing dissecting the site; introduction of new fencing, security hut, gate, smoking shelter, cycle shelter, lighting, substation and transformer, acoustic screening to the north west and all other associated works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Feb 2020

  2. Further information requested

    29 Mar 2020

  3. Further information received

    20 May 2020

  4. Decision: Grant Permission

    6 Jul 2020

  5. Decision due

    16 Jul 2020

  6. Grant issued

    13 Aug 2020

Application Details

Location
Site 527 & 528, Greenogue Business Park, Rathcoole, Co. Dublin
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
31000 ha
Floor Area
1438 sq m

Timeline

Registration Date
20 February 2020Other applications received that week
Status
Decision Following A.I.
Decision
Grant Permission
Decision Date
6 July 2020
Grant Date
13 August 2020

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

208m
SD07A/0429Grant Permission for Retention8 Jun 2007

Retention of internal two storey store 50sqm total retention area and 5.4m high to existing unit P22 previously 174sqm total and 7.5m high overall building height as per granted planning Reg. Ref. S99A/0339 PL06S.117589

Unit P22, Greenogue Industrial Estate, Rathcoole, Co. Dublin

214m
SD17A/0278Invalid - Site Notice10 Aug 2017

Construction of an 18.75sq.m ESB substation with a height of 3.37m.

Commons Little, Alymer Road, Newcastle, Co Dublin

214m
SD17A/0313Granted5 Sept 2017

Construction of an 18.75sq.m ESB sub-station with a height of 3.37m.

Commons Little, Alymer Road, Newcastle, Co Dublin

310m
ED17/0034Declared Exempt21 Jun 2017

Rilta Environmental Ltd. operates a waste transfer station for the handling of hazardous and non-hazardous wastes at Site 14A Geeenogue Business Park under planning permission SD02A/0301. The site encompasses 0.5ha and comprises a main warehouse, hazardous chemical store, offices, three covered tanker bays, a covered dispatch area and a weighbridge. The current permission authorises the acceptance, storage and packaging of 60,000 tonnes of waste comprising 27,000 tonnes of non-hazardous, commercial and industrial, construction and demolition wastes, sewage and industrial sludges, and 33,000 tonnes of hazardous waste. Rilta intends to accept, package and temporarily store air pollution control residue (APCR), before exporting it for disposal. This material will be classified as hazardous and the annual acceptance rate will be 30,000 tonnes. APCR will make up the bulk of the 33,000 of the currently authorised hazardous waste, and it is not proposed to increase either the quantity of hazardous waste (33,000) or the overall quantity of waste (60,000 tonnes) that is currently approved. There will be no change to the waste acceptance and handling procedures. All wastes will continue to be off-loaded, packaged and stored inside the main warehouse and will not be visible from any public road contiguous or adjacent to the curtilage of the building. It is not proposed to change the operational hours and, as the APCR will replace the other hazardous wastes already approved,there will be no increase in traffic movements to and from the facility.

Site 14 A1, Greenogue Business Park, Rathcoole, Co. Dublin.

352m
ED18/0029Declared Not Exempt29 Aug 2018

Installation of lights along laneway. Install and erect suitable lighting along the 300 meter laneway.

St. Finians Gaa Club, Aylmer Road, Newcastle, Co Dublin

407m
ED25/0028Declared Exempt24 Mar 2025

St Finian's GAA Club would like to upgrade a section of their existing grass training and youth Football Pitch area to an all-weather training and youth Football Pitch and all associated site works. The proposed area is 95m long x 65m wide, outlined in red on the attached drawings.

119A, St Finian's GAA Club, Aylmer Rd, Newcastle, Co.Dublin, D22 XA71

422m
SD19B/0468Granted4 Dec 2019

Single storey extension to front, east side and rear comprising a family flat; one and two storey dormer style extension to side and rear, incorporating dormer windows to front and rear; 2 rooflights to existing front roof.

119, Aylmer Road, Newcastle, Co. Dublin

426m
ED23/0035Declared Exempt11 Aug 2023

Upgrade a section of existing pitch area and associated site works. The proposed area is 40m long x 40m wide (outlined in red on the attached google satellite map). Area to be used for training purposes only

119A, St. Finian's GAA Club, Aylmer Road, Newcastle, Co. Dublin, D22 XA71

455m
SD17A/0193Granted20 Jun 2017

Two storey detached house in side garden, new vehicular access, new vehicular access and car parking in front garden and associated works.

132, Aylmer Road, Newcastle, Co. Dublin

463m
SD13A/0237Refuse Permission for Retention25 Nov 2013

Retention of development of temporary offices for 3 years; development comprises 162sq.m. of prefabricated free standing ancillary office accommodation to approved (Reg. Ref. S01A/0868) warehouse unit and subsequent retention (Reg. Ref. SD03A/0581) in 2 no. adjacent blocks; Block 1A consists of 58sq.m. of ancillary office on 2 no. floors 116sq.m. total, 6.15m high including external access stairs to side; Block 1B consists of 46sq.m. of ancillary office on ground floor only, 3.15m high.

Site 14B, Grants Way, Greenogue Industrial Estate, Rathcoole, Co. Dublin.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?