Luas Depot, Red Cow, Clondalkin, Dublin 22
Grant Permission for RetentionPlanning application SD20A/0150
Dublin - South Dublin County Council
Proposed Development
Retention of 3 standalone coated steel prefabricated units comprising of 2 single storey prefabricated units (each c.31sq.m GFA) and associated entrance ramps used for canteen and welfare use respectively; 1 single storey prefabricated modular unit (c.199sq.m GFA) and associated entrance ramp used for office use; all site development works are proposed on a site of c.0.245ha.
Application Timeline
Application received
24 Jun 2020
Decision: Grant Permission for Retention
17 Aug 2020
Decision due
18 Aug 2020
Appeal submitted
14 Sept 2020
Appeal decided: To Remove Condition(s)
21 Jan 2021
Grant issued
1 Feb 2021
Application Details
- Location
- Luas Depot, Red Cow, Clondalkin, Dublin 22
- Applicant
- N/A
- Application Type
- Retention
- Planning Authority
- South Dublin County Council
- Site Area
- 2450 ha
- Floor Area
- 261.2 sq m
Timeline
- Registration Date
- 24 June 2020Other applications received that week
- Status
- Officer Allocation
- Decision
- Grant Permission for Retention
- Decision Date
- 17 August 2020
- Grant Date
- 1 February 2021
- Permission Expires
- 14 January 2021
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-308169-20
- Decision
- To Remove Condition(s)
- Submitted
- 14 September 2020
- Decided
- 21 January 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Bus shelter.
Outside SDS on Naas Road (outbound), Dublin 22.
Is the commercial use as open storage of lands at Clonacoole, Naas Road, Clondalkin, D22 development, & if so, is it exempt development
Clonacoole, Naas Road, Clondalkin, Dublin 22
Construction of a detached garage adjacent to the side including the dishing of the existing footpath and access from the hammerhead at Dunmore Park.
Site adjacent to the side of, 82, Dunmore Park, Ballymount, Dublin, 24
It is proposed to carry out an Energy Retrofit under 'The Better Energy Homes Scheme', to install external wall insulation to the front facade, gable wall and to parts of the rear facade. There is an extension to the rear that will not be insulated. The Insulation will be a depth of 110mm with a plain acrylic finish.
9, St. Bridget's Cottages, Bushelloaf, Dublin 22
An ESB substation building of approx. 4.5m (W) 5m (L) and 2.9m (H) only. The substation building will be block built with a plastered finish and a flat concrete roof.
Unit 2, Block K, Ballymount Industrial Estate, Dublin 24
The site is approximately 1.5 acres and is fully concreted and consists of three permanent structures which include the depolluting bay (area where potentially polluting materials are removed), a small garage and a spare parts store (all indicated on Figure 1 attached). The depolluting bay is a single story building with steel and concrete frame and galvanised roofing. The garage and spare parts store are small single storey structures with a galvanised frame construction. The remaining structures include three portacabins housing offices and a parts shop and 5 mobile containers housing spare parts. The site currently operates as an authorised treatments facility for the dismantling, recovery and depollution of End of Life Vehicles (ELV's) under its Waste Permit (Registration Number WPR 006/2). Westlink operates three collection trucks collecting ELV'S from the general public in the surrounding South Dublin region. The company also hold a contract from Dunlaoighre Rathdown County Council for the removal of ELV'S from the travelling community. The general public can also deposit cars at the site free of charge. On arrival at the site Elv's are examined and inspected to ensure only material that are permitted are accepted on site. ELV'S are then stored on paved areas awaiting the depollution process. The depollution process involves a number of below and above vehicle operations in order to remove all materials that could pose a threat to the enviroment on crushing of the car. These materials include all fluids, lean-acid batteries, filters tyres, air conditioning systems, air bags and catalysts. After the depollution process ELV's are crushed and baled by a baler machine. The baled cars are sent to appropriately licenced facilities for further processing. All other wastes removed from the ELV's are stored on site in appropriate containers and removed offsite by permitted waste contractors for further treatment and disposal.
Westlink Recovery Services Limited, Red Cow, Naas Road, Dublin 22
Use of premises as a laundry for hairdressing business (Peter Mark). The unit will house industrial grade washing machines and dryers. Used towels from Peter Marks hairdressers will be delivered to the unit via Peter Mark vehicles; the towels will be washed, dried and folded in the unit before being returned to the stores.
Unit 232, Western Industrial Estate, Holly Road, Dublin 12
20m monopole carrying 3 no. antennae, 4 no. radio link dishes, associated equipment, outdoor cabinets and fencing for a new 3G broadband network.
National Seals Systems, Unit 20, Western Industrial Estate, Dublin 12.
A 3m high 'lamp post' style relief vent stack servicing the existing below ground natural gas pressure reduction unit with all ancillary services and associated site works.
Castlefarnham DRIug, Kingswood Castle, Off Ballymount Road, Dublin 24
Erect a 25m monopole containing 3 no. antennae, 4 no. dishes, associated equipment, outdoor cabinets and fencing for a new 3g broadband network.
Flexo, Unit 214, Holly Road, Western Industrial Estate, Clondalkin, Dublin 22
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?