← Back to search

Ballymount Drive, Ballymount Industrial Estate, Dublin 12

Granted

Planning application SD20A/0307

Dublin - South Dublin County Council

Proposed Development

Construction of a new industrial unit for storage and office purposes, the relocation of an existing fire escape door on existing Unit D1, and all associated site works.

View the full application file on the council's planning portal →

Application Timeline

  1. Further information requested

    28 Jan 2021

  2. Application received

    11 Mar 2021

  3. Further information received

    11 Mar 2021

  4. Decision due

    7 Apr 2021

  5. Decision: Grant Permission

    7 Apr 2021

  6. Grant issued

    17 May 2021

Application Details

Location
Ballymount Drive, Ballymount Industrial Estate, Dublin 12
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
392 ha
Floor Area
168.5 sq m

Timeline

Registration Date
11 March 2021
Status
Decision Following A.I.
Decision
Grant Permission
Decision Date
7 April 2021
Grant Date
17 May 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

31m
ED09/0007Declared Exempt10 Mar 2009

Storage within the cutilage of an industrial building, in connection with the industrial process carried on in the building, of the deposit of waste arising from the industrial process.

Unit 6, Ballymount Industrial Estate, Walkinstown, Dublin 12

44m
S00A/0053Granted2 Feb 2000

(A) Retention of internal first floor extensions within existing industrial unit. (B) Additional alterations including construction of new internal stairs, relocation of door on the eastern elevation.

Units E1 and E3, Ballymount Industrial Estate, Walkinstown, Dublin 12.

46m
SD08A/0095Granted11 Feb 2008

Upgrading existing elevations to include revised fenestration, canopy to front and side entrances, new parapet cladding to all side and gable elevations and new thru coloured plaster finish throughout

Unit 1M, Ballymount Drive, Ballymount Industrial Estate, Walkinstown, Dublin 12

46m
SD04A/0063Granted29 Jan 2004

Partial change of use from light industrial to ancillary office use within part of the existing industrial unit on the ground floor (19 sq.m.), and for additions to existing internal ancillary office floor area on the first floor (37 sq.m.), and a new first floor window on the west side of the building

Unit 1M, Ballymount Drive, Walkinstown, Dublin 12.

46m
SD07A/0729Granted10 Sept 2007

Partial demolition of existing two storey warehouse/office building and provision of new 3 storey building along western side accommodating new reception/staircase area and staff facilities on ground floor together with meeting rooms and management offices on second floor, all to be used in conjunction with existing warehouse; alterations to existing southern elevation of warehouse to provide new parapeted elevation, new car parking, 7 no. car places, access and new landscaping to front and general refurbishment of existing warehouse building.

Unit 1M, Ballymount Drive, Ballymount Industrial Estate, Walkinstown, Dublin 12

59m
SD07A/1058Granted22 May 2008

Redevelopment of a light industrial building which was previously subdivided into two units totalling 1199 sq. m. Construction of a new building on the site of Unit No.1 to provide 679 sq. m. approximately of warehouse area over one storey and 565 sq. m. approximately of associated office area over two storeys. Units No 1 and No 2 (E1) will be connected internally so that they amalgamate to form one single unit on the site totalling 2710 sq. m. approximately. The proposed redevelopment will include hard and soft landscaping, drainage works, signage and other associated works.

E1, E2, E3 Ballymount Industrial Estate, Ballymount Drive, Walkinstown, Dublin 12

65m
SD08A/0805Granted28 Nov 2008

Two storey extension to the north gable end of existing industrial units. The extension will comprising two separate warehouse units, each with 100sq.m. warehouse floor space and 22sq.m. of ancillary office space: the gross internal floor space to be provided is 244sq.m. The overall height of the development is 7.3m.

Unit 51, Ballymount Drive, Walkinstown, Dublin 12.

65m
SD04A/0274Grant Permission for Retention15 Oct 2004

Revised elevation, mezzanine floor with offices, and all associated site works.

Unit 3C, Ballymount Industrial Estate, Ballymount, Dublin 12.

66m
SD21A/0158Granted2 Dec 2021

Erection of 2 two storey industrial units adjacent to existing S1 unit comprising of warehouse, office and toilet at ground floor level and proposed storage to mezzanine floor level; alterations to external area/existing car park and all associated site works.

Unit S1, Ballymount Drive, Ballymount Industrial Estate, Dublin 12

98m
SD02A/0518Granted29 Apr 2003

Extension of existing warehouse.

Unit G2A Ballymount Drive, Walkinstown, Dublin 12.