Ballykinlalee , Ballinahinch , Co Tipperary
CONDITIONALPlanning application 20715
Tipperary - Tipperary County Council
Proposed Development
construct two storey detached dwelling house, detached garage, entrance, boundary walls, wastewater treatment system, polishing filter and all associated site works
Application Timeline
Application received
7 Jul 2020
Decision: CONDITIONAL
26 Aug 2020
Decision due
31 Aug 2020
Grant issued
29 Sept 2020
Application Details
- Location
- Ballykinlalee , Ballinahinch , Co Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 0.598 ha
- Floor Area
- 262.41 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 7 July 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 26 August 2020
- Grant Date
- 29 September 2020
- Permission Expires
- 28 September 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
the construction of a part two-storey detached dwellinghouse, detached domestic garage, detached domestic fuel storage shed, wastewater treatment system, site entrance and all ancillary site works thereto (Outline Planning Permission 15600969)
Ballykinlalee , Newport , Co Tipperary
slatted loose shed with underground effluent tank and Permission to construct slatted loose shed with underground effluent tank, roofed manure stead area and all associated site works
Gortshane , Newport , Co. Tipperary
a change of site boundary and relocation of a polishing filter from that granted in planning file 02-510388
Gortshane Middle , Newport , Co. Tipperary
an extension to farmyard consisting of a cattle shed with underground slurry storage tank
Gortshane Middle , Newport , Co Tipperary
new garage and associated works
Gortshane East , Killoscully , Newport
to fill the existing poor quality agricultural land with inert materials comprising of Class 5 and Class 6 material (topsoil, subsoil, soil, recovered concrete and stone) in order to raise the level of the ground, provision of a temporary wheel wash on site, proposed access track, utilising existing site entrance including all ancillary site works - NIS submitted with application
Ballyard Td , Birdhill , Co. Tipperary
new dwelling, garage, wastewater treatment system, polishing filter, entrance and associated works
Gortshane Middle , Newport , Co Tipperary
construction of a new dwelling, garage, wastewater treatment system, polishing filter, entrance and associated works
Gortshane Middle , Newport , Co. Tipperary
construction of a new dwelling, garage, wastewater treatment system, polishing filter, entrance and all associated site works
Gortshane Middle , Newport , Co. Tipperary
a high-power electric vehicle charging hub & associated infrastructure, consisting of the following: (i) installation of 8 no. electric vehicle bays & 4 no. charging points (powered by 100% renewable energy), (ii) installation of new canopy with associated illuminated signage, (iii) new modular esb substation, (iv) landscape renewal & (v) revised parking bay markings (zevi compliant).
Applegreen Motorway Service Area , Junction 7 (M7) , Lackanavea Birdhill Co. Tipperary