domestic garage revised position as constructed from previously granted permission ref no. 07/511337

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 Oct 2021

  2. Decision: CONDITIONAL

    2 Dec 2021

  3. Decision due

    6 Dec 2021

  4. Grant issued

    14 Jan 2022

Application Details

Location
Falleen , Toomevara , Co Tipperary
Applicant
N/A
Application Type
RETENTION
Planning Authority
Tipperary County Council
Site Area
0.4 ha

Timeline

Registration Date
12 October 2021Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
2 December 2021
Grant Date
14 January 2022
Permission Expires
13 January 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

263m
2461010CONDITIONAL26 Nov 2024

the demolition of an existing derelict dwelling, the erection of a dwelling, entrance and wastewater treatment system including associated site works

Falleen , Ballymackey , Nenagh Co Tipperary

893m
2260429CONDITIONAL19 Aug 2022

the construction of air vent stack units to service ventilation of the proposed pig houses granted under previous planning grant file ref:20211, incl assoc. siteworks

Woodville , Ballymackey , Nenagh Co Tipperary

894m
211371CONDITIONAL15 Sept 2021

an overground effluent / slurry store, including associated site works, application relates to an activity which holds an integrated pollution prevention and control licence

Woodville , Ballymackey , Nenagh

897m
20211CONDITIONAL6 Mar 2020

demolition of gilt house, two weaner houses and one first stage weaner house, construction of a modern second stage weaner house and extension of a farrowing house, extension of a loose sow house to provide additional first stage weaner accommodation, construction of a new pre-finisher house for slow growing pigs, construction of a slurry reception tank and all associated site development works on existing pig rearing operation (This application is accompanied by an Environmental Impact Assessment Report (EIAR) and relates to an activity which holds an integrated pollution prevention and control licence)

Woodville , Ballymackey , Nenagh Co. Tipperary

917m
20119N/A12 Feb 2020

demolition of gilt house, two weaner houses and one first stage weaner house, construction of a modern second stage weaner house and extension of a farrowing house, extension of a loose sow house to provide additional first stage weaner accommodation, construction of a new pre-finisher house for slow growing pigs, construction of a slurry reception tank and all associated site development works on existing pig rearing operation (This application is accompanied by an Environmental Impact Assessment Report (EIAR) and relates to an activity which holds an integrated pollution prevention and control licence)

Woodville , Ballymackey , Nenagh Co. Tipperary

956m
20185N/A28 Feb 2020

demolition of gilt house, two weaner houses and one first stage weaner house, construction of a modern second stage weaner house and extension of a farrowing house, extension of a loose sow house to provide additional first stage weaner accommodation, construction of a new pre-finisher house for slow growing pigs, construction of a slurry reception tank and all associated site development works on existing pig rearing operation (This application is accompanied by an Environmental Impact Assessment Report (EIAR) and relates to an activity which holds an integrated pollution prevention and control licence)

Woodville , Ballymackey , Nenagh Co. Tipperary

1.1km
18600281N/A8 Mar 2018

demolition of existing substandard dwellinghouse and outbuilding, construction of a replacement single storey dwellinghouse, installation of a new septic tank and percolation area and all associated site works

Cappa , Ballymackey , Co Tipperary

1.1km
18601172CONDITIONAL26 Sept 2018

a) retention of the change of use of existing outbuilding from agricultural to living accommodation, b) permission for a single storey extension to the existing outbuilding consisting of additional living accommodation (this extension will form one single dwelling house when combined with the existing outbuilding), c) permission for a new septic tank & percolation area to replace the existing substandard septic tank, d) permission to demolish an existing substandard dwelling house & e) all associated site works

Cappa , Ballymackey , Co Tipperary

1.4km
25155CONDITIONAL5 Aug 2025

a slatted suckler house with underground slurry accommodation, calf creep area, ancillary concrete and all associated site works

Ballyknockane , Cloughjordan , Co Tipperary

1.5km
19600834CONDITIONAL29 Jul 2019

demolition of existing garage and boiler together with construction of side extension to existing dwelling, alteration to existing front elevation, change existing tiled roof to slated roof, change existing brick and rough dashed external wall finish to plastered wall finish, provision of new sewerage treatment system and all associated site works

Ballyknockane , Ballymackey , Nenagh

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?