← Back to search

ESB's Thurles 110kV substation , Ballygemmane , Thurles Co. Tipperary

CONDITIONAL

Planning application 21303

Tipperary - Tipperary County Council

Proposed Development

construction of a 36 m high lattice type communication structure carrying antennae, dishes and ancillary equipment located within a 2.4 m high palisade compound

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    11 Mar 2021

  2. Further information requested

    30 Apr 2021

  3. Further information received

    19 Jul 2021

  4. Decision: CONDITIONAL

    12 Aug 2021

  5. Decision due

    15 Aug 2021

  6. Grant issued

    15 Sept 2021

Application Details

Location
ESB's Thurles 110kV substation , Ballygemmane , Thurles Co. Tipperary
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
0.003 ha

Timeline

Registration Date
11 March 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
12 August 2021
Grant Date
15 September 2021
Permission Expires
14 September 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

1m
21198N/A19 Feb 2021

the construction of a 36m high lattice communication structure carrying dishes, antennae and associate equipment all within a 2.4 m high palisade compound

ESB's Thurles 110 kv Substation , Townland of Ballygemmane , Thurles Co. Tipperary

114m
20771CONDITIONAL13 Jul 2020

construction of 1 no. A+-30 Mvar STATCOM transformer, 1 no. auxillary transformer, 3 no. reactors and 1 no. outdoor cooling bank, control and valve building (233m2), 1 harmonic filter, 1 HV circuit breaker (including CT and VT), 1 MV disconnector and earth switch, 2 no. cable sealing ends, 1 no. 110kV feeder bay, 1 busbar connection and underground connection to existing ESB Thurles 110 kV substation, security fencing, security gate, 7 no. 22m high lightning masts, permeable and non-permeable surfacing, additional internal access road, additional fencing to match existing 2.6 m high palisade and all other ancillary site development works and 2 temporary contractors compounds (the development is an extension to the existing substation and this extension has an overall site area (within the planning application boundary) of 1.839ha. In operation the STATCOM would be accessed through the existing gated entrance to the site via the local road to the immediate South. During construction, temporary access is proposed to the east of the existing substation. A Natural Impact Statement (NIS) has been prepared as part of this application)

Ballygammane , Thurles , Co. Tipperary

143m
2560940CONDITIONAL22 Sept 2025

a Battery Energy Storage System (BESS) development to consist of a new site entrance and access track, site security fencing including a noise acoustic barrier, access gates, BESS enclosures, a BESS intake substation, MV skid, a back-up generator, a monitoring house, an auxiliary transformer, spares containers, CCTV, an onsite toilet, carparking, a temporary construction stage compound area, landscaping and all associated ancillary development services and works, all to be provided within a total overall application boundary of 2.69 ha. Permission is sought for the proposed BESS development for a period of 10 years with an operational period of 40 years. An Appropriate Assessment Screening Report (AASR) and Natura Impact Statement (NIS) has been prepared for this development and submitted with this planning application. A separate application will be submitted to An Coimisiún Pleanála to obtain permission for a 110kV substation on site

Ballygammane and adjacent to the existing Thurles 110kV substation , Thurles , Co. Tipperary

185m
20633N/A22 Jun 2020

construction of 1 no. A+-30 Mvar STATCOM transformer, 1 no. auxillary transformer, 3 no. reactors and 1 no. outdoor cooling bank, cooling and valve building (33m2), 1 harmonic filter, 1 HV circuit breaker (including CT and VT), 1 MV disconnector and earth switch, 2 no. cable sealing ends, 1 110kV feeder bay, 1 busbar connection and underground connection to existing ESB Thurles 110 kV substation, security fencing, security gate, 7 no. 22m high lightning masts, permeable and non-permeable surfacing, additional internal access road, additional fencing to match existing 2.6 m high palisade and all other ancillary site development works and 2 temporary contractors compounds (the development is an extension to the existing substation and this extension has an overall site area (within the planning application boundary) of 1.839ha. In operation the STATCOM would be accessed through the existing gated entrance to the site via the local road to the immediate South. During construction, temporary access is proposed to the east of the existing substation. A Natural Impact Statement (NIS) has been prepared as part of this application)

Ballygammane , Thurles , Co. Tipperary

233m
2560848N/A29 Aug 2025

Battery Energy Storage System (BESS) development which will consist of a new site entrance and access track, site security fencing including a noise acoustic barrier, access gates, BESS enclosures, a BESS intake substation, MV skid, a back-up generator, a monitoring house, an auxiliary transformer, spares containers, CCTV, an onsite toilet, carparking, a temporary construction stage compound area, landscaping and all associated ancillary development services and works, all to be provided within a total overall application boundary of 2.69 ha. Permission is sought for the proposed BESS development for a period of 10 years with an operational period of 40 years. The development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and will be subject to a completeness check under Section 34D of the Planning and Development Act, 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Appropriate Assessment Screening Report (AASR) and Natura Impact Statement (NIS) has been prepared for this development and submitted with this planning application. A separate application will be submitted to An Coimisiún Pleanála to obtain permission for a 110kV substation on site.

Ballygammane and adjacent to existing Thurles 110kV substation , Thurles , Co. Tipperary

333m
2560066CONDITIONAL4 Feb 2025

1) domestic garage/store, 2) sunroom to side of existing house, 3) conversion of existing domestic garage to a bedroom and ensuite including alterations to roof and front elevation, 4) additional window to side elevation and 5) all associated site works

Ballygammane , Thurles , Co. Tipperary

536m
2260650CONDITIONAL27 Nov 2022

a) construction of a new, part two-storey, part single-storey detached dwelling, b) new detached garage, c) new site access, d) new connections to existing utilities, e) new waste-water treatment system and percolation area and f) all associated site works

The Furze , Thurles , Co. Tipperary

610m
21502N/A15 Apr 2021

completion of partially constructed 15.3km long 38kV overhead electricity line from Thurles electricity substation to the Borrisoleigh electricity substation as permitted under TCC Reg 08/511136 which comprises an overhead line supported by a total of 116 structures - as this permission has expired, permission is sought for works not yet completed, namely 1) works to 38 no. structures to (subject to final detailed design|) erect replacement wooden poleset structures or alter existing structures, 2) stringing of conductor along approx. 7 km of the overhead line, and 3) all ancillary works related to the project

Ballygammane Lisduff Knockanacunna Cassestown Farranreigh Tooreen , Rossestown Brittas Clonamuckoge More Clonamuckoge Beg Kilkillahara Ballybristy Lisheenataggart , Rorardstown Lower Rorardstown Upper Rathleasty Kivilcorris Clonbrassil Fishmoyne Knoc

614m
21638CONDITIONAL10 May 2021

completion of partially constructed 15.3km long 38kV overhead electricity line from Thurles electricity substation to the Borrisoleigh electricity substation as permitted under TCC Reg 08/511136 which comprises an overhead line supported by a total of 116 structures - as this permission has expired, permission is sought for works not yet completed, namely 1) works to 38 no. structures to (subject to final detailed design) erect replacement wooden poleset structures or alter existing structures, 2) stringing of conductor along approx. 7 km of the overhead line, and 3) all ancillary works related to the project

Ballygammane Lisduff Knockanacunna Cassestown Farranreigh Tooreen , Rossestown Brittas Clonamuckoge More Clonamuckoge Beg Kilkillahara Ballybristy Lisheenataggart , Rorardstown Lower Rorardstown Upper Rathleasty Kivilcorris Clonbrassil Fishmoyne Knoc

954m
2460885CONDITIONAL15 Oct 2024

the as-built changes to dwelling house previously granted planning permission (reference no. PLC/8809) including retention of existing sheds

Ballygemmane , Thurles , Co. Tipperary

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?