Barnanalleen Moanmore Seskin , Seskin , Co Tipperary
N/APlanning application 2260411
Tipperary - Tipperary County Council
Proposed Development
a solar PV development on a 92 ha site consisting of: (1) The erection of solar panels on ground-mounted galvanised steel frames, 198 no. string inverters attached to selected ground-mounted galvanised steel frames, 8 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; (2) 3 no. site entrances with access gates utilizing existing farm field entrances which will be upgraded and internal accesses; (3) 1 no. on-site IPP switching substation and associated works abutting the existing Cauteen 110kv substation; (4) a temporary construction compound; (5) all associated ancillary development works. The development can operate as an independent solar PV development and in conjunction with the solar PV developments permitted under planning permission references 17/600456 and 21/1109. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application
View the full application file on the council's planning portal →Application Details
- Location
- Barnanalleen Moanmore Seskin , Seskin , Co Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 92 ha
Timeline
- Registration Date
- 8 August 2022
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
a solar PV development on a 92 ha site consisting of: - The erection of solar panels on ground-mounted galvanised steel frames, 198 no. string inverters attached to selected ground-mounted galvanised steel frames, 8 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; - 3 no. site entrances with access gates utilizing existing farm field entrances which will be upgraded and internal accesses; - 1 no. on-site IPP switching substation and associated works abutting the existing Cauteen 110kv substation; - a temporary construction compound; and - all associated ancillary development works; at Barnanalleen, Moanmore and Seskin, County Tipperary. The development can operate as an independent solar PV development and in conjunction with the solar PV developments permitted under planning permission references 17/600456 and 21/1109. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application.
Barnanalleen , Moanmore and , Seskin
a 10 year planning permission for a solar development on a 39 ha site consisting of: Three site entrances with access gates utilizing existing farm field entrances which will be upgraded and internal accesses; Upgrading of existing laneway to permit access to a proposed substation site (the proposed substation and associated works are currently the subject of a Strategic Infrastructure Development Pre- Application Consultation with An Bord Pleanala); Security fencing around the proposed substation site; Solar panels on ground-mounted galvanised steel frames, 81 no. string inverters attached to selected ground-mounted galvanized steel frames, 6 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; A temporary construction compound; and All associated ancillary development works. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application
Barnanalleen and Lisheennamalausa , Co. Tipperary
RED III development which will consist of a 10-year permission for the construction of a solar photovoltaic (PV) energy development on a site spanning approximately 65.9 hectares. It will comprise ground-mounted solar PV panels installed on steel support structures, along with 17 no. transformers, underground cabling including a cable route connecting to the IPP Substation Building consented under Planning Reference 2260420, perimeter fencing with secure access gates, 43 no. closed-circuit television cameras on posts, 3 no. temporary construction compounds, new and upgraded access tracks, and associated landscaping and ancillary works. The site will be accessed from four existing access points off the L-8210, which dissects the Application Site, three of which will be upgraded to facilitate access. The development will have an operational capacity of up to 53.1 megawatt peak and is designed to operate for 40 years from the date of commissioning. A Natura Impact Statement (NIS) will accompany the planning application.
Land within the townlands of Seskin Moanmore Lisheennamalausa Ballyryan West Gortdrum and Barnanalleen , in the Civil Parish of Solloghod-More , Co. Tipperary
RED III application for the development, consisting of the construction of a solar photovoltaic (PV) energy development on a site spanning approximately 65.6 hectares. It will comprise ground-mounted solar PV panels installed on steel support structures, along with 17 no. transformers, underground cabling, perimeter fencing with secure access gates, 43 no. closed-circuit television cameras on posts, 3 no. temporary construction compounds, new and upgraded access tracks, and associated landscaping and ancillary works. The site will be accessed from four existing access points off the L-8210, which dissects the application site, three of which will be upgraded to facilitate access. The development will have an operational capacity of up to 53.1 megawatt peak and is designed to operate for 40 years from the date of commissioning. A Natura Impact Statement (NIS) will accompany the planning application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
land within the townlands of Lisheennamalausa Ballyryan West Gortdrum and Barnanalleen , in the Civil Parish of Solloghod-More , Co. Tipperary
a 10 year planning permission for a solar development on a 39 ha site consisting of: Three site entrances with access gates utilizing existing farm field entrances which will be upgraded and internal accesses; Upgrading of existing laneway to permit access to a proposed substation site (the proposed substation and associated works are currently the subject of a Strategic Infrastructure Development Pre- Application Consultation with An Bord Pleanala); Security fencing around the proposed substation site; Solar panels on ground-mounted galvanised steel frames, 81 no. string inverters attached to selected ground-mounted galvanized steel frames, 6 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; A temporary construction compound; and All associated ancillary development works. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application
Barnanalleen and Lisheennamalausa , Co. Tipperary
a 10 year planning permission for a solar development on a 42.2 ha site consisting of: Three site entrances with access gates utilizing existing farm field entrances which will be be upgraded and internal accesses; Upgrading of existing laneway to permit access a proposed substation site (the proposed substation and associated works are currently the subject of a Strategic Infrastructure Development Pre- Application Consultation with An Bord Pleanala); security fencing around the proposed substation site; Solar panels on ground-mounted galvanised steel frames, 66 no. string inverters attached to selected ground-mounted galvanized steel frames, 6 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; A temporary construction compound; and All associated ancillary development works. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application
Barnanalleen and Lisheennamalausa , Co Tipperary
development which will consist of a 10-year planning permission to construct and complete a synchronous condenser and battery storage development with a total site area of c. 1.3 hectares comprising of 40 no. battery energy storage units, 5 no. twin skid structures, 1 no. synchronous condenser, 1 no. generator circuit breaker, 1 no. auxiliary transformer and bund, 1 no. step-up transformer and bund, 5 no. control modules, 1 no. cooler unit, 1 no. emergency diesel generator and fuel tank, 1 no. single storey storage container, CCTV cameras, security fencing, access gates, access track, landscaping works, internal cabling and ancillary infrastructure works. The synchronous condenser and battery energy storage development would be operational for 35 years. A Natura Impact Statement (NIS) will be submitted with the application
Land c. 145m south of Seskin Road , Seskin , Co. Tipperary
a new agricultural entrance to access agricultural lands and all associated site works
Barnaleen , Donohill , Co Tipperary
the construction of a dwelling, site entrance, domestic garage, on-site effluent treatment system, and all associated site development works
Knockphelagh , Monard , Co. Tipperary
construction of dwelling, domestic garage, site entrance, install effluent treatment system including all associated site development works
Knockphelagh , Monard , Co. Tipperary
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?