Ballydine , Kilsheelan , Co. Tipperary

CONDITIONAL

Planning application 23196

Tipperary - Tipperary County Council

Proposed Development

the existing temporary carpark (contractor carpark facility) and associated existing service roadway and existing compound area, comprising a mix of existing stone base and also tarmac surface treatment, and including existing site lighting installations, existing fencing, existing smoking shelter and existing bicycle rack. We also wish to apply for permission to extend the existing carpark by circa 2m to the east to accommodate the construction of 178 no permanent carparking spaces (which includes for the designation of 17 no. new e-car charging carparking spaces and 1 no. new combined disabled/e-car charging carparking space), upgrade of the existing surface finish to a tarmac finish as applicable throughout, installation of line markings and kerbing, drainage works including the installation of a petrol/oil interceptor and attenuation system, adaption of existing site lighting as required ( including the replacement of all existing site lighting fixtures), the alterations of existing tree line, adaptation of existing compound area to form a secure delivery drop-off/short-term storage area, and all necessary alterations to accommodate the above works, complete with all associated site works and ancillary accommodation. The planning application is accompanied by a Natura Impact Statement (NIS). This application refers to a development on a site that carries out activity for which an industrial Emissions Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and where the major accident directive applies

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    13 Jul 2023

  2. Further information requested

    5 Sept 2023

  3. Further information received

    19 Sept 2023

  4. Decision: CONDITIONAL

    10 Nov 2023

  5. Decision due

    13 Nov 2023

  6. Grant issued

    14 Dec 2023

Application Details

Location
Ballydine , Kilsheelan , Co. Tipperary
Applicant
N/A
Application Type
RETENTION
Planning Authority
Tipperary County Council

Timeline

Registration Date
13 July 2023
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
10 November 2023
Grant Date
14 December 2023
Permission Expires
13 December 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

17m
22644N/A22 Nov 2022

the existing contractor carpark facility and associated service roadway, comprising a mix of existing stone base and also tarmac surface treatment, including 8 no. existing lighting poles, smoking shelter and bicycle rack. Planning permission is also sought for the extension of the existing contractor carpark by 2m to the east, upgrading of the existing surface finish to a tarmac finish throughout, installation of line markings and kerbing to accommodate the construction of 178 no. permanent carparking spaces which includes for the designation of 18 no. new e-car charging carparking spaces and 1 no. new disabled carparking space, complete with all necessary drainage works and the replacement of all existing lighting poles, the alteration of existing tree line and all necessary alterations to accommodate the works, complete with all associated site works and ancillary accommodation. This planning application is accompanied by a Natura Impact Statement (NIS). This application refers to a development on a site that carries out an activity for which an Industrial Emissions License under PartIV of the Environmental Protection Agency Act 1992 (as amended) is required and where Major Accident Directive applies.

Ballydine , Kilsheelan , Co. Tipperary

119m
2560085CONDITIONAL11 Feb 2025

the development of a new purified water utility (PuW) building. The development will consist of: i) a new purified water utility (PuW) building with two no. levels, to provide a gross floor area of approximately 281 square meters and a maximum height of 15.0 meters at the building stair core; ii) all associated site development and ancillary works including modifications to footpaths, drainage and utility services, service connections to existing high-level piperacks and landscaping works. The proposed development is located on a site that operates under an existing Industrial Emissions (IE) Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act, 2003). The proposed development is on a site which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 applies

MSD Ireland (Ballydine) , Ballydine Kilsheelan Clonmel , Co. Tipperary

139m
19601276CONDITIONAL14 Nov 2019

construction of an extension to an existing utility building to enclose existing vessel, maintenance platform, access stair & associated equipment. This application refers to a development on a site that carries out an activity for which an Industrial Emissions License under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and where the Major Accident Directive applies

Ballydine , Kilsheelan , Clonmel

173m
2560487CONDITIONAL29 May 2025

the construction of an MV electrical building. The development will consist of: i) a new MV electrical building to comprise electrical rooms over an under-croft level to provide a gross floor area of approximately 168.8 square meters and a maximum height of 4.76 metres to include grated steel access platforms; ii) all associated site development and ancillary works including modifications to footpaths, drainage and utility services, and ground works. The proposed development is located on a site that operates under an existing Industrial Emissions (IE) Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act, 2003). The proposed development is on a site which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 applies

MSD Ireland (Ballydine) , Ballydine Kilsheelan Clonmel , Co. Tipperary

199m
20693CONDITIONAL2 Jul 2020

an extension to the existing Research and Development and Formulation Building. The proposed development will comprise a total gross floor area of c.6400 sqm including (i) a new three-storey extension to the northern elevation of the existing Research & Development and Formulation Building, to be developed in two blocks, and to a maximum height of 19.94m (ii) 30 no. new permanent car parking spaces; (iii) a temporary construction compound and contractors parking area to support the development; (iv) all associated site development and ancillary works, including local modifications to internal site roads, footpaths, underground drainage and utility services, realignment of internal fencing, and provision of a new storm water attenuation tank. This application refers to a development on a site that carries out an activity for which an Industrial Emissions licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and where the Major Accident Directive applies

Ballydine , Kilsheelan , Clonmel

200m
20637N/A22 Jun 2020

development which will consist of an extension to the existing Research and Development and Formulation Building. The proposed development will comprise a total gross floor area of c.6400 sqm including (i) a new three-storey extension to the northern elevation of the existing Research & Development and Formulation Building, to be developed in two blocks, and to a maximum height of 19.94m (ii) 30 no. new permanent car parking spaces; (iii) a temporary construction compound and contractors parking area to support the development; (iv) all associated site development and ancillary works, including local modifications to internal site roads, footpaths, underground drainage and utility services, realignment of internal fencing, and provision of a new storm water attenuation tank. This application refers to a development on a site that carries out an activity for which an Industrial Emissions licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and where the Major Accident Directive applies

Ballydine , Kilsheelan , Clonmel

217m
21360N/A23 Mar 2021

construction of a proposed three-storey pilot plant manufacturing facility sized approximately 3,266 square metres and approximately 20.75 metres high and located and linked to the existing factory 03 manufacturing building and located south of the O.S.D. manufacturing facility, currently under construction (ref. 20/693). The project development alos includes the following: a) An equipment yard housing plant, equipment and abatement system, vents and equipment housings including a covered waste tank, b) Roof mounted equipment and vents, c) Modifications to existing underground utilities including a surface water attenuation tank, underground storage tanks and miscellaneous works, d) The extension of the temporary contractors’ compound, currently under construction and additional local temporary contractor parking together with a second compound directly adjacent to the proposed facility, e) Revised landscaping and site-works, f) Modifications to the existing internal roads layouts, site lighting, pipe bridges, links, bunded tanks and supporting structures, and a truck staging area, g) Modifications to the existing car park layout to allow for the inclusion of additional accessible car parking spaces and electrical charge points, h) Alterations to the elevations of Factory 03 to accommodate the proposed development. This application consists of a development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act 2003) is required. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement ("NIS") accompany this planning application. This is a site to which the Chemicals Act (Control of Major Accident Hazards involving dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies

Ballydine , Kilsheelan , Clonmel

222m
2460825CONDITIONAL27 Sept 2024

an extension to the existing factory 03 production building at the site at Ballydine, Kilsheelan, Clonmel, Co. Tipperary. The development will consist of: (i) a new 4 level extension to the southern elevation of the existing factory 03 building to provide a gross floor area of approximately 2,967 sqm and maximum height to parapet of 29.11m; (ii) all associated site development and ancillary works including modifications to internal roads, footpaths, underground drainage and utility services, provision of low level (height c. 0.5 m) retaining wall, adjustment of the existing high level piperacks/cable trays for connections into the proposed building and landscaping works. The proposed development is located on a site that operates under an existing Industrial Emissions (IE) Licence under Part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act, 2003). The proposed development is on a site which the Chemicals Act (Control of Major Accident Hazards Involving Dangerous Substances) Regulations 2015 applies

MSD Ireland (Ballydine) , Ballydine , Kilsheelan Clonmel Co. Tipperary

245m
21407CONDITIONAL30 Mar 2021

construction of a proposed three-storey pilot plant manufacturing facility sized approximately 3,266 square metres and approximately 20.75 metres high and located and linked to the existing factory 03 manufacturing building and located south of the O.S.D. manufacturing facility, currently under construction (ref. 20/693). The project development alos includes the following: a) An equipment yard housing plant, equipment and abatement system, vents and equipment housings including a covered waste tank, b) Roof mounted equipment and vents, c) Modifications to existing underground utilities including a surface water attenuation tank, underground storage tanks and miscellaneous works, d) The extension of the temporary contractors’ compound, currently under construction and additional local temporary contractor parking together with a second compound directly adjacent to the proposed facility, e) Revised landscaping and site-works, f) Modifications to the existing internal roads layouts, site lighting, pipe bridges, links, bunded tanks and supporting structures, and a truck staging area, g) Modifications to the existing car park layout to allow for the inclusion of additional accessible car parking spaces and electrical charge points, h) Alterations to the elevations of Factory 03 to accommodate the proposed development. This application consists of a development for an activity for which a licence under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act 2003) is required. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) accompany this planning application. This is a site to which the Chemicals Act (Control of Major Accident Hazards involving dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies

Ballydine , Kilsheelan , Clonmel

302m
2040CONDITIONAL21 Jan 2020

a 135sqm extension to a utility building to enclose water storage vessels, maintenance platform and associated equipment. This application refers to a development on a site that carries out an activity for which an Industrial Emissions licence under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required and where the Major Accident Directive applies

Ballydine , Kilsheelan , Clonmel