Flemingstown , Clogheen , Co. Tipperary
CONDITIONALPlanning application 2460809
Tipperary - Tipperary County Council
Proposed Development
the construction of a sheep grid with access gate on local road and all associated site works
Application Timeline
Application received
24 Sept 2024
Further information requested
18 Nov 2024
Further information received
23 Mar 2025
Decision: CONDITIONAL
16 Apr 2025
Decision due
19 Apr 2025
Grant issued
20 May 2025
Application Details
- Location
- Flemingstown , Clogheen , Co. Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 0.22 ha
Timeline
- Registration Date
- 24 September 2024Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 16 April 2025
- Grant Date
- 20 May 2025
- Permission Expires
- 19 May 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
(i) cubicle shed with loose straw area and underground effluent tanks (ii) farm office building containing canteen, office, boot room, shower room and toilets and all associated site works
Doon , Araglin , Co. Tipperary
and completion of new farm office building (currently under construction), connection to existing septic tank and all associated ancillary site works. Retention permission is also being sought for existing extension to cubicle house, slatted underground effluent storage tank and loose house and all associated ancillary site works
Doon , Araglin , Co. Tipperary
Retention (i) Second stage house extension (ii) Loose dry sow house extension and all associated site works
Doon , Araglin
(i) second stage house extension (ii) loose dry sow house extension and all associated site works
Doon , Araglin , Co. Tipperary
construction of pig house with underground slatted effluent tank and all associated site works
Doon , Araglin , Co. Tipperary
cubicle shed extension with underground effluent tank and all associated site works
Doon , Araglin , Co. Tipperary
second stage house extension and all associated site works
Doon , Araglin , Co. Tipperary
second stage house extension and all associated site works
Doon , Araglin , Co. Tipperary
construction of (i) loose dry sow house with underground slatted effluent tank and all associated site works
Doon , Araglin , Co. Tipperary
Retention (i) Second stage house extension (ii) Loose dry sow house extension and all associated site works
Doon , Araglin
Planning a project of your own?