Proposed Development

development which will consist of: The power plant comprising the following main components; Engine Hall comprising up to 6 no. dual fuel gas/diesel IC reciprocating engines and associated generating equipment; 1 no. exhaust stack cluster; Electrical Annex Building; 1 No. 120 MW Step-up transformer; Workshop/Stores Building; Administration Building; Radiator Coolers; Bunded Tank Farm comprising: 2 x Fuel Oil Storage Tank, SCR reagent Tank, Lube Oil Storage Tank, Lube Oil Maintenance Tank, Lube Oil Disposal Tank, Pilot Oil Tank; Cycle shed; Fire pump house, Firefighting water tank; Surface Water Attenuation Tank, Raw Water Storage Tank; Fencing; Car Park; Landscape planting around perimeter of site and all ancillary services

View the full application file on the council's planning portal →

Application Details

Location
Ard Gaoithe Technology Park , Ard Gaoithe Lawlesstown , Clonmel
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Tipperary County Council
Site Area
2.8 ha

Timeline

Registration Date
28 May 2026
Status
INCOMPLETED APPLICATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

62m
2660540N/A3 Jun 2026

a power plant comprising the following main components; Engine Hall comprising up to 6 no. dual fuel gas/diesel IC reciprocating engines and associated generating equipment; 1 no. exhaust stack cluster; Electrical Annex Building; 1 No. 120 MW Step-up transformer; Workshop/Stores Building; Administration Building; Radiator Coolers; Tank Farm comprising: 2 x Fuel Oil Storage Tanks, SCR reagent Tank, Lube Oil Storage Tank, Lube Oil Maintenance Tank, Lube Oil Disposal Tank, Pilot Oil Tank; Standby Generators; Cycle shed; Fire pump house, Firefighting water tank; Surface Water Attenuation Tank; Raw Water Storage Tank; Fencing; Car Park; Landscape planting around perimeter of site and all ancillary services. The plant is subject to a pollution control licence from the EPA

Ard Gaoithe Technology Park , Ard Gaoithe Lawlesstown , Clonmel

143m
22174CONDITIONAL1 Mar 2022

the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited is to apply for a change of use for the existing 100 square metre cottage, which is a protected structure on the development from domestic to office use. Existing outbuildings and sheds are proposed to be demolished.

Ard Gaoithe , Lawlesstown , Clonmel

151m
2461039CONDITIONAL5 Dec 2024

the construction of a wholesale warehouse including all associated site development works such as yards, carparking areas, fencing, lighting, drainage and access from the existing Ard Gaoithe Business Park road

Ard Gaoithe Business Park , Lawlesstown , Clonmel

159m
22138N/A18 Feb 2022

the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited intend to apply for a change of use for the existing cottage on the development from domestic to office use

Ard Gaoithe , Lawlesstown , Clonmel

169m
22113N/A11 Feb 2022

the proposed development will consist of the construction of 3 no. warehousing/light industrial units (with a floor area of 1029sqm for building 1, a floor area of 1430 sqm for building 2 and a floor area of 1430 sqm for building 3, parking spaces and all associated services. In addition, Flamewell Limited intend to apply for a change of use for the existing cottage on the development from domestic to office use

Ard Gaoithe , Lawlesstown , Clonmel

192m
22689CONDITIONAL21 Dec 2022

the construction of a light industrial Unit which will be sub-divided into 3no units each incorporating two-storey office space. The proposed development will include an access road off the existing Ard Gaoithe Business Park road, roads, yards, carpark area, site fencing, site lighting and all associated siteworks including connection to all existing site services

Ard Gaoithe Business Park , Lawlesstown , Clonmel

211m
2560495CONDITIONAL30 May 2025

the alterations to previously granted permission (PD. Ref: 22689), incorporating the amalgamation of units 1 and 2 and for the change of use from light industrial to warehouse and storage use, together with all associated site development works

Ard Gaoithe Business Park , Lawlesstown Clonmel , Co. Tipperary

240m
22602N/A13 Oct 2022

the erection of a 0.9m high masonry wall with 1m high palisade railing fixed on top, to boundaries of existing car park forming a new secure compound with new gate at existing entrance

Unit 3a Ard Gaoithe Business Park , Clonmel , Co. Tipperary

240m
19600515CONDITIONAL15 May 2019

(a) An extension to the existing waste intake shed including backlit signage, (b) A new higher roof to existing waste intake shed, (c) An open fronted shed over the WEEE area, (d) An open fronted shed to the wood picking area, (e) New concrete storage bays, (f) New 2 storey weighbridge building and weighbridge, (g) New single storey prefabricated clock in and staff locker building, (h) 2 new vehicular entrances including re-aligned hedgerows and widened roadways, (i) New staff carparking and paladin fence surround, (j) New elevated walkway, (k)Relocation of existing fuel storage tank on site, (l) Expansion of concrete yards, (m) New packaged waste water treatment system and percolation area on site, (n) New metal sheeted fence and gate, (o) New 9m high post and mesh windbreak to rear of wood-picking area AND FOR PERMISSION FOR THE INDEFINITE RETENTION OF (p) Concrete storage bays, (q) A single storey prefabricated staff welfare facility consisting of toilets, showers, canteen and meeting room

Lawlesstown , Clonmel , Co. Tipperary

249m
22616CONDITIONAL28 Oct 2022

the construction of a boundary wall to existing parking area consisting of a 900 mm rendered blockwork wall including concrete cap with 1000mm decorative palisade type railing fixed on top, and the erection of a new security gate at existing property entrance and assoicated site works

Unit 3a Ard Gaoithe Business Park , Clonmel , Co. Tipperary

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?