Waterford Industrial Estate 38 KV substation , Waterford Industrial Estate , Cork Road
CONDITIONALPlanning application 18601
Waterford - Waterford City and County Council
Proposed Development
Retention permission for the existing 36 metre high lattice communications structure, carrying radio antennae, including dishes, within a 2.4 metre high palisade compound, shared with other licenced operators following on from the previous parent permission LPA ref: 12/129
View the full application file on the council's planning portal →Application Timeline
Application received
4 Sept 2018
Decision: CONDITIONAL
25 Oct 2018
Decision due
29 Oct 2018
Appeal submitted
20 Nov 2018
Application Details
- Location
- Waterford Industrial Estate 38 KV substation , Waterford Industrial Estate , Cork Road
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Waterford City and County Council
Timeline
- Registration Date
- 4 September 2018
- Status
- APPEALED
- Decision
- CONDITIONAL
- Decision Date
- 25 October 2018
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP30303618
- Submitted
- 20 November 2018
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
single storey warehouse extension to rear (South) over existing open yard area, together with all associated site development works all
Keltech , 37-38 Waterford Industrial Park , Cork Road
single storey warehouse extension to rear (South) over existing open yard area, together with all associated site development works all at
Keltech Ltd , 37-38 Waterford Industrial Park , Cork Road
for the proposed Part 1 storey & Part 2 storey extension (9424m2 approx.) to the Northern & Eastern sides of the existing Bausch & Lomb Ireland facility. This extension is to include new production facilities, storage areas, staff offices, link corridors and staff accommodation. This is also to include new delivery facilities including loading docks and associated marshalling yards, plant rooms and to include minor internal and external modifications to the existing building - The proposed provision of new access road and vehicular entrance gateway to the northern boundary of the site, this is to allow vehicular access to the site from the existing roundabout on the Old Kilmeaden Rd. - These works are to include all associated plant and equipment, site works, site fencing, signage, staff parking facilities and alterations to internal road network and drainage. - This application relates to development for the purposes of the activity requiring an Industrial Emissions Licence. - This application is to be accompanied by an Natura Impact Statement (NIS)
Unit 424-425 , IDA Industrial Estate , Cork Road
to construct 31 car parking spaces off the estate road adjacent to
Unit 502 at Western Extension , Industrial Estate , Cork Road
the proposed construction of a new 265.8m2 single storey warehouse extension (7.39 metres high to match existing parapet height) to the western end of the existing Unit 301, to include alterations to external western elevation with proposed Kingspan cladding to match existing, together with all associated site works
Teva Pharmaceuticals Ireland , Unit 301 IDA Industrial Estate , Cork Road
to install 1,600msq of roof mounted Solar PV Panels to both sides of 3 No. pitched roofs in 3 No. arrays, together with handrail at roof edge of eaves level, surrounding panels and all associated site development works
Keltech , Waterford Industrial Estate , Cork Road
for a single storey warehouse extension located between existing Keltech buildings over their existing car park with all ancillary site development works at
Keltech , 37-38 Waterford Industrial Park , Cork Road
EXTENSION OF DURATION OF Planning Ref. 13500060: Planning permission sought by Teva Pharmaceuticals Ireland for extension consisting of warehousing, loading bays, plant rooms, associated car parking and landscaping. The floor area is 1,996m2, the building is 17.1 meters high and the development is located
Unit 14/15 , Waterford Industrial Estate , Cork Road
change of use from office use (ancillary to a manufacturing/storage facility) to a managed mixed office use over two-storeys to the front of existing building and retention permission for new signage and elevational changes to front and side of existing building together with permission for a change of use from a manufacturing/storage facility to a sub-divided, centrally managed, mixed use development consisting of: manufacturing/storage units, pharmaceutical research & development incubation hubs together with offices, to accommodate science & technology sales, enterprise & training, innovation and specialist uses, and permission for elevational changes, internal modifications, connection to existing public services and all associated site works
Units 24F 25F & 26F , Waterford Industrial & Business Park , Cork Road
the construction of a new 10.8m2 external oil tank compound with rendered blockwork walls to match existing bin store to the front of existing building
Teva Pharmaceuticals Ireland , Unit 301 IDA Industrial Estate , Cork Road
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?