← Back to search

Clashnagoneen , Cappagh , Co. Waterford

CONDITIONAL

Planning application 22677

Waterford - Waterford City and County Council

Proposed Development

continuance of use, indefinitely, of a commercial store with office and all ancillary works, as previously granted planning permission under Reference No. 17/338

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    28 Jul 2022

  2. Further information requested

    20 Sept 2022

  3. Further information received

    27 Feb 2023

  4. Decision: CONDITIONAL

    5 Apr 2023

  5. Decision due

    11 Apr 2023

  6. Grant issued

    9 May 2023

Application Details

Location
Clashnagoneen , Cappagh , Co. Waterford
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Waterford City and County Council

Timeline

Registration Date
28 July 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
5 April 2023
Grant Date
9 May 2023
Permission Expires
8 May 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

4m
17338CONDITIONAL18 May 2017

RETENTION for a change of use from an agricultural store to a commercial store with office and retention planning permission for a septic tank and all ancillary works

Clashnagoneen , Cappagh , Co Waterford

10m
20430N/A2 Jul 2020

to construct an extension to existing commercial unit with associated works at

Clashnagoneen , Cappagh , Co Waterford

10m
20565REFUSED17 Aug 2020

to construct an extension to existing commercial unit with associated works at

Clashnagoneen , Cappagh , Co Waterford

210m
2460269N/A17 May 2024

to construct slatted shed with loose area and all associated site works

Clashnagoneen , Cappoquin , Co. Waterford

210m
2460296CONDITIONAL30 May 2024

to construct slatted shed with loose area and all associated site works

Clashnagoneen , Cappoquin , Co. Waterford

320m
20171CONDITIONAL16 Mar 2020

single storey dwelling house, garage/store, entrance, septic tank, percolation area and all ancillary site works at

Ballyhane , Cappoquin , Co Waterford

557m
17550CONDITIONAL31 Jul 2017

to construct a one-and-a-half-storey extension to the side of dwelling , a single-storey extension to the rear, to renovate existing dwelling which will include raising part of the roof of the existing dwelling, replace the existing septic tank with a wastewater treatment system in accordance with the EPA Code Of Practice on single dwellings and all ancillary site works

Ballyhane (E.D. Modelligo) , Cappoquin , Co. Waterford

596m
17564REFUSED4 Aug 2017

for development consisting of a 10 year permission for the construction of a Solar PV Energy development within a total site are of up to 62.8hA, to include one single-storey electrical substation building and associated compound electrical transformer/inverter station modules, solar PV panels ground mounted on steel support structures,access roads, fencing and associated electrical cabling, ducting and ancillary infrastructure

Ballyard Ballyhane & Clashnagoneen , Cappoquin , Co Waterford

707m
17902CONDITIONAL22 Dec 2017

the partial demolition of existing dwelling, demolition of existing outbuilding, construction of new extensions to East & West Elevations and carport to North Elevation, changes to existing elevations, alterations to existing site entrance and for ancillary site works

Boherawillin , Modeligo , Dungarvan

950m
2660471N/A25 Jun 2026

10-year permission for a solar farm, within a total site area of c.149.12ha, comprising of the following:- - Solar photovoltaic panels on ground mounted frames. The solar panels are arranged within a site area of c. 145.17ha, with an expected lifespan of 40 years; - 18 no. single-storey transformer stations; - 4 no. single-storey storage containers; - Underground electric ducting, cabling and joint bays within the development site and within the N72, R671, and unclassified local roads known locally as Nicholastown and Ballyard to connect the solar farm field parcels. The site area within the public road is c. 3.95ha; - An overhead networking cable of approximately 30m in length supported by 2no. wooden ESB poles crossing the River Finisk; - A new entrance to the Drumroe site from the N72, upgrades to 2 no. existing entrances at Clashnagoneen from the unclassified local roads known locally as Nicholastown and Ballyhane and 2 no. additional entrances to the northern parcels of the Clashnagoneen site from unclassified local road known locally as Ballyard, upgrades to the existing entrance to the Kilcannon site from the L1013, internal access tracks and a clear span bridge over the Clashnagoneen stream; - Security fencing, CCTV, landscaping and all associated ancillary site and development works. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

Drumroe Clashnagoneen Kilcannon (Osborne) and adjoining townlands , East of Cappoquin west of Cappagh south of Modeligo , Co. Waterford.