Proposed Development

for a Solar Photovoltaic Array comprising 71,500m² of solar panels exporting a maximum of 10 megawatts to the National Grid, associated single storey control buildings including ESB Substation, Client-side Substation, Communications Building, Storage Building and 4no. Inverters, ancillary equipment, fencing and access road extension.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    17 Oct 2023

  2. Further information requested

    6 Dec 2023

  3. Further information received

    20 Feb 2024

  4. Decision: CONDITIONAL

    13 Mar 2024

  5. Decision due

    18 Mar 2024

  6. Grant issued

    17 Apr 2024

Application Details

Location
Pickardstown , Tramore , Co. Waterford
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Waterford City and County Council
Site Area
12 ha

Timeline

Registration Date
17 October 2023Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
13 March 2024
Grant Date
17 April 2024
Permission Expires
16 April 2029

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

485m
17746CONDITIONAL24 Oct 2017

to demolish existing sunroom and construct a single storey kitchen extension with minor internal and side elevation alterations, together with all associated site works

Forest View , Drumcannon , Tramore

533m
18510CONDITIONAL27 Jul 2018

construct a single store extension to the side and rear of dwelling

Ballinattin , Tramore , Co. Waterford

689m
2460190REFUSED16 Apr 2024

for a residential development consisting of demolition of existing derelict property and the construction of 3 No. two-storey dwellings, together with all associated site development works at Crobally Upper, Tramore, Co. Waterford.

Crobally Upper , Tramore , Co. Waterford

744m
17449REFUSED23 Jun 2017

the erection of 3 detached dormer type houses, new access off Gleann Doire, connections to public sewer and water mains and all associated site works

Gleann Doire & Glen Road , Tramore , Co. Waterford

746m
19357CONDITIONAL24 May 2019

the erection of 3 detached dormer type houses, new access off Gleann Doire, connections to public sewer and water mains and all associated site works

Gleann Doire & Glen Road , Tramore , Co. Waterford

765m
17271CONDITIONAL20 Apr 2017

to retain the rear extension to dwelling, planning permission to construct an extension to the front of dwelling and all ancillary site works

Orchard Cottage , 6 Glen Road , Tramore

793m
19160N/A12 Mar 2019

Extension to existing cottage and all associated site works

River cottage , Pickardstown , Tramore

807m
19473CONDITIONAL28 Jun 2019

the construction of a ground floor single storey rear extension, flat roof dormer window to the front, first floor gable window to the front, solar panels to the south facing rear roof and all associated site works

Pickardstown , Tramore , Co. Waterford

865m
21183CONDITIONAL10 Mar 2021

change of use from storage to habitable use at lower ground floor, and altered site boundaries, together with permission for change of use from residential use to community based care home for four residents, permission to demolish existing store to facilitate a new split-level extension to side of existing house, elevational changes, connection to on-site services and all associated site works

Crobally Upper , Pickardstown , Tramore

888m
1940CONDITIONAL29 Jan 2019

the construction of a two-storey dwelling plus associated site works

Crobally Lower , Tramore , Co. Waterford

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?