← Back to search

IDA Ardmore Business & Technology Park , Mullingar , Co.Westmeath

CONDITIONAL

Planning application 22347

Westmeath - Westmeath County Council

Proposed Development

a new Advanced Building Solution consisting of office and light industrial/production spaces. Permission is also sought for vehicular/pedestrian entrance, signage, new timber post-and-rail boundaries, car parking, cycle shelters, landscaping, gas skid, underground storage tank, independent ESB substation & switch room building, access road and all associated site works. The development has been subject of a Screening for Appropriate Assessment in accordance with Article 6(3) of the EU Habitats Directive (Directive 92/43/EEC) and the Planning and Development Act 2000 as amended. The Screening for Appropriate Assessment will be submitted to the Planning Authority with the Planning Application

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    1 Jul 2022

  2. Further information requested

    25 Aug 2022

  3. Further information received

    28 Oct 2022

  4. Decision due

    24 Nov 2022

  5. Decision: CONDITIONAL

    24 Nov 2022

  6. Grant issued

    29 Dec 2022

Application Details

Location
IDA Ardmore Business & Technology Park , Mullingar , Co.Westmeath
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Westmeath County Council

Timeline

Registration Date
1 July 2022
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
24 November 2022
Grant Date
29 December 2022
Permission Expires
28 December 2027

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

154m
2660324N/A20 Jun 2026

development at the site at Ardmore Business & Technology Park. The site is c. 1.307 hectares in size. It is made up of greenfield lands together with sections of existing road, footpath and cycleway. It is bound to the north, east and west by estate roads within Mullingar Business Park (with access from the N52), and to the south by an existing hedgerow. The development will consist of: [1] The construction of an Advanced Building Solution (ABS) building ranging from one to three storeys (6.2 meters (m) to 14.2 m in height), with a gross floor area of 2,500 square meters (sq. m) to accommodate light industrial / manufacturing and office uses. The building will comprise: (a) A three-storey reception and support office block (12.7 m to 14.2 m in height, 700 sq. m in area) providing covered entrance, reception, administration, staff welfare facilities, ancillary office space and plant rooms; (b) A light industrial / manufacturing production space (10 m clear internal height, 12.7 m to 14 m externally, 1,725 sq. m in area); (c) A single-storey services block (6.2 m in height, 75 sq. m in area) accommodating a substation, switchroom and waste storage area, together with an associated external services yard; and (d) The provision of c. 300 sq. m of photovoltaic panels at roof level. [2] The modification of two existing vehicular access points to provide one point of vehicular and pedestrian access and one point of articulated lorry access; the creation of a new shared pedestrian / cycle entrance point and path. [3] The construction of 41 no. car parking spaces (including 3 no. accessible spaces and 7 no. EV charging spaces) and 42 no. bicycle parking spaces (6 no. Sheffield bicycle stands and 15 no. bicycle stands under shelters, each stand accommodating 2 no. bicycles). [4] The provision of a new uncontrolled pedestrian and cycle crossing in the Mullingar Business Park Estate Road and the northern part of the site, together with associated vehicular and pedestrian signage and ancillary works. [5] All associated and ancillary site development works, site and landscape clearance, the installation of hard and soft landscape planting; drainage infrastructure; fencing and boundary treatments; building, vehicular and pedestrian signage; utilities and site services; and all associated site works

Mullingar (Ardmore) Business & Technology Park , Marlinstown Ardmore , Mullingar Co. Westmeath

204m
176222CONDITIONAL10 Aug 2017

Upgrade works to the existing entrance with the installation of a new security gate and fencing, installation of security cameras including cabinets and installation of a new rigid wire mesh boundary fence around the entire site (approx. 2.4km)

Ardmore IDA Business & Technology Park , Marlinstown , Mullingar

304m
2560115CONDITIONAL19 Mar 2025

development which will consist of the following works: 1. Full Permission is sought for the construction of a new shipping area and tank storage extension building to the rear of the existing building. 2. Retention Permission is also sought for the as constructed engine storage facility building to the rear of the existing building together with the security fencing erected along the northeastern boundary all as shown on the submitted drawings with all ancillary site works and services

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar County Westmeath

304m
2460117N/A15 Apr 2024

A temporary free standing shipping area extension to move completed products for final dressing and shippping.

Unit 1 IDA Ardmore Business & Technology Park I Marlinstown I Mullingar I Co. Westmeath I Ireland I N91 R762 , Marlinstown , Mullingar

304m
22257CONDITIONAL17 May 2022

development consisting of the installation of a roof mounted solar photovoltaic panels to include all ancillary works and services

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar

304m
22178N/A7 Apr 2022

The development will consist of the installation of a roof mounted solar photovoltaic panels to include all ancillary works and services.

Unit 1 IDA Ardmore Business & Technology Park , Marlinstown , Mullingar Co. Westmeath

320m
2260036CONDITIONAL16 Dec 2022

development of 65 no. residential units at Ardmore Hills, Marlinstown, Mullingar, Co. Westmeath, a site of circa. 2.24 Has. The proposed development will comprise the construction of 3 no. 2-bedroom semi-detached & mid-terrace houses; 32 no. 3-bedroom semi-detached & mid-terrace houses; 27 no. 4-bedroom semi-detached houses; 3 no. 5-bedroom detached houses. The development provides for 123 no. car parking spaces, provision of communal open spaces, all associated hard and soft landscaping, boundary treatments, footpaths, and all other ancillary works above and below ground

Ardmore Hills Marlinstown , Mullingar , Co. Westmeath

401m
2360224CONDITIONAL14 Jul 2023

development which will consist of an extension of the internal road network from the existing 1-arm roundabout located to the West of the site. The development will include a road extension (approximately 75m long), associated footpaths, public lighting and all associated services and site works to facilitate the development

IDA Ardmore Business & Technology Park , Marlinstown Ardmore , Mullingar Co. Westmeath

411m
22495CONDITIONAL12 Oct 2022

Consisting of an extended hardstanding area(50m x 37m) for improved circulation, facilitating current operations, and a complementary enhanced landscaping amenity area adjacent to the existing premises and all associated ancillary works.

Unit 1 IDA Ardmore Business and Technology Park , Marlinstown , Mullingar

471m
176126CONDITIONAL24 Apr 2017

to construct 10 new detached dwelling houses, new boundary walls, roads, footpaths and all associated site services at 79, 80, 81, 82, 83, 84, 85, 86, 87,88 Ardmore Hills.

Ardmore Hills , Ardmore Road , Mullingar