Barrettspark, New Ross Rural
Granted (Conditional)Planning application 20211885
Wexford - Wexford County Council
Proposed Development
Permission for retention of an extension constructed to the side of an existing
Application Timeline
Application received
3 Dec 2021
Decision due
27 Jan 2022
Decision: Granted (Conditional)
4 Feb 2022
Grant issued
9 Mar 2022
Application Details
- Location
- Barrettspark, New Ross Rural
- Applicant
- N/A
- Application Type
- Retention
- Planning Authority
- Wexford County Council
- Site Area
- 0.15 ha
- Residential Units
- 1
Timeline
- Registration Date
- 3 December 2021Other applications received that week
- Status
- Decision Made
- Decision
- Granted (Conditional)
- Decision Date
- 4 February 2022
- Grant Date
- 9 March 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for the erection of an extension to an existing dwelling
Castlemoyle, New Ross Urban
Permission for the following to an existing residential property: demolition
Irishtown, New Ross Urban
Permission for retention of the following: pitched roof to converted garage
Irishtown, New Ross Urban
Permission is sought for alterations to previously approved planning ref:
Irishtown, New Ross Urban
Permission for retention for the change of use from existing retail unit
Irishtown, New Ross Urban
Permission for the erection of a ground floor extension to the side and rear of
Irishtown, New Ross Urban
Permission for the change of use from commercial property to residential & 2 sto
New Ross, New Ross Urban
Permission for change of use from commercial property to residential property &
New Ross, New Ross Urban
Permission for change of use from a commercial property to a residential propert
New Ross, New Ross Urban
Permission for retention for a rear extension to an existing fully serviced
New Ross, New Ross Urban