Crosstown, Ardcavan
Granted (Conditional)Planning application 20261102
Wexford - Wexford County Council
Proposed Development
Permission to construct 2 no. fully serviced dormer-style houses, new
Application Timeline
Application received
20 Aug 2026
Further information requested
9 Oct 2026
Further information received
15 Oct 2026
Decision: Granted (Conditional)
6 Nov 2026
Decision due
11 Nov 2026
Application Details
- Location
- Crosstown, Ardcavan
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Wexford County Council
- Site Area
- 0.8 ha
- Residential Units
- 2
Timeline
- Registration Date
- 20 August 2026Other applications received that week
- Status
- n/a
- Decision
- Granted (Conditional)
- Decision Date
- 6 November 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
PERMISSION FOR DEVELOPMENT CONSISTING OF A). PROPOSED CHANGE OF USE FROM RETAIL
TOWNPARKS, WEXFORD URBAN NO. 3
PERMISSION FOR RETENTION OF AN EXISTING BIN STORE AND PLANNING PERMISSION TO REM
TOWNPARKS, WEXFORD URBAN NO. 3
RETENTION FOR DEVELOPMENT AT NO. 3 REDMOND COVE. THE DEVELOPMENT WILL CONSIST
TOWNPARKS, WEXFORD URBAN NO. 3
Permission for the proposed erection of alterations and extension to existing
Townparks, Wexford Urban No. 3
Permission for retention of the amalgamation of 2 no. untis into 1 no. unit toge
Townparks, Wexford Urban No. 3
Permission for retention of the amalgamation of 2 no units into 1 no unit togeth
Townparks, Wexford Urban No. 3
Install a public digital phone to replace the old RIR payphone.
Redmond Quay, Wexford
PERMISSION FOR THE CONSTRUCTION OF A SINGLE STOREY EXTENSION TO THE SIDE OF
TOWNPARKS, WEXFORD URBAN NO. 2
Proposed works to Loreto Graveyard are only (Protected Structure Ref Numbers WBC
Townparks, Wexford Urban No. 3
DEMOLITION, FOR SAFETY REASONS, OF THE EXISTING STRUCTURE TOGETHER WITH ASSOCIAT
TOWNPARKS, WEXFORD URBAN NO.3
The submission window has closed
A decision issued on this application, so observations can no longer be made. Anyone who made a submission during the five-week window can appeal to An Coimisiún Pleanála within four weeks of the decision — until Friday 4 December 2026 — for a fee of €220.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?