← Planning Wire · Cork County Council news

Battery storageDecisionCork

Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork

22 November 2023 · Permission.ie Planning Wire · from the Cork County Council planning register · published 31 August 2026

Cork County Council refused permission on 22 November 2023 for a battery energy storage plant at Cobh Co.Cork, an application first lodged on 28 September 2023.

Key facts

Reference
23/5947
Planning authority
Cork County Council
Location
Belvelly Port Facility Marino (Townlands) Marino Point, Cobh Co.Cork
Received
28 September 2023
Application type
Permission
Status
Application Closed
Decision
Refused
Decision date
22 November 2023

In context

It is one of 14 battery storage applications Cork County Council has received in the past twelve months, against 60 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 22 November 2023. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Cork County Council register. This is the source for every figure in the story above.

The proposed development will consist of; 1) the construction of a stationary battery energy storage system which will include 154 no. 20ft. containers and 22 no. medium voltage transformers and connection to the existing substation, 2) the construction of a new internal access road, to connect to an internal road previously permitted under application register reference: 19/6783, which will connect to an existing internal road on the Marino Point site, with access from an existing entrance on the R624, 3) heating, ventilation and air condition units and all other associated site, boundary and development works. A Natura Impact Statement has been prepared in respect of the proposed development and will be submitted to the planning authority with this application.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork", 22 November 2023. https://www.permission.ie/news/cork-county-council/23%2F5947

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/cork-county-council/23%2F5947">Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork</a>, Permission.ie analysis of the national planning register, 22 November 2023.</p>
Full application record

Map, site boundary, timeline and nearby applications for 23/5947.

Cork planning register

Every application lodged in Cork, updated daily.

Get stories like this the day they are lodged

A county watch emails you every new application in Cork the week it appears.

Set up alerts
Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork | Permission.ie