Battery storageDecisionCork
Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork
22 November 2023 · Permission.ie Planning Wire · from the Cork County Council planning register · published 31 August 2026
Cork County Council refused permission on 22 November 2023 for a battery energy storage plant at Cobh Co.Cork, an application first lodged on 28 September 2023.
Key facts
- Reference
- 23/5947
- Planning authority
- Cork County Council
- Location
- Belvelly Port Facility Marino (Townlands) Marino Point, Cobh Co.Cork
- Received
- 28 September 2023
- Application type
- Permission
- Status
- Application Closed
- Decision
- Refused
- Decision date
- 22 November 2023
- Council file
- View on the Cork County Council planning portal
In context
It is one of 14 battery storage applications Cork County Council has received in the past twelve months, against 60 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.
What happens next
The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 22 November 2023. If no appeal is lodged, the council’s decision stands and a final grant issues.
The development description, as lodged
Verbatim from the Cork County Council register. This is the source for every figure in the story above.
The proposed development will consist of; 1) the construction of a stationary battery energy storage system which will include 154 no. 20ft. containers and 22 no. medium voltage transformers and connection to the existing substation, 2) the construction of a new internal access road, to connect to an internal road previously permitted under application register reference: 19/6783, which will connect to an existing internal road on the Marino Point site, with access from an existing entrance on the R624, 3) heating, ventilation and air condition units and all other associated site, boundary and development works. A Natura Impact Statement has been prepared in respect of the proposed development and will be submitted to the planning authority with this application.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork", 22 November 2023. https://www.permission.ie/news/cork-county-council/23%2F5947
<p>Source: <a href="https://www.permission.ie/news/cork-county-council/23%2F5947">Cork County Council refuses permission for battery energy storage plant at Cobh Co.Cork, Co. Cork</a>, Permission.ie analysis of the national planning register, 22 November 2023.</p>
Map, site boundary, timeline and nearby applications for 23/5947.
Cork planning registerEvery application lodged in Cork, updated daily.
Get stories like this the day they are lodged
A county watch emails you every new application in Cork the week it appears.
Set up alerts