Battery storageLodgedDonegal
Battery energy storage plant proposed at CROCKAHENNY, INISHOWEN, Co. Donegal
18 March 2026 · Permission.ie Planning Wire · from the Donegal County Council planning register · published 1 September 2026
An applicant lodged plans with Donegal County Council on 18 March 2026 for a battery energy storage plant at CROCKAHENNY, INISHOWEN. The application seeks a 10-year permission and the accelerated RED III consenting route for renewables.
Key facts
- Reference
- 2660441
- Planning authority
- Donegal County Council
- Location
- CROCKAHENNY, INISHOWEN, CO. DONEGAL
- Received
- 18 March 2026
- Application type
- PERMISSION
- Site area
- 0.5 hectares
- Permission sought
- 10 years
- Status
- INCOMPLETED APPLICATION
- Submissions until
- 21 April 2026 (closed)
In context
It is one of 5 battery storage applications Donegal County Council has received in the past twelve months, against 59 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.
What happens next
The five-week window for public submissions has closed. The council normally decides within eight weeks of the application being lodged, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Donegal County Council register. This is the source for every figure in the story above.
A 10 YEAR PLANNING PERMISSION FOR A LONG DURATION ENERGY STORAGE FACILITY CONSISTING OF: INSTALLATION AND OPERATION OF 1 NO. BATTERY ENERGY STORAGE SYSTEM COMPOUND CONTAINING BATTERY ENERGY STORAGE CONTAINERS, 1 NO. ELECTRICAL SUBSTATION AND COMPOUND, CONNECTION TO THE NATIONAL GRID SYSTEM VIA 50M OF UNDERGROUND CABLE TO THE ESB CROCKAHENNY 38KV SUBSTATION, ELECTRICAL TRANSFORMERS AND INVERTER UNITS, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES, CCTV, INTERNAL ACCESS ROAD, ASSOCIATED ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFESPAN OF THE DEVELOPMENT WILL BE 35 YEARS AND THE SITE OF THE PROPOSED DEVELOPMENT HAS A TOTAL AREA OF C. 0.54 HECTARES. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Battery energy storage plant proposed at CROCKAHENNY, INISHOWEN, Co. Donegal", 18 March 2026. https://www.permission.ie/news/donegal-county-council/2660441
<p>Source: <a href="https://www.permission.ie/news/donegal-county-council/2660441">Battery energy storage plant proposed at CROCKAHENNY, INISHOWEN, Co. Donegal</a>, Permission.ie analysis of the national planning register, 18 March 2026.</p>
Map, site boundary, timeline and nearby applications for 2660441.
Donegal planning registerEvery application lodged in Donegal, updated daily.
Get stories like this the day they are lodged
A county watch emails you every new application in Donegal the week it appears.
Set up alerts