Dublin City Council grants permission for battery energy storage plant at Dubli, Dublin

28 August 2025 · Permission.ie Planning Wire · from the Dublin City Council planning register · published 31 July 2026

Dublin City Council granted permission on 28 August 2025 for a battery energy storage plant at Dubli, an application first lodged on 30 May 2025.

Key facts

Reference
WEB2226/25
Planning authority
Dublin City Council
Location
a c. 1.7 ha site located within the ESB Inchicore substation site, specifically lands south of Kylemore Way and northwest of the existing ESB Substation, Kylemore Way, Dublin 8, D08 E398 and to the immediate west of the Kylemore BESS, Kylemore Road, Dubli
Received
30 May 2025
Application type
Permission
Site area
2 hectares
Status
Decision Notice Issued
Decision
GRANT PERMISSION
Decision date
28 August 2025

In context

There were 59 nationally in the past twelve months. Of the 72 such applications decided by councils in the past three years, 78% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 28 August 2025. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Dublin City Council register. This is the source for every figure in the story above.

The proposed development will consist of a battery energy storage system (BESS) located within a fenced compound and will (subject to detailed design, commercial and technical considerations) comprise of 1. Up to 60 no. battery energy storage enclosures, split across 6 no. bays, each bay contains 2 no. rows of 5 no. enclosures. Each bay is on a concrete plinth of width c. 6.5 m and a maximum length of c. 47 m. Each battery enclosure will incorporate battery packs as well as power electronics, battery management systems, cooling units and fire suppression systems. 2. 6 No. Medium Voltage (MV) Skids , twin Inverter Skids (c. 12.8m x 6m x 2.4m) and associated bunds and fire walls. 3. Control building (c. 222 sq.m). 4. Ancillary plant and equipment comprising of a) A firefighting water tank (c. 9.75m high) and pumphouse (c. 17 sq.m) b) 2 no. Auxiliary Transformers (c. 2m x 2m x 2m) and associated bunds and fire walls c) 3 no. spare parts stores (20ft containers) (c. 15 sq.m each) d) 2 no. backup diesel generator plinths (c. 28.7 sq.m each) e) HV compound including 2 no. Grid step-up transformers (c. 5.7m x 3.3m x 2.8m and c. 6.6m x 5.5m x 5.1m), associated bunds and fire walls, and all other associated equipment including prefabricated electrical control room (c. 51 sq.m), linking with an underground cable and f) An underground fire water retention tank and underground attenuation tank. 5. Operation and Maintenance site offices including welfare facilities (c. 27.9 sq.m) 6. All service connections including electrical, potable water and connections to surface water drains 7. 1 no. lightning monopole (c. 18m high) and 8. All other ancillary site clearance and development works including provision of areas of hardstanding, internal access roads lighting and CCTV, laydown area, fencing and access gates (c. 3.5m in height), car parking; and connections to site services and networks. Planning permission is being sought for a duration of 10-years.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Dublin City Council grants permission for battery energy storage plant at Dubli, Dublin", 28 August 2025. https://www.permission.ie/news/dublin-city-council/WEB2226%2F25

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/dublin-city-council/WEB2226%2F25">Dublin City Council grants permission for battery energy storage plant at Dubli, Dublin</a>, Permission.ie analysis of the national planning register, 28 August 2025.</p>
Full application record

Map, site boundary, timeline and nearby applications for WEB2226/25.

Dublin planning register

Every application lodged in Dublin, updated daily.

Get stories like this the day they are lodged

A county watch emails you every new application in Dublin the week it appears.

Set up alerts
Dublin City Council grants permission for battery energy storage plant at Dubli, Dublin | Permission.ie