Battery storageLodgedDublin
Battery energy storage plant proposed at Newtown, North Road, Co. Dublin
21 September 2026 · Permission.ie Planning Wire · from the Fingal County Council planning register
Coldwinters Energy Limited lodged plans with Fingal County Council on 21 September 2026 for a battery energy storage plant at Newtown, North Road. The application seeks an operational life of 40 years. Submissions from the public can be made until 25 October 2026, and a decision is due by 13 November 2026.
Live from the council register. This application was read from Fingal County Council’s own register the day it was listed. It has not yet reached the national planning dataset, which runs one to five weeks behind; the full record page, map and site boundary will appear here when it does.
Key facts
- Reference
- FW26A/0358E
- Planning authority
- Fingal County Council
- Location
- Newtown, North Road, Co. Dublin
- Applicant
- Coldwinters Energy Limited
- Received
- 21 September 2026
- Application type
- Permission
- Operational life
- 40 years
- Status
- Registered
- Decision due
- 13 November 2026
- Submissions until
- 25 October 2026
In context
There were 58 nationally in the past twelve months. Of the 70 such applications decided by councils in the past three years, 79% were granted.
What happens next
Anyone can make a submission or observation to Fingal County Council until 25 October 2026, for a fee of €20. Only those who make a submission can later appeal the decision. The council is due to decide by 13 November 2026, unless it requests further information, which stops the clock.
The development description, as lodged
Verbatim from the Fingal County Council register. This is the source for every figure in the story above.
The construction, operation and decommissioning of a battery energy storage system (BESS), that comprises of one of three battery technology options (Technology Option 1, Technology Option 2 or Technology Option 3). The technology options for the Project comprise of the following parameters: • Technology Option 1: 18 BESS units (4.2 m H × 2.7 m W × 7.6 m L); 9 MV stations (2.8 m H × 2.2 m W × 8.6 m L); Design Layout 1 (Drawing No. 24052-202). • Technology Option 2: 18 BESS units (4.2 m H × 2.5 m W × 6.1 m L); 9 MV stations (2.9 m H × 2.5 m W × 6.1 m L); Design Layout 2 (Drawing No. 24052-203). • Technology Option 3: 16 BESS units (3.2 m H × 2.5 m W × 6.1 m L); 2 MV stations (2.9 m H × 2.5 m W × 12.2 m L); Design Layout 3 (Drawing No. 24052-204) Construction elements for the proposed project include: • Site access track, hardstanding area, foundations for the Battery Energy Storage System (BESS) and Medium Voltage (MV) stations, BESS switch room building, control building, welfare and spare parts building, 38kV transformer and associated bund, earth and Low Voltage (LV) transformer, Distribution System Operator (DSO) substation, associated drainage infrastructure, and all ancillary works; • Installation of BESS units and MV stations; installation of underground power and communications cables between the BESS, MV stations, DSO substation, and control building; • Construction, use, and decommissioning of a temporary site compound to facilitate the works, along with the construction of a new site entrance; • Provision of a grid connection route from the DSO substation to the Finglas 220/38kV substation; and • All associated site works, including site clearance, ancillary development (such as site drainage), installation of security gates and fencing, permanent and temporary signage. The proposed site will be used as a single purpose site as a BESS facility, supporting the decarbonisation of the electrical grid. Permission is sought for the proposed development for a period of 10 years, with an operational period of 40 years.
Cite this story
Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.
Source: Permission.ie analysis of the national planning register, "Battery energy storage plant proposed at Newtown, North Road, Co. Dublin", 21 September 2026. https://www.permission.ie/news/fingal-county-council/FW26A%2F0358E
<p>Source: <a href="https://www.permission.ie/news/fingal-county-council/FW26A%2F0358E">Battery energy storage plant proposed at Newtown, North Road, Co. Dublin</a>, Permission.ie analysis of the national planning register, 21 September 2026.</p>
The Fingal County Council record for FW26A/0358E, with documents and drawings as lodged.
Dublin planning registerEvery application lodged in Dublin, updated daily.
Get stories like this the day they are lodged
A county watch emails you every new application in Dublin the week it appears.
Set up alerts