← Planning Wire · Galway County Council news

Battery storageDecisionGalway

Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, Ireland, Co. Galway

22 January 2024 · Permission.ie Planning Wire · from the Galway County Council planning register · published 1 September 2026

Galway County Council granted permission on 22 January 2024 for a 240 MW / 240 MWh battery storage plant at Somerset, Ireland, an application first lodged on 21 July 2023.

Key facts

Reference
2360827
Planning authority
Galway County Council
Location
Somerset, Co. Galway, Ireland
Received
21 July 2023
Application type
PERMISSION
Site area
3 hectares
Stated capacity
240 MW
Storage capacity
240 MWh
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
22 January 2024

In context

It is one of 3 battery storage applications Galway County Council has received in the past twelve months, against 60 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 22 January 2024. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Galway County Council register. This is the source for every figure in the story above.

to include development of a 240MWh battery energy storage systems facility within a total site area of up to 3.02 hectares, the site will include 1no. 38KV substation compound including 1no. single storey electrical substation building with an area of 69m2 & associated switchgear, 12no. electrical inverters & 6no. electrical transformer, 31no. containerised battery storage modules on concrete plinths, access tracks & new site entrance, associated electrical cabling & ducting, security gates, perimeter security fencing, CCTV security monitoring & lighting system, landscaping works & all associated ancillary infrastructure

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, Ireland, Co. Galway", 22 January 2024. https://www.permission.ie/news/galway-county-council/2360827

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/galway-county-council/2360827">Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, Ireland, Co. Galway</a>, Permission.ie analysis of the national planning register, 22 January 2024.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2360827.

Galway planning register

Every application lodged in Galway, updated daily.

Get stories like this the day they are lodged

A county watch emails you every new application in Galway the week it appears.

Set up alerts