← Planning Wire

Battery storageDecisionGalway

Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, IRELAND, Co. Galway

29 July 2026 · Permission.ie Planning Wire · from the Galway County Council planning register · published 1 September 2026

Galway County Council granted permission on 29 July 2026 for a 240 MW / 240 MWh battery storage plant at Somerset, IRELAND, an application first lodged on 4 June 2026.

Key facts

Reference
2660898
Planning authority
Galway County Council
Location
Somerset, CO GALWAY, IRELAND
Received
4 June 2026
Application type
PERMISSION
Site area
3 hectares
Stated capacity
240 MW
Storage capacity
240 MWh
Permission sought
10 years
Status
DECISION MADE
Decision
CONDITIONAL
Decision date
29 July 2026

In context

It is one of 3 battery storage applications Galway County Council has received in the past twelve months, against 59 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 29 July 2026. If no appeal is lodged, the council’s decision stands and a final grant issues. The applicant sought a 10-year permission, which sets how long they have to start the development.

The development description, as lodged

Verbatim from the Galway County Council register. This is the source for every figure in the story above.

for a 10-year planning permission. The development will consist of a 240MWh Battery Energy Storage Systems facility within a total site area of up to 3.02 hectares. The development will include: 1No. 38kV Substation Compound including 1No. Single Storey electrical Substation Building with an area of 69m2 and Associated Switchgear, 12 No. Electrical Inverters, and 6 No. Electrical Transformers, 31 No. Containerised Battery Storage Modules on Concrete Plinths, Access Tracks and new Site Entrance, Associated Electrical Cabling and Ducting, Security Gates, Perimeter Security Fencing, CCTV Security Monitoring and Lighting System, Landscaping Works and all Associated Ancillary Infrastructure.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, IRELAND, Co. Galway", 29 July 2026. https://www.permission.ie/news/galway-county-council/2660898

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/galway-county-council/2660898">Galway County Council grants permission for 240 MW / 240 MWh battery storage plant at Somerset, IRELAND, Co. Galway</a>, Permission.ie analysis of the national planning register, 29 July 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2660898.

Galway planning register

Every application lodged in Galway, updated daily.

Get stories like this the day they are lodged

A county watch emails you every new application in Galway the week it appears.

Set up alerts