Battery storageDecisionMayo

Mayo County Council grants permission for battery energy storage plant at Aghalusky, Castlebar, Co. Mayo

12 March 2026 · Permission.ie Planning Wire · from the Mayo County Council planning register · published 1 September 2026

Mayo County Council granted permission on 12 March 2026 for a battery energy storage plant at Aghalusky, Castlebar, an application first lodged on 17 November 2025.

Key facts

Reference
2560820
Planning authority
Mayo County Council
Location
Aghalusky, Castlebar, Mayo
Received
17 November 2025
Application type
PERMISSION
Site area
0.9 hectares
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision date
12 March 2026

In context

It is one of 4 battery storage applications Mayo County Council has received in the past twelve months, against 59 nationally. Of the 72 such applications decided by councils in the past three years, 78% were granted.

What happens next

The applicant, or anyone who made a submission on the application, can appeal the decision to An Coimisiún Pleanála within four weeks of 12 March 2026. If no appeal is lodged, the council’s decision stands and a final grant issues.

The development description, as lodged

Verbatim from the Mayo County Council register. This is the source for every figure in the story above.

The proposed development which will consist of the following elements: the installation and operation of 1no. battery energy storage system compound containing battery energy storage containers, 1no. electrical substation and compound, connected to the national grid system via c. 50m of underground cable to the ESB Castlebar 38kV substation, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road, associated ancillary site development, landscaping and reinstatement works. The operational lifespan of the development will be 35 years. The site of the proposed development has a total area of 0.89 hectares.

Cite this story

Free to quote, reproduce and republish with attribution (CC BY 4.0). Every figure on this page is traceable to the council record linked above; please link to this page so readers can check it too.

For print or broadcast

Source: Permission.ie analysis of the national planning register, "Mayo County Council grants permission for battery energy storage plant at Aghalusky, Castlebar, Co. Mayo", 12 March 2026. https://www.permission.ie/news/mayo-county-council/2560820

For the web (with link)
<p>Source: <a href="https://www.permission.ie/news/mayo-county-council/2560820">Mayo County Council grants permission for battery energy storage plant at Aghalusky, Castlebar, Co. Mayo</a>, Permission.ie analysis of the national planning register, 12 March 2026.</p>
Full application record

Map, site boundary, timeline and nearby applications for 2560820.

Mayo planning register

Every application lodged in Mayo, updated daily.

Get stories like this the day they are lodged

A county watch emails you every new application in Mayo the week it appears.

Set up alerts
Mayo County Council grants permission for battery energy storage plant at Aghalusky, Castlebar, Co. Mayo | Permission.ie