Planning application 03/4726

Cork - Cork County Council

Proposed Development

Upgrade of electrical equipment in the existing 110kv compound,installation of 2no. replacement transformers & equipment in new compound

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    19 Sept 2003

  2. Decision: CONDITIONAL

    4 Nov 2003

  3. Decision due

    13 Nov 2003

  4. Grant issued

    10 Dec 2003

Application Details

Location
CORKBEG, CORKBEG,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
19 September 2003
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
4 November 2003
Grant Date
10 December 2003

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

165m
03/5609CONDITIONAL12 Nov 2003

Installation of a replacement flare tower of 51m in height

Corkbeg Whitegate Co. Cork

266m
17/4344CONDITIONAL17 Feb 2017

Construction of a new steel distillation column T204N of height 38 metres above ground level and 1.2 metres in diameter, to improve Propane and Butane product quality. The column will be provided with steel access platforms and pipework connections to existing facilities. The column will be placed on a new concrete foundation at ground level, with surface water drainage routed to existing facilities. There will be no continuous emissions from the column.

Corkbeg Whitegate Midleton Co. Cork

278m
03/2301CONDITIONAL15 May 2003

See application for details

CORKBEG, CORKBEG,

333m
08/8727CONDITIONAL3 Sept 2008

Construction of 1 no. stainless steel column T302N of which 51m will be above ground (including pipework), approx 1.4m diameter at upper part and 2.06m diameter at lower part

Corkbeg Whitegate

348m
13/5464CONDITIONAL29 Jul 2013

36m multi-user support structure (to replace existing temporary mobile structure), carrying associated telecommunications equipment, associated equipments cabins, all within secure compound, including access track. The development will form part of Vodafone Ireland Ltd’s existing GSM and 3G Broadband telecommunications network

Ballytigeen Whitegate Co.Cork

364m
18/4266INCOMPLETED APPLICATION2 Feb 2018

Heavy Atmosphere Gas Oil (HAGO) project located within the existing Whitegate Oil refinery. The proposed HAGO development principally comprises 35m high reactor and a 27m high vacuum column. It will be provided with steel access platforms and pipework connections to existing facilities. A new remote instrument building that stores the control hardware will also be included. The proposed HAGO development will be placed on a concrete foundation at ground level, with surface water drainage routed to existing facilities. There will be no continuous emissions from the proposed development. The proposed development is for the purposes of an activity which holds an existing Industrial Emissions Licence. The proposed development relates to modifications to an establishment within the meaning of Part 11 (Major Accidents Directive) of the Planning and Development Regulations, 2001, as amended.

Corkbeg Whitegate Midleton Co Cork

366m
23/6011CONDITIONAL5 Oct 2023

Permission for construction of a machinery/straw storage shed and associated site works

Ballytigeen Whitegate Co.Cork

366m
18/4725CONDITIONAL23 Mar 2018

Heavy Atmospheric Gas Oil (HAGO) project located within the Whitegate Oil Refinery. The proposed HAGO development principally comprises a 35m high steel reactor and a 27m high steel vacuum column. It will be provided with steel access platforms and pipework connections to existing facilities. A new remote instrument building that stores the control hardware will also be included. The proposed HAGO development will be placed on a concrete foundation at ground level, with surface water drainage routed to existing facilities. There will be no continuous emissions from the proposed development. The proposed development is for the purposes of an activity which holds an existing Industrial Emissions Licence. The proposed development relates to modifications to an establishment within the meaning of Part 11 (Major Accidents Directive) of Planning and Development Regulations, 2001 as amended.

Corkbeg Whitegate Midleton Co. Cork

394m
20/4268CONDITIONAL13 Feb 2020

Construction of a machinery/straw storage shed and associated site works.

Ballytigeen Whitegate Co. Cork

396m
10/8114CONDITIONAL4 Oct 2010

Construction of a new Amine and Sulphuric Acid Plant consisting of a 28 metre high (including pipework) above ground level open steel structure incorporating an exhaust stack of 40 metres height above ground level and a stand-alone aluminium clad steel tower, T-1003, 30metres in height (including pipework) above ground level. The proposed development is for the purposes of an activity which requires an integrated pollution prevention and control licence. The proposed development relates to modifications to an establishment within the meaning of Part 11 of thses Regulations (Major Accident Directive)