Application Timeline
Application received
6 Dec 2004
Decision: CONDITIONAL
3 Feb 2005
Decision due
8 Feb 2005
Grant issued
11 Mar 2005
Application Details
- Location
- Farranavarrigane Macroom
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 6 December 2004Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 February 2005
- Grant Date
- 11 March 2005
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Dwellinghouse
Inchinashingane Macroom
Permission to carry out the following on the site of their existing baby food production facility. Permission for (1) Construction of a new hardstanding compound to the north of the existing 38Kva substation. The compound to be secured with 2.9m high palisade fence, (2) Installation of 5MW (5x1MW) of hydrotreated vegetable oil (HVO) stationary standby generators for emergency electricity generation, each generator is enclosed in a weatherproof container (2.8m high x 0.8m Long x 5.0m wide). (3) Installation of 2 no. transformers within the compound and associated cabling. (4) Extension to the existing concrete roadway to access the compound. (5) All associated site works. The development relates to an activity in relation to which a revised Integrated Pollution Prevention and Control Licence is required
Inchinashingane Macroom Co. Cork
Alterations & extension to garage (including raising of roof pitch), and retention of first floor dormer windows to front of dwelling
Inchinashingane Macroom
Extension to the existing timber frame building manufacturing facility, for the purpose of timber frame building manufacturing and storage
IDA Industrial Estate Coolcour Macroom Co. Cork
Factory building with offices and dispatch area to manufacture timber framed buildings including site develoment works, services and construction of access road
Coolcour Macroom
Permission for the construction of an extension of area approx. 5,122 sq.metres to the existing manufacturing building, and the construction of a canopy of area approx. 1,188 sq.metres over vehicle parking area at east side of proposed extension, and vehicular parking, and all ancillary services and associated site works to the existing timber frame building manufacturing facility.
Cygnum Timber Frame Ltd IDA Industrial Estate Coolcour Macroom Co Cork
The construction of an Extension to the existing Timber Frame Building Manufacturing Facility, for the purpose of Timber Frame Building Manufacturing and Storage.
IDA Industiral Estate Coolcour Macroom Co. Cork
Construction of an extension to the existing timber frame building manufacturing facility, for the purpose of timber frame building manufacturing and storage
IDA Industrial Estate Coolcour Macroom, Co Cork P12 P623
Permission for the installation of rooftop photovoltaic solar panel arrays consisting of approximately 1,000 square metres of solar panels on the eastern roof slopes, and approximately 1,000 square metres of solar panels on the western roof slopes of the existing manufacturing building, and all ancillary services and associated site works.
IDA Industrial Estate Coolcour Macroom Co. Cork
Permission for the installation of rooftop photovoltaic solar panel array consisting of approximately 1,000 square meters of solar panels on the eastern roof slopes, and approximately 1,000 square meters of solar panels on the western roof slopes of the existing building, and all ancillary services and associated site works
IDA Industrial Estate Coolcour Macroom Co.Cork